XYZ Corporation operates two plants, each of which has a capacity of 170 units per day. Each day, XYZ must ship their product to each of four customers. Customers A, B, and C each have a demand of 12 units per day while customer D has a demand of 304 units per day. The cost of shipping one unit of each product from each of the two plants to each of the customers is shown in the table below. Customer A Customer B Customer c Customer D Plant 1 20 15 14 24 Plant 2 25 25 23 19 a. How many units should XYZ ship from each plant to each customer? (Leave no cells blank-be certain to enter "O" wherever required. Round your answer to the nearest whole number.) Customer A Customer B Customer C Customer D Plant 1 Plant 2
Q: 24. Powerco has three electric power plants that supply the needs of four cities. Each power plant…
A:
Q: GulfOil Company (GOC) can buy two types of crude oil: light oil at $49/barrel and heavy oil…
A: Given data is
Q: The Ottery Creek Winery produces three kinds of table wine - a blush, a white, and a red. The winery…
A: Given Information:
Q: The Copperfield Mining Company owns two mines, which produce three grades of ore: high, medium, and…
A: Objective Functions and Constraints: Based on the given details, we found the…
Q: Ewing Oil has oil fields in San Diego and Los Angeles. The San Diego field can produce up to 500,000…
A: SD = San Diego LA = Los Angeles D = Dallas H = Houston C = Chicago N = New York
Q: HEAVYLOAD INC has 3 resources (Resource A, Resource B and Resource C) in its production process. The…
A: Given data The numbers of demand for all the 3 resources are as follows. A=700 B= 1000 C=200…
Q: City 1 produces 500 tons of waste per day, city 2 produces 400 tons of waste per day, and city 3…
A: Let considered be the tons of city waste that is sent to incinerator, for. Let…
Q: Irwin Textile Mills produces two types of cotton cloth—denim and corduroy. Corduroy is a heavier…
A: Let Denim = X1 and Corduroy = X2 Maximize profit = 2.25 X1 + 3.10 X2 subject to 5 X1 + 7.5 X2…
Q: A car dealer has warehouses in Millville and Trenton and dealerships in Camden and Atlantic City.…
A:
Q: Universal Claims Processors processes insurance claims for large national insurance companies. Most…
A: It is a linear programming problem where the objective function of the firm is to minimize or…
Q: A food wholesaler has three kinds of individual bags of potato chips: regular, barbeque, and salt…
A: Simplex method is one of the most used techniques in linear programming. A problem can be solved…
Q: A factory is to produce two products P1 and P2. The products require machining on two critical…
A: Given data in tabular form : P1 P2 available time Overtime profit M1 5 4 120 50 8 on…
Q: Mackk Engine produces diesel trucks. New government emission standards have dictated that the…
A: Given information: Type 1 truck Sell = $50,000 Costs = $38000 Pollution Emits =…
Q: Ewing Oil has oil fields in San Diego and Los Angeles. The San Diego field can produce up to 500,000…
A: Network Diagram from given data: SD = San Diego LA = Los Angeles D = Dallas H = Huston C = Chicago…
Q: Each day, workers at an emergency department work two 6-hour shifts chosen from 12 A.M. to 6 A.M., 6…
A: Given data, The different shift 1) 12 A.M to 6 A.M 2) 6 A.M to 12 P.M 3) 12 P.M to 6 P.M 4) 6 P.M…
Q: An airline needs to deliver 360 passengers and 32 tons of cargo from Manhattan to New York. It has…
A: The linear programming method is used to find out a feasible solution among the available options…
Q: Midtown Manufacturing Company makes trash cans and plastic buckets, both of which requires labor…
A: The question of optimization can be solved using the graphical method, simplex method, and using…
Q: Muir Manufacturing produces two popular grades of commercial carpeting among its many other…
A: Given information:Each roll of grade X carpet uses synthetic fiber is=50unitsProduction time of…
Q: Irwin Textile Mills produces two types of cotton cloth—denim and corduroy. Corduroy is a heavier…
A: Let Denim = D and Corduroy = C Maximize profit = 2.25D + 3.10C subject to 5D + 7.5 C <=…
Q: Niki holds two part-time jobs, Job I and Job II. She never wants to work more than a total of 12…
A: GIVEN THAT: TOTAL HOURS AVAILABLE TO WORK = 12 HRS PER WEEK PREPARATION TIME NEEDED FOR JOB 1= 2 HRS…
Q: a company possesses two manufacturing plants, each of which can produce three products: X,Y, and Z…
A: Let x1 be the number of hours of plant A in use.x2 be the number of hours of plant B in use.
Q: Muir Manufacturing produces two popular grades of commercial carpeting among its many other…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: pleqse solve the question 2 here using the information in question 1
A: as per your instruction, we are solving the second question. given,
Q: An air conditioning manufacturer produces room air conditioners at plants in Houston, Phoenix, and…
A: Given data
Q: TechConsult Projects Ltd provides technical services to various small businesses in the San Antonio…
A: Ti = Technicians Ci = Clients
Q: Nash Auto has two plants, two warehouses, and three customers. The plants are in Detroit and…
A: Modular design is basically to decompose complex systems into simple modules in order to more…
Q: The Livewright Medical Supplies Company has a total of 12 salespeople it wants to assign to three…
A: Below is the solution:-
Q: A manufacturer produces bicycles and motorcycles, each of which must be processed through two…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: ABC is a small manufacturer of two types of popular all-terrain snow skis, the J and the D models.…
A: THE ANSWER IS AS BELOW:
Q: AutoIgnite produces electronic ignition systems for automobiles at a plant in Cleveland, Ohio. Each…
A: 1) It is asked to formulate a linear programming model that can be used to develop a daily…
Q: The Shop at Home Network sells various household goods during live television broadcasts. The…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: You have solved a 3-variable maximisation Linear Program with the objective function of z = 4x1 +…
A: Objective function: Maximize Z = 4x1+3x2+7x3 x1 = 7 x2 = 0 x3 = 0 Optimal value of Z =…
Q: Juiceco manufactures two products: premium orange juice and regular orange juice. Both products are…
A: Decision variables:
Q: A factory manufactures three products, A, B, and C. Each product requires the use of two machines,…
A: The linear programming model is used to maximize the profit or minimize the cost using the limited…
Q: The Electrotech Corporation manufactures two industrial-sized electrical devices: generators and…
A: Given data is Profit of generator = $275 Profit of alternator = $190 Wiring hours for generator = 3…
Q: NEO Chemical produces two products, namely A and B. Each product is produced by blending three types…
A: Given data is Revenue by product A = 60 euros Revenue by product B = 50 euros Available RM1 = 600…
Q: A company has a total of 3 factories to produce steel and iron. Every month, the company must meet…
A: Cost is in pounds
Q: Exeter Mines produces iron ore at four different mines; however, the ores extracted at each mine are…
A:
Q: Corsouth Mortgage Associates is a large home mortgage firm in the Southeast. It has a pool of…
A: Let , x=number of permanent operatorsy=number of temporary operatorsz=number of part time…
Q: A company makes two products, X and Y, using two machines, 1 and 2. Each unit of X that is produced…
A:
Q: A company produces two products that are processed on two assembly lines. Assembly line 1 has 100…
A: Two products are processed on two assembly lines Available Hours: Assembly Line 1 = 100 hours…
Q: A food wholesaler has three kinds of individual bags of potato chips: regular, barbeque, and salt…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: A manufacturing firm produces two products. Each product must undergo an assembly process and a…
A: let the products be A, B suppose the number of units A produced = x the number of units B produced =…
Q: Weenies is a food processing plant which manufactures hot dogs and hot dog buns. They grind their…
A: Hot dogs Hot dog buns Sign Available Flour (pound/ unit) 0.1 <= 200 Pork…
Q: The Pine Valley Board of Education must hire teachers for the coming school year. The types of…
A: Given data, History, science 20 $21, 000History, math 15 $22, 000English, science 12 $23,…
Q: A company manufactures two products, X and Y by using three machines A, B, and C. Machine A has 4…
A: Given Information:
Q: For what value of h will a sensitivity analysis on the effect of a change of h pounds of peat be…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Virginia Tech operates its own power generating plant. The electricity generated by this plant…
A: Let C1, C2, and C3 be the quantities of coal 1, coal 2, and coal 3. Objective function: Max…
Q: The Livewright Medical Supplies Company has a total of 12 salespeople it wants to assign to three…
A:
Q: Ewing Oil has oil fields in San Diego and Los Angeles. The San Diego field can produce up to 500,000…
A:
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 4 images
- The Tinkan Company produces one-pound cans for the Canadian salmon industry. Each year the salmon spawn during a 24-hour period and must be canned immediately. Tinkan has the following agreement with the salmon industry. The company can deliver as many cans as it chooses. Then the salmon are caught. For each can by which Tinkan falls short of the salmon industrys needs, the company pays the industry a 2 penalty. Cans cost Tinkan 1 to produce and are sold by Tinkan for 2 per can. If any cans are left over, they are returned to Tinkan and the company reimburses the industry 2 for each extra can. These extra cans are put in storage for next year. Each year a can is held in storage, a carrying cost equal to 20% of the cans production cost is incurred. It is well known that the number of salmon harvested during a year is strongly related to the number of salmon harvested the previous year. In fact, using past data, Tinkan estimates that the harvest size in year t, Ht (measured in the number of cans required), is related to the harvest size in the previous year, Ht1, by the equation Ht = Ht1et where et is normally distributed with mean 1.02 and standard deviation 0.10. Tinkan plans to use the following production strategy. For some value of x, it produces enough cans at the beginning of year t to bring its inventory up to x+Ht, where Ht is the predicted harvest size in year t. Then it delivers these cans to the salmon industry. For example, if it uses x = 100,000, the predicted harvest size is 500,000 cans, and 80,000 cans are already in inventory, then Tinkan produces and delivers 520,000 cans. Given that the harvest size for the previous year was 550,000 cans, use simulation to help Tinkan develop a production strategy that maximizes its expected profit over the next 20 years. Assume that the company begins year 1 with an initial inventory of 300,000 cans.FeVer Beverages is a typical coffee shop that operates at Batangas. Recently, the general manager is facing a challenge about not meeting their target lead time of serving the hot coffee of 15 minutes. The lead time starts from order taking until order serving. The staffing model of the shop has one cashier, one barista and a guard. The number of staff, equipment, and raw materials have been found sufficient. Based on the initial data analysis, the volume of customers has been stable. Because there is a need for the lead time to improve as to retain its customers and to even grow, a problem-solving effort has been started using the Lean Six Sigma DMAIC approach. Using the FEVER Beverages, you should create your own Project Charter and SIPOC Diagram.Cakes baked by the Freshfood Bakery are transported from the ovens to be packaged by one of three wrappers. Each wrapper can wrap an average of 200 cakes per hour. The cakes are brought to the wrappers at the rate of 500 per hour. If a cake sits longer than 5 minutes before being wrapped, it will not be fresh enough to meet the bakery’s quality control standards. Does the bakery need to hire another wrapper?
- The following data relates to the number of passengers the Mussina border post between Zimbabwe and South Africa can process:Maximum passengers that can be processed per day based on all the equipment and personnel = 5000 trucksCurrent number of passengers being processed = 4000 passengers per dayActual number of passengers processed yesterday = 3600Calculate the current utilisation level of the border post passenger processing system A. 18% B. 50% C. 80% D. 72% E. 90%Galaxy Candy Company manufactures two popular candy bars, the Eclipse bar and the Nova bar. Both candy bars go through a mixing operation where the various ingredients are combined, and the Coating Department where the bars from the Mixing Department are coated with chocolate. The Eclipse bar is coated with both white and dark chocolate to produce a swirled effect. A material shortage of an ingredient in the Nova bar limitsproduction to 300 batches per hour. Production and sales data are presented in the following table. Mixing CoatingAvailable capacity in hours 525 500Use of capacity in hours per batch of product: Eclipse 1.5 2.0 Nova…A manufacturing firm has three plants and wants to find the most efficient means of meeting the requirements of its four customers. The relevant information for the plants and customers, along with shipping costs in dollars per unit, are shown in the table below: Customer (requirement) Factory (capacity) Customer 1 (25) Customer 2 (50) Customer 3 (125) Customer 4 (75) A (100) $ 15 $ 10 $ 20 $ 17 B (75) $ 20 $ 12 $ 19 $ 20 C (100) $ 22 $ 20 $ 25 $ 14 Note: This question requires Solver.Formulate the problem in Solver and find the optimal solution. What is the minimum total cost to meet all customer requirements?
- ChocoTown has a 4,000 square foot outlet store that serves five major customer regions, denoted A, B, C, D and E. The locations of the points representing the customer regions and their weekly demands are shown in the table below. The ChocoTown outlet store is at location (10,20). Customer Region Location Demand ($/week) A (0,10) 4,000 B (0,20) 2,000 C (20,0) 4,000 D (30,20) 3,000 E (40,10) 2,000 CandyTime is a new competitor of ChocoTown and they are considering opening a 4,000 square foot store at location (30,10). Assume the travel time from location i to j in minutes equals the straight line distance from i to j. a) Use the spatial interaction model to estimate the demand that would be captured by the new CandyTime store. Demand captured by CandyTime = ___________ b) Suppose the CandyTime store is located at (30,10), but it is not 4,000 square feet. Use the spatial interaction model to find the size in square feet for…A steel production plant manufactures bands and coils which sell at a profit of $25 and $30 per ton,respectively. The production rate of the plant for bands is 200 tons/hr, and that for coils is 140 tons/hr.Based on the market analysis, it has been identified that the weekly demand is at most 6000 tons and4000 tons for bands and coils, respectively . The plant operates for a maximum of 40 hours per week. 1. In Microsoft Excel, formulate a linear programming model instance for this problem, then solve. 2. Assume that the products need to be painted after manufacturing, and the painting departmentcan paint at a rate of 600 tons per hour for bands and 400 tons per hour for coils. The paintingdepartment works only for 20 hours. Update the linear programming model instance to accom-modate this requirement, and re-solve the problem. 3. The plant is planning to introduce another product “rods” to its production mix with the followingparameters:•Profit/ton = $40•Production volume = 150…R. C. Coleman distributes a variety of food products that are sold through grocery store and supermarket outlets. The company receives orders directly from the individual outlets, with a typical order requesting the delivery of several cases of anywhere from 20 to 50 different products. Under the company’s current warehouse operation, warehouse clerks dispatch order-picking personnel to fill each order and have the goods moved to the warehouse shipping area Because of the high labor costs and relatively low productivity of hand order picking, management has decided to automate the warehouse operation by installing a computer-controlled order-picking system along with a conveyor system for moving goods from storage to the warehouse shipping area. R. C. Coleman’s director of material management has been named the project manager in charge of the automated warehouse system. After consulting with members of the engineering staff and warehouse management personnel, the director compiled a…
- A gold mining area in Lanao contains on average, 1 ounce of gold per ton. Two methods of processing are available; method A costs ₱1.5 M per ton and recovers 90% of gold; method B cost ₱1.3M per ton and recovers 80% of the gold. If gold can be sold for ₱2.4M per ounce, which method is better and by how much?K The Dahlia Medical Center has 30 labor rooms, 19 combination labor and delivery rooms, and 4 delivery rooms. All of these facilities operate around the clock. Time spent in labor rooms varies from hours to days, with an average of about a day. The average uncomplicated delivery requires about one hour in the delivery room. The average time in a combination labor-delivery room is about 24 hours. During an exceptionally busy three-day period, 103 healthy babies were born at Dahlia Medical Center. 57 babies were born in separate labor and delivery rooms and 46 were born in combined labor and delivery rooms. Which of the facilities (labor rooms, combination labor and delivery rooms, or delivery rooms) had the greatest utilization rate? had the highest utilization rate of %. (Enter your response as a percent rounded to two decimal places.) The delivery rooms combination labor and delivery rooms labor roomsJefferson Company’s demand for its only product exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units. Actual run time this week 6,106 minutes Machine time available per week 8,600 minutes Actual run rate this week 4.32 units per minute Ideal run rate 6.00 units per minute Defect-free output this week 11,315 units Total output this week (including defects) 15,500 units 1. Compute the utilization rate.2. Compute the efficiency rate. 3. Compute the quality rate. 4. Compute the overall equipment effectiveness (OEE).