Use the schedule below to answer these questions. (Assume a 5-day work week, weekends are shown as non-work days in gray) What is the total float for Activity D? What is the total float for Activity G? What is the free float for Activity J? What is the total float for Activity A? What is the free float for Activity A? O Task Name Duration Predecessors 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 2 1 Start 0Days 2 A 6Days 1 3 B 3Days 1 4 C 5Days 25 5 D 6 days 3 6 E 1 Day 3 7 F 4 Days 6 G 80ays 6 H 40s 7 I 5Days 7 J 4Days 6 K 1 Day 11,8 2Days 10,129,4 End 0Days 13 8 9 10 11 12 13 14

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Use the schedule below to answer
these questions. (Assume a 5-day
work week, weekends are shown as
non-work days in gray)
What is the total float for Activity D?
What is the total float for Activity G?
What is the free float for Activity J?
What is the total float for Activity A?
What is the free float for Activity A?
O Task Name Duration Predecessors 27 28 29 30 31 1 2 3 4 5 6 7 8 9
Start Days
A 6Days
1
B 3Days
4 C 5Days
5
D
6 days
6
E
1 Day
7
F 4Days
8
G 80ays
9
H 4Days
10
1
5Days
11
J
4Days
12
K
1 Day
11,8
B
L 2Days 10,129,4
14
End
0Days
13
alalal
1
2
3
1
25
3
3
6
67769
B
13
3
14 15 16 17 18 19 20 21 22 23
Transcribed Image Text:Use the schedule below to answer these questions. (Assume a 5-day work week, weekends are shown as non-work days in gray) What is the total float for Activity D? What is the total float for Activity G? What is the free float for Activity J? What is the total float for Activity A? What is the free float for Activity A? O Task Name Duration Predecessors 27 28 29 30 31 1 2 3 4 5 6 7 8 9 Start Days A 6Days 1 B 3Days 4 C 5Days 5 D 6 days 6 E 1 Day 7 F 4Days 8 G 80ays 9 H 4Days 10 1 5Days 11 J 4Days 12 K 1 Day 11,8 B L 2Days 10,129,4 14 End 0Days 13 alalal 1 2 3 1 25 3 3 6 67769 B 13 3 14 15 16 17 18 19 20 21 22 23
Expert Solution
steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.