The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: Code A B C D E F G H I D Description Find location; determine resource requirements Requisition of lumber and sand Dig and grade Saw lumber into appropriate sizes Position lumber in correct locations Nail lumber together Put sand in and under the equipment Put dirt around the equipment Put grass all over the garden, landscape, paint Time (hrs) 25 65 100 25 20 15 20 5 35 Immediate Predecessor(s) Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activities E through I of the project. None A A B D, C E F F G, H A- B- C- D- E- F- G- H- 0 20 40 60 80 100 120 140 160 180 200 220

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter5: Network Models
Section5.3: Assignment Models
Problem 18P
icon
Related questions
Question
The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for
the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is
as follows:
Code
A
BC
с
D
Description
Find location; determine resource requirements
Requisition of lumber and sand
EFGH-
Time
(hrs)
25
65
100
25
20
15
20
5
35
Dig and grade
Saw lumber into appropriate sizes
Position lumber in correct locations
Nail lumber together
Put sand in and under the equipment
Put dirt around the equipment
Put grass all over the garden, landscape, paint
Refer to the legend for the activity that corresponds to each code.
Using the line drawing tool, draw a Gantt chart for activities E through I of the project.
Immediate Predecessor(s)
None
A
A
B
D, C
E
F
F
G, H
C
A-
B-
D
E-
F-
G-
H-
9
0 20 40 60 80 100 120 140 160 180 200 220
Q
N
Transcribed Image Text:The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: Code A BC с D Description Find location; determine resource requirements Requisition of lumber and sand EFGH- Time (hrs) 25 65 100 25 20 15 20 5 35 Dig and grade Saw lumber into appropriate sizes Position lumber in correct locations Nail lumber together Put sand in and under the equipment Put dirt around the equipment Put grass all over the garden, landscape, paint Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activities E through I of the project. Immediate Predecessor(s) None A A B D, C E F F G, H C A- B- D E- F- G- H- 9 0 20 40 60 80 100 120 140 160 180 200 220 Q N
te
od
ed
ner
ΦΦ
len
со
htt
Imount
Legend
READ MO
P
Inel La
CALELER
€
Code
ABCDWLOI –
А
G
H
Print
Activity
Planning
Purchasing
Excavation
Sawing
Placement
Assembly
Infill
Outfill
Decoration
Done
O
X
Transcribed Image Text:te od ed ner ΦΦ len со htt Imount Legend READ MO P Inel La CALELER € Code ABCDWLOI – А G H Print Activity Planning Purchasing Excavation Sawing Placement Assembly Infill Outfill Decoration Done O X
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 6 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,