Three activities are candidates for crashing on a project network for a large computer installation (all are, of course, critical). Activity details are in the following table: Normal Crash Activity Time (days) Time (days) A BC с 7 4 11 629 9 Normal Cost $5,000 $1,400 $4,200 Total Cost with Crashing Immediate Predecessor(s) $5,500 $3,100 $6,200 A B
Q: Which of the following is false about the Assumptions of queuing model? The waiting space available…
A: Queuing theory is the study of waiting for lines/queues. This model helps to determine the length…
Q: Problem 5-4 (Algo) AlwaysRain Irrigation, Inc. would like to determine capacity requirements for the…
A: The quantity of resources, facilities, or infrastructure required to satisfy the demand for a…
Q: Interview Tips to Get the Job: 5 Things You Need to Ace the Interview
A: An interview is a form of conversation that involves an interviewer who poses a question while…
Q: Management Question. How does the insufficiency of training materials, resources, and support…
A: In today's fast-paced and ever-changing environment, training and development inside organisations…
Q: Stage 2 General Mathematics - Summative Discrete Models Test 1. Nine activities are needed to…
A: The relationships and dependencies between the tasks or activities of a project are graphically…
Q: What is the final value of the decision tree?
A: Find the given details below:
Q: Capitec Bank is a retail bank headquartered in South Africa. It is one of the largest banks in the…
A: A risk register is an aspect that records all the possible and identified risks that are associated…
Q: From the Research Topic and Research Questions below kindly provide an Introduction and Literature…
A: Research is the aspect of the study that is concerned with the creation of new knowledge of…
Q: Which category of performance metrics is NOT included in Kaplan and Norton's Balanced Scorecards?…
A: The organization uses a performance management framework called "Kaplan and Norton's Balanced…
Q: A fabrication cell at Spradley's Sprockets uses the pull method to supply gears to an assembly line.…
A: Demand (d) = 453 gears per dayWaiting days (w) = 1.2 daysProduction time (p) = 2.4 daysPolicy…
Q: PROJECT SCENARIO Social media law encompasses all the legal issues associated with user-generated…
A: Employee online privacy rights refer to an individual's right to retain personal privacy when using…
Q: Answer the 3 questions in the case study Using Project Management Software to Schedule the Olympic…
A: Utilizing project management software, Olympic organizers meticulously planned event logistics,…
Q: The chapter presents multiple techniques that service i rms can use to make their processes leaner.…
A: Marketing techniques specify the plans or strategies that are used by businesses or companies to…
Q: questionnaire for hiring a CSR (Corporate Social Responsibility) Manager for a renowned…
A: The questionnaire specifies the set of questions that can be structured or unstructured based on the…
Q: A medical equipment testing and calibration service is shown below. The customer usually brings the…
A: A "bottleneck job" refers to a specific task or process within a workflow or system that hinders the…
Q: Q. How is the problem description different for a business case compared to an actual business…
A: The distinction between a business case problem description and an actual business problem…
Q: Q.1.1 Explain how the regulatory environment for transport in South Africa can impact on a business…
A: The regulatory environment includes a set of laws, legal requirements, norms, and regulations that…
Q: Lusail Food aims to produce (30,000) units next year. After studying the time, it turned out that…
A: Workload analysis deals with analyzing or gathering information number of employees or staff…
Q: 0#3. Cookie Problem. You're operations manager of a bakery. You want to ensure that the production…
A: Here, there is a total of 14 samples, and for each sample, I am given the individual data, so, I…
Q: To support National Heart Week, the Heart Association plans to install a free blood pressure testing…
A: customers per hourcustomers per hour
Q: The Economic Order Quantity (EOQ) model is a classical model used for controlling inventory and…
A: The practice of monitoring and managing the acquisition, storage, and use of materials or goods…
Q: Solve the below Linear program and find the optimal solution from the below options: Minimize z = 2x…
A: Linear programming (LP) is a mathematical optimization technique that helps solve problems where an…
Q: Slide 2: Company Overview • Write a brief introduction to Walmart, including its industry, the size…
A: Walmart is a global retail juggernaut with a vast store network and a strong online presence.…
Q: 2) What is the main objective of a supply chain? A) Minimizing supply chain transportation costs B)…
A: A supply chain's primary goal is to maximize the total value produced. Value creation for the…
Q: Triton Submarines LLC offers small submersibles that can take up to three individuals 1,000 m deep…
A: Decision-making analysis is the approach or aspect that includes the systematic and well-structured…
Q: Walmart experiences a demand of 5 units per day for its LED TVs. The lead time for re-stocking LED…
A: Daily demand (d) = 5Lead time (L) = 10
Q: e) Solve the mixed-integer linear program formulated in part (d). How much of each product should be…
A: Note:You have asked only for part e. I have answered only them Formulation:Decision Variables:P1=…
Q: 3-D printing, also known as "additive manufacturing." generally works by adding tiny layers of…
A: The given question pertains to comprehension and understanding the information given in the…
Q: 2. The following table lists the activities of a network along with their time estimates: Activity…
A: For each activity, I will determine the expected activity time, standard deviation, and variance,…
Q: Find the Optimal Economic order quantity for the following: Annual Demand-3600 units Ordering…
A: The Optimal Economic Order Quantity (EOQ) is the optimal quantity of a product to order at one time…
Q: Find the below table which shows the task time. The Maximum output of the company is 240 bottles per…
A: Project schedule helps in calculating different values related to the production cycle like the…
Q: Research topic - What is the future of strategic managemnt planning and managemnt personnel in a…
A: Strategic management gives the general direction to a company indicating what it should do in the…
Q: You have the following data: Actual Forecast 1 50 50 2 46 3 52 4 51 5 48 6 45 7 52…
A: Exponential smoothing is based on the time series forecasting method. It is particularly useful for…
Q: The Action Toy Company has decided to manufacture a new train set, the production of which is broken…
A: Find the Given details below:
Q: Describe the pros and cons of outsourcing web development to offshore teams.
A: Outsourcing can be defined as the process of relying on the third party and hiring that party in…
Q: Discussion Question: Service Level Agreements (SLAs) are becoming more commonplace within…
A: A service-level agreement specifies the set or the level of service expected between the customer or…
Q: he Westchester Chamber of Commerce periodically sponsors public service seminars and programs.…
A: Linear programming helps us to find the resource allocation, with given constraintsWe have to…
Q: Consider the following activities for a project. Answer the questions below. a. Assume the…
A: TaskPredecessorsDuration (days)Resource1-Order review2Ryan2-Order vendor parts116Carly3-Produce…
Q: Joseph and Krystal are part of your social group. They joined Missile’s Financial Services together…
A: The given case is about workplace communication. Workplace communication is the interchange of…
Q: e) (P1, P2, P3, y1, y2, y3) = (0, 77, 109, 0, 1, 1) with a profit of $ 5260 is wrong
A: Note:You have asked only for part d and e. I have answered only them FormulationDecision…
Q: In the initial solution of a transportation problem, the only restriction is that there should be…
A: The transportation model is used to calculate the minimum cost of the route by selecting different…
Q: Charles Lackey operates a bakery in Idaho Falls, Idaho. Because of its excellent product and…
A: Produce loaves per month (Output) =1500Productivity per hour = 2.344 loaves/hourLabor hours per…
Q: A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling…
A: A bottleneck operation is a specific position in a production or workflow process where the slowest…
Q: Suppose a foreign company is planning to enter the Chinese market and looking for a business with…
A: Market entry strategy is the aspect of the business in which a company plans to enter the market. It…
Q: What is the grocer's expected profit? Use Excel. Note: Do not round intermediate calculations. Round…
A: I will determine the expected profit for the grocer,
Q: This is a follow up question please do f and g
A: The critical path consists of various activities. All the activities have early and late times…
Q: Dr. Huckvale, of and Huckvale & Associates, LLP, is examining how overhead costs behave as a…
A:
Q: The process for renewing a driver's license at the Archer County Courthouse is as follows. First,…
A: Bottleneck analysis helps the organization in allocating resources more effectively. Bottlenecks can…
Q: Can Huawei Overcome Roadblocks in its Quest for Global Markets? Huawei Technologies Ltd. (Huawei)…
A: International Business is the aspect of business that deals with the trade of products, knowledge,…
Q: Given the following 3 firms, which provides the machinery with the best System Availability? And…
A: Availability- It is the measure of a piece of time in which a piece of equipment or machinery is…
Trending now
This is a popular solution!
Step by step
Solved in 3 steps
- Normal Time Problem 1 You are the manager of a project to improve a billing process at your firm. The following table contains the data you will need to conduct crashing of the project duration. Indirect costs are $1,600 per week, and penalty costs are $1,200 per week after Week 12. Activity Immediate Predecessor(s) Crash Time (weeks) Normal (Direct) Cost Crash Cost (weeks) ($) ($) A 4 1 5,000 8,000 B 5 2 8,000 11,000 C A 1 1 4,000 4,000 Ꭰ B 6 3 6,000 12,000 E B, C 7 6 4,000 7,000 F Ꭰ 7 6 4,000 7,000 What is the optimum choice for project duration?Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Normal Crash Normal Activity Time (weeks) Time (weeks) Cost ABCDEFG 4 2 3 8 6 3 4 3 1 3 4 3 2 2 $2,100 $2,300 $600 $2,400 $800 $3,400 $1,400 Total Cost with Crashing Immediate Predecessor(s) $2,750 $2,900 $600 $2,680 $1,100 $4,600 $1,900 a) Based on the given information regarding the activities for the project, the project length b) The total cost required for completing this project on normal time = $ 13000. | | A B C D, E = 16 weeks. c) For reducing the duration of the project by one week, the activity that should be crashed first is activity D The cost of the project based on the first activity selected for crashing will increase by $ 70. d) The maximum weeks by which the project can be reduced by crashing = 7 weeks. Total cost of crashing the…2:30 PM ě 0.3KB/s 1ll 54 4G+ 00:15:12 Remaining Multiple Choice The primary difference between PERT and CPM is that CPM uses probabilities on the activity times and PERT does not. O. PERT considers activity costs and CPM does not. PERT can assign probabilities to activity times and CPM does not. CPM considers activity costs and PERT does not. 5 of 20 II
- Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Immediate Predecessor(s) A 44 33 $ 2 comma 100$2,100 $ 2 comma 700$2,700 long dash— B 22 11 $ 2 comma 200$2,200 $ 2 comma 900$2,900 long dash— C 33 33 $ 500$500 $ 500$500 long dash— D 88 44 $ 2 comma 500$2,500 $ 2 comma 820$2,820 A E 66 33 $ 1 comma 000$1,000 $ 1 comma 300$1,300 B F 33 22 $ 3 comma 400$3,400 $ 4 comma 800$4,800 C G 44 22 $ 1 comma 500$1,500 $ 2 comma 000$2,000 D, E Part 2 a) Based on the given information…Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table D Total Cost with Normal Time Crash Time Normal Immediate Activity (weeks) (weeks) Cost Crashing Predecessor(s) A 4 3 $2,000 $2,650 B 2 1 $2,300 $3,100 TTTT C 3 3 $750 $750 D 8 4 $2,300 $2,580 A E 6 3 $1,000 $1,300 B F 3 2 $3,000 $4,400 C G 4 2 $1,600 $2,000 D, E a) Based on the given information regarding the activities for the project, the project length = weeks. b) The total cost required for completing this project on normal time = $ ▼ c) For reducing the duration of the project by one week, the activity that should be crashed first is activity The cost of the project based on the first activity selected for crashing will increase by $ weeks. d) The maximum weeks by which the project can be reduced by crashing = Total cost of crashing the project to…Activity Normal_time Crash_time Normal_cost Crash_cost Slack A 31 17 4800 6200 В 14 14 5500 5500 C 34 18 5100 6600 21 17 4500 6800 E 15 15 5300 5300 F 17 17 5300 5300 The table shows normal time, crash time, normal cost, crash cost and slack time of activities in a project. According to this table which activity must be crashed first? Assume there is only one critical path. (Only type the name of the activity, Example: A. @orsdemir. Copyrighted content. Cannot be posted.) 0ㅇ11 2 0
- Consider the following activity description with associated cost data shown in Table 1. The cost data represents the total cost and should be considered linear with time. Table 1: Crash Cost Table Activity Immediate Predecessor Normal Duration (days) Normal Cost ($) Crash Duration (days) Crash Cost ($) A --- 5 50 3 150 B --- 4 40 2 200 C B 7 70 5 250 D A, C 2 20 1 50 E A, C 5 125 1 525 F B 10 80 7 290 G D 7 50 3 250 H E, F 6 60 3 180 Reduce the project duration to minimum duration and calculate the cost. Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.Environment Recycling, Inc. must clean up a large automobile tire dump under a state environmental cleanup contract. Suppose that some of the activities in the Environment Recycling, Inc. project can be crashed.The table below shows the crash times and costs associated with performing the activities at their original (normal) times and also for the crash times (all times are in weeks). Normal Crash Normal Crash Activity Predecessor(s) Time Time Cost Cost A — 6 5 $490 $640 B A 9 7 1,800 2,400 C A 8 7 860 1,060 D — 7 6 620 920 E B, C, D 9 7 1,900 2,300 F D 4 2 820 1,320 G D 4 3 620 870 H E 5 4 500 710 I F, G, H 7 5 950 1,550 Choose the correct network for the project. The correct network is C . Identify the critical path. The critical path is A-B-E-H-I. What is the total project completion time? Round your answer to the nearest whole number. ___ weeks What is the lowest cost solution if…Three activities are candidates for crashing on a project network for a large computer installation (all are, of course, critical). Activity details are in the following table: Activity A B C Normal Time Crash Time Normal (days) (days) Cost 7 6 4 11 2 9 $5,000 $1,400 $4,000 Total Cost with Immediate Crashing Predecessor(s) $5,600 $3,300 $6,400 a) Activity that should be crashed first to reduce the project duration by 1 day is A b) Activity that should be crashed next to reduce the project duration by one additional day is A B A B C ect: 0
- Three activities are candidates for crashing on a project network for a large computer installation (all are, of course, critical). Activity details are in the following table: Total Cost Normal Time Crash Time Normal with Immediate Activity (days) (days) Cost Crashing Predecessor(s) A 7 6 $4,500 $5,000 $1,400 $3,200 $6,800 B 4 A C 11 9 $4,600 В a) Activity that should be crashed first to reduce the project duration by 1 day isYou company has just received an order for SPEEDY 1 electric motor from a customer. The data on direct costs, activity duration, and precedence relationships are given below: Normal Time (days) Normal Cost Crash Time (days) Predecessor(s) Activity Crash Cost A 4 $1000 $1300 В 7 1400 4 2000 2000 2700 D 6. 1200 1400 A 900 2 1100 11 2500 6 3750 G 4 800 1450 D, E H 300 1 500 F, G (a) Construct the AON network for the project. (b) Determine all paths that run from the start to the end of the network.Problem Statement: Project Control and Monitoring You are working on a manufacturing project having a budget of PKR 3,600,000 and expected time of its completion is one year. There is an ideal condition that your budget and work are evenly spread across the duration of the project that is twelve month. At the end of forth month, the senior management has called a meeting and invited all the stakeholders to brief about the status of the project. You being the PM of this project is giving the presentation to all the attendees and informed that project is on schedule and PKR 1,800,000 have already been spent on the project. Required: Calculate Cost and Schedule Variance What is SPI and CPI of the project? Estimate at completion and Estimated time to complete?