1. Organize the infomation above in an activity precedence table showing the activity, precedent and duration (calculated using the PERT weighted average formula and round to the nearest integer).
Q: 4. Schedules and activities of a project are shown below. Answer the questions. Activity…
A: A) The CPM chart is as follows: The critical path is: A-D-E-H-I-L
Q: The nine activities A to I whích make up a project are subject to the following precedence…
A: Disclaimer- Since you have posted a question with multiple sub parts , we will solve first three sub…
Q: A project for improving a billing process has the following precedence relationships and activity…
A:
Q: The new director of special events at a large university has decided to completely revamp graduation…
A: Given data is
Q: The figure shows the network diagram of a project along with the activity durations (T). In this…
A: A project schedule network diagram shows the sequential and analytical connection between tasks in a…
Q: The activities described by the following table are given for the Howard Corporation in Kansas Time…
A: This question is related to the topic Project Management and This topic falls under Operations…
Q: Consider following data. Draw activity on arc (AOA) network diagram. Find out critical path,…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: 1. Organize the information above in an activity precedence table showing the activity, precedent…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: activities, define the located activities on the critical path, define the total project duration,…
A: Find the Given details below: Activity Precedent Activity Time (Week) A - 7 B - 5 C B, E…
Q: I need help for number 12, please. Based on question number 11, which I already know the answer,…
A:
Q: Before answering the following questions, you must draw the arrow diagram, rectangles, network…
A: Given data is
Q: Suppose you have a project with a Budget at Completion (BAC) of $250,000 and a projected length of…
A: Given, Budget at Completion (BAC) of $250,000 Time- 10 months
Q: Construct a Gantt chart for the following set of activities and indicate the project completion…
A:
Q: The first question: The part of a construction project whose activities are shown in Table No. 1…
A:
Q: Given the activities whose sequence is described by thefol lowing table, draw the appropriate…
A: Critical path refers to the stage sequences, that require maximum time for the project completion.
Q: Prepare an arrow diagram and a list of earliest and latest starts and finishes , the tota float and…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: Q4. Answer the following questions (a-h), based on the provided project Gantt Chart. The red line…
A: Note: Since you have posted a question with multiple sub-parts, we will solve first four sub-parts…
Q: 1. Alpha Team received an assignment from the Company to work on a bridge construction project. Budi…
A: ES -Early start time LS - Late start time EF - Early finish time LF - Late finish time ES =…
Q: A project manager has compiled a list of major activities that will be required to install a…
A:
Q: Construct a Network Diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequence of the task that is performed to complete a…
Q: I need a detailed explanation and assistance to solve this problem: A company decides to plan a…
A: Drawing the project network as shown in the diagram using AOA convention we represent the activities…
Q: Construct a CPM network based on activity on node method with the details given below and find the…
A: Given information, Activity Immediate Predecessor Duration A 1 B A 4 C A 2 D A 2 E…
Q: accompanying Table 1 shows the activities, times and sequences required for the project planning and…
A: the critical path is a step by step technique to identify the critical activities in the project.…
Q: (i) Construct a network diagram showing the various logical activity relationships from this…
A: For each activity, we have immediate predecessor data and Time in days, using the above table,…
Q: Activity Preceding Activity Expected Completion Time (in Weeks) A None B A 2 A D B 12 E D 10 F 9 D H…
A: Activity Immediate Predecessors Duration A - 5 B A 2 C A 6 D B…
Q: a) The expected (estimated) time for activity C is 12.00 weeks. (Round your response to two decimal…
A: To determine the Estimated time for any activity, we would use the below formula, the expected time…
Q: Ann's team is documenting activity attributes for each schedule activity. What attributes should be…
A: Activity attributes refers to the descriptive components of any activity. These attributes include…
Q: 5. Construct an activity-on-arrow precedence diagram for each of the following cases. Note that each…
A: The project network is the visual representation of the project activities and their durations to…
Q: Project Planning Practice Draw or make a Gantt Chart for the following Activities Draw or make…
A:
Q: Table 1 Time (In Days) 9. Activities Immediate Predecessors A -- В A 5 A 9 B,C E В, С 7 F D 10 G E…
A: There are following table shows the activities, times and sequences required for the project…
Q: an the following table the activities with their precedence sequence and expected time (days) are…
A: Network Diagram :
Q: (a). Draw the Activity on Node (AoN) network diagram. (b). Find the critical path and write that…
A: Below is the solution:-
Q: Before answering the following questions, you must draw the arrow diagram, rectangles, network…
A:
Q: Before answering the following questions, you must draw the arrow diagram, rectangles, network…
A: Find the given details below: Activity Dependency Optimistic Time(To) a(Weeks) Pessimistic…
Q: a. Prepare/draw a full Gantt Chart as at end of Week 5. b. Calculate and indicate the missing (?)…
A: Part a:
Q: (i) Construct a Network Diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequential and analytical relationship between tasks in…
Q: 2. Draw an AON network diagram and calculate its early start, early finish, late start and late…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: The following CPM/PERT network represents a small project with 4 activities labelled A through D.…
A: Given data is
Q: A renovation of the gift shop at Orlando Amway Center has six activities (in hours). In the…
A: Programme Evaluation and Review Technique(PERT) is a probabilistic technique, where an activity time…
Q: A network consists of the activities in the following list. Times are gi Activity Preceding Time А 8…
A: Network Diagram-
Q: the network consists of the following list. Times are given in week. 1. draw the network diagram.…
A: Given data, Activity Preceding Optimistic Probable Pessimistic A -- 5 11 14 B -- 3 3 9 C --…
Q: Project Management In the below Precedence Diagram ( The activities durations are in weeks ) If…
A: Here, in the question, we have Network diagram, for each activity node, I have following data like…
Q: Questions 1. Organize the information above in an activity precedence table showing the activity,…
A: Answer of all pats are below:-
Q: Given the network plan that follows, compute the early, late, and slack times. What is the project…
A:
Q: What is the expected completion time? What is the critical path? What is the latest that Jersey…
A: A network diagram is visual diagram of activity relationship in a project which helps to identify…
Q: In reference to the attached activity precedence diagram and activity times shown. (Feel free to…
A: Slack time = Slack time is the time by which a activity can be delayed , without delaying the over…
Q: • Draw the Network diagram. • Calculate expected time and variance for each activity. • Find the…
A: Let: a= OPTIMISTIC TIME b= PESSIMISTIC TIME m= MOST LIKELY TIME Te = EXPECTED TIME = (a+4m+b)/6…
Q: The following is NOT one of the advantages of CPM and PERT: a) Straightforward concept and not…
A: Option A is incorrect Project management and review techniques often called the PERT approach and…
Step by step
Solved in 2 steps with 4 images
- Farihah is a project manager for a systems development project involving a new database application for her organization’s human resources department. Despite Farihah’s best efforts at estimating the time requirements for the project, the team has missed the deadline for completing the Analysis Phase and producing the System Proposal. Farihah had estimated during her 6-week Planning Phase that Analysis would require 2 months, but the team finished the System Proposal 2 weeks behind their planned target date. Based on her discussions with the team members, Farihah believes that the system is more complex than she originally thought. Should Farihah adjust her timeline, or can she try to make up for the lost two weeks? Farihah needs your advice.B/U pe Activity A B D 11. A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $4,000 per week for every week the project exceeds 37 weeks. What is the lowest total cost for completing this project? Predecessor Time 18 11 A A B C E D Normal A H 12 15 3 19 Asbe de ABC' AMBBC RACE AB 7 8 12 6 Normal Cost Crash Time Crash Cost $22,000 $32,000 $62,000 $18,000 $35,000 $8,000 $23,000 $32,000 $56,000 $12,000 5 $18,000 19 $22,000 $9,000 $15,000 $5,000 $13,000 $20,000 $45,000 2 5 4What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Cost $800 $200 $600 $750 $1,200 Normal Crash Activity Time (days) Time (days) 4 3 8 6 The total cost of crashing the project by 4 days is $ ABCDE 487 355 (Enter your response as a whole number.) Total Cost with Crashing Immediate Predecessor(s) $1,500 $1,650 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) Each Activity Should be Reduced BY (days) Activity A B C D E $1,100 $600 $650 A C
- You are in charge of a project at the local community center. The center needs to remodel one ofthe rooms in time for the start of a new program. Delays in the project mean that the center mustrent other space at a nearby church at additional cost. Time and cost data for your project arecontained in below table. Your interest is in minimizing the cost of the project to the communitycenter.Using the normal times for each activity, what is the earliest date you can complete the project?Suppose the variable overhead costs are $50 per day for your project. Also, suppose that thecenter must pay $40 per day for a temporary room on day 15 or beyond. Find the minimum-costproject schedule using below format.The AON diagram for the community center project is below. Crash 4 times and find total cost.A company is willing to develop their rocket before the end of current financial year which is now 28 weeks away. The chief engineer of the company has decided to use PERT technique in order to plan, schedule and control program of development for the data given in table below. What is the probability that the program will be completed by the end of the current financial year? (all durations are in weeks). (i) G) Optimum Duration Most likely duration Pesimistic duration 1 2 3 8 13 3 2 8 4 3 8 10 4 7 10 3 6. 3 8 4 9 10 4 8. 4 9. 5 7 9. 12 6. 5 11 7 9. 14 8 4. 00 2.PROJECT PLANNING & SCHEDULING WITH GANNT CHART Given the activities of a project; their optimistic (to), most likely (tm) and pessimistic(tp) time estimates; and their immediate predecessors shown below:1. When is the earliest project completion?2. Which activities are critical (should not be delayed)?3. Which activities are noncritical (can be delayed)?4. How long can each of the activities be delayed without delaying the wholeproject (maximum slack)? Activities Activity Times,months ImmediatePredecessors Maximum Slack,months A 2 - B 3 - C 2 A D 4 B E 4 C F 3 C G 5 D, E H 2 F, G
- The table below contains data for the installation of new equipment in a manufacturing process for a steel corporation. Your company is responsible for the installation project. Indirect costs are $6,000 per week, and a penalty cost of $10,000 per week will be incurred by your company for every week the project is delayed beyond week 15. Activity Immediate Predecessor(s) Normal Time (weeks) Crash Time (weeks) Normal Cost ($) Crash Cost ($) A None 2 1 7,000 10,000 B None 2 2 3,000 3,000 C A 3 1 12,000 40,000 D B 3 2 12,000 28,000 E C 1 1 8,000 8,000 F D, E 5 3 5,000 15,000 G E 3 2 9,000 18,000 H F, G 8 6 14,000 32,000 Construct a network diagram for the project. What are the project completion time and the total cost under normal conditions? What is the shortest time duration for this project regardless of cost? What is the resulting total cost? What is the…What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Crash Normal Activity Time (days) Time (days) Normal Cost A 5 4 B 9 7 C 6 5 D 7 5 E 7 4 Total Cost with Crashing Immediate Predecessor(s) $800 $300 $600 $750 $1,200 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) Each Activity Should be Reduced BY (days) Activity A B C D E $1,100 $400 $650 $1,500 $1,650 | | | < 0The MXN Sdn. Bhd. has identified eight activities that would need to be implemented in order to complete the construction project as listed in the table below. Using the PERT three-estimate approach, the company has obtained the estimated duration and the precedence relationships for each activity. In addition, the company may get penalized if it fails to complete the project within 35 weeks. Activity A B с D E F G H Immediate predecessor(s) None A A None B,C C,D Table 2: Project Description D, F E, G Optimistic 2 7 4 7 3 2 Time estimate (week) SKT AM X Most likely m 6 8 13 7 9 6 Pessimistic b 7 16 13 17 9 9 (a) Construct the activity on the node (AON) network for this project. (b) Compute the expected activity time and the variance for each activity. termine the forward and backward pass, activity slack, and identify the critical path. Estimate the probability that all the activities on the current critical path will be completed within 35 weeks. (e) Estimate the probability that the…
- Mangement Project management is a discipline that involves planning, organizing, and overseeing the execution of a project from initiation to completion. It encompasses defining project goals, outlining tasks, allocating resources, and managing budgets and timelines. A successful project manager must possess strong leadership skills, effective communication, and the ability to mitigate risks and solve problems efficiently. Collaboration among team members is crucial, as is the flexibility to adapt to unexpected challenges that may arise during the project lifecycle. Continuous monitoring and evaluation ensure that the project stays on track, meeting objectives and delivering value to stakeholders. Question: How can project managers encourage effective collaboration and communication among team members to ensure the successful and timely completion of a project?What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Crash Activity Time (days) Time (days) A B C D E 580 4 (O ∞ 6 8 4 6 3 4 5 Normal Cost Activity A B C D E $800 $200 $600 $750 $1,200 Total Cost with Crashing Immediate Predecessor(s) $1,100 $500 $650 The total cost of crashing the project by 4 days is $ $1,500 $1,650 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the tab below. (Enter your responses as whole numbers.) Each Activity Should be Reduced BY (days) 1 0 1 2 3 | | | < 0 (Enter your response as a whole number.)What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Crash Time Activity Time (days) (days) AB А C D E 67555 5 BCD w 55 с 4 2 Activity A E 3 Normal Cost $800 $300 $600 $750 $1,200 Immediate Total Cost with Crashing Predecessor(s) $1,100 $500 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) $650 $1,500 $1,650 - Each Activity Should be Reduced BY (days) A C