Wheeler's Bike Company manufactures custom racing bicycles. The company uses a job order cost system to determine the cost of each bike. Estimated costs and expenses for the coming year follow: Bike parts Factory machinery depreciation Factory supervisor salaries Factory direct labor Factory supplies Factory property tax Advertising cost Administrative salaries Administrative-related depreciation Total expected costs $ 339,800 56,500 143,500 210,780 39,900 34,250 25,500 49,500 19,700 $919,430 Required: 1. Calculate the predetermined overhead rate per direct labor hour if the average direct labor rate is $11.71 per hour. 2. Determine the amount of applied overhead if 17,900 actual hours are worked in the upcoming year.

Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter18: Pricing And Profitability Analysis
Section: Chapter Questions
Problem 1CE: Ventana Window and Wall Treatments Company provides draperies, shades, and various window...
icon
Related questions
Question

Sh51

Wheeler's Bike Company manufactures custom racing bicycles. The company uses a job order cost system to determine the cost of
each bike. Estimated costs and expenses for the coming year follow:
Bike parts
Factory machinery depreciation
Factory supervisor salaries
Factory direct labor
Factory supplies
Factory property tax
Advertising cost
Administrative salaries
Administrative-related depreciation
Total expected costs
$ 339,800
56,500
143,500
210,780
39,900
34,250
25,500
49,500
19,700
$919,430
Required:
1. Calculate the predetermined overhead rate per direct labor hour if the average direct labor rate is $11.71 per hour.
2. Determine the amount of applied overhead if 17,900 actual hours are worked in the upcoming year.
Transcribed Image Text:Wheeler's Bike Company manufactures custom racing bicycles. The company uses a job order cost system to determine the cost of each bike. Estimated costs and expenses for the coming year follow: Bike parts Factory machinery depreciation Factory supervisor salaries Factory direct labor Factory supplies Factory property tax Advertising cost Administrative salaries Administrative-related depreciation Total expected costs $ 339,800 56,500 143,500 210,780 39,900 34,250 25,500 49,500 19,700 $919,430 Required: 1. Calculate the predetermined overhead rate per direct labor hour if the average direct labor rate is $11.71 per hour. 2. Determine the amount of applied overhead if 17,900 actual hours are worked in the upcoming year.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 6 steps

Blurred answer
Knowledge Booster
Cost classification
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College