8. AYALA LAND,INC. began work on a P70 million contract in 2019 to construct an office building. During 2019, LPB uses the percentage of completion method. At 12/31/2019, the balance in certain accounts were ; construction in process, P 24.5 million; accounts receivable P 2.4 million; and billings on construction in process, P 12 million. At 12/31/2019, the estimated future costs to complete the project total P3.85 million. Prepare the entry to record the income from construction recognized in year 2019. a. Construction in Progress Construction Costs P 7,350,000 24,500,000 Construction revenue P31, 850,000 b. Construction in Progress P 7,350,000 17,150,000 Construction Costs Construction revenue C. Construction Costs P24, 500,000 P24,500,000 Construction in Progress Construction revenue P 7,350,000 17,150,000 d. Construction Costs P31,850,000 Construction revenue P24, 500,000

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 6P
icon
Related questions
Question
100%
Please refer to the picture below to answer the question. Question: What is the journal entry to record the income from construction recognized in year 2019?
8. AYALA LAND, INC. began work on a P70 million contract in 2019 to construct an
office building. During 2019, LPB uses the percentage of completion method. At
12/31/2019, the balance in certain accounts were ; construction in process, P
24.5 million; accounts receivable P 2.4 million; and billings on construction in
process, P 12 million. At 12/31/2019, the estimated future costs to complete the
project total P3.85 million.
Prepare the entry to record the income from construction recognized in year
2019.
a. Construction in Progress
Construction Costs
Construction revenue
b. Construction in Progress
P 7,350,000
24,500,000
P31, 850,000
P 7,350,000
17,150,000
Construction Costs
Construction revenue
C. Construction Costs
P24, 500,000
P24,500,000
Construction in Progress
Construction revenue
P 7,350,000
17,150,000
d. Construction Costs
Construction revenue
Construction in Progress
P31,850,000
P24, 500,000
7,350,000
Transcribed Image Text:8. AYALA LAND, INC. began work on a P70 million contract in 2019 to construct an office building. During 2019, LPB uses the percentage of completion method. At 12/31/2019, the balance in certain accounts were ; construction in process, P 24.5 million; accounts receivable P 2.4 million; and billings on construction in process, P 12 million. At 12/31/2019, the estimated future costs to complete the project total P3.85 million. Prepare the entry to record the income from construction recognized in year 2019. a. Construction in Progress Construction Costs Construction revenue b. Construction in Progress P 7,350,000 24,500,000 P31, 850,000 P 7,350,000 17,150,000 Construction Costs Construction revenue C. Construction Costs P24, 500,000 P24,500,000 Construction in Progress Construction revenue P 7,350,000 17,150,000 d. Construction Costs Construction revenue Construction in Progress P31,850,000 P24, 500,000 7,350,000
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
SWFT Comprehensive Vol 2020
SWFT Comprehensive Vol 2020
Accounting
ISBN:
9780357391723
Author:
Maloney
Publisher:
Cengage