The terms of the arrangement require the operator to: a. Construct a road-completing construction within two years b. Maintain and operate the road for three years c. Resurface the road when the original surface has deteriorated below a specified condition. The operator estimates that it will have to undertake the resurfacing at the end of year 4. d. The government grants the operator the right to collect toll fees from road users and in addition, guarantees a minimum amount of P100 and interest at a specified rate of 24.42% to reflect the timing of cash receipts. e. The contract ends in year 5. The operator makes the following estimates: Year Contract Cost Stand-alone selling price
Q: During the year, Agency XYZ entered into a contract with a third party for the construction of a new…
A: Solution : Calculation of cost of the building Total initial contract price 14,500,000…
Q: d, if the contractor was able to finish the building earlier than agreed, it will be rewarded an…
A: In the given situation, a construction contract was agreed upon at certain price with an cost…
Q: On January 1, 2041, ENGR Inc. accepted a long-term construction project to construct a building with…
A: Construction Contract: A construction contract is a contract between a customer and a general…
Q: The terms of the arrangement require the operator to: a. Construct a road-completing construction…
A: Opportunity cost: It is the cost of gain sacrificed when one alternative is selected over the cost…
Q: On January 1, Year 1, Crawford Construction Company enters into a contract with a customer to build…
A: Revenue to be recognised = Price * Percentage of completion
Q: Please answer and show all steps: A construction company is engaged in a three-year renovation…
A: Comment- Since we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit the…
Q: The terms of the arrangement require the operator to: a. Construct a road-completing construction…
A: Carrying value is the amount which is computed after deducting accumulated depreciation from the…
Q: On January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision…
A: Answer - Given, Estimated total cost of contract for the 10 houses = P40M. In CY 20x6, total…
Q: The following events occurred between December 31, 2020 (the reporting date) and March 22, 2021, the…
A: Here discuss about the details whether adjustment entry or the disclosure which are made after the…
Q: ABC Co., a private contractor, wins a bid to construct an expressway for provincial government,…
A:
Q: The terms of the arrangement require the operator to: Construct a road-completing construction…
A: Note: Assuming that the intangible asset is written down on straight-line basis.
Q: Abot Company, a private contractor, wins a bid to construct a railway for the government. The terms…
A: All amounts are in P.
Q: Rainy August Afternoon Co. (RAA) enters into a service concession arrangement whereby RAA undertakes…
A: Step 1 Under service concession arrangement, public properties are granted to private entities to…
Q: A contractor has been appointed to complete alterations to buildings owned by Bangkok. The contract…
A: The Number of shares to be issued are 24,444 Shares ( (BD2,200,000 *50%) / BD45) Nominal value =…
Q: The terms of the arrangement require the operator to: Construct a road-completing construction…
A: According the International Accounting Standard 11 (IAS 11), the revenues and expenses associated…
Q: Kami, Inc. charges an initial franchise fee of P500,000 for the right to operate to operate as a…
A: The franchise revenue is recognized at the time of providing service and the payment of the…
Q: ABC Co. a private contractor, wins a bid to construct a railway for the government. The terms of the…
A: Net Income: After deductions such as taxes, retirement plan payments, and health insurance, net…
Q: On January 1, 2021, Ansley Company contracted with a contractor to construct a building for…
A: Lets understand the basics. As per IAS 23 "Borrowing cost", cost incurred for the the construction…
Q: On January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision…
A: Construction accounting requires a special revenue recognition rules for contract in procee.in this…
Q: On January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision…
A: Under contract costing, a contract is made between the parties on some specific project.in generally…
Q: On January 1, 2018, Star Construction Company entered into a contract with KC Company to build a…
A: As per our protocol we are supposed to answer one full question. Kindly repost the question to get…
Q: On April 1st, Ma Construction entered into a contract of one-month duration to build a barn for…
A: Discounts, credits, rebates, performance bonuses, penalties, sales returns, refunds, price…
Q: On January 1, 2020, San Juan Builders Inc. accepted a long-term construction project to build a…
A: SOLUTION- CONSTRUCTION CONTRACT IS A MUTUAL OR LEGALLY BINDING AGREEMENT BETWEEN TWO PARTIES BASED…
Q: Ace Construction Company is under contract to build an athletic facilty for a local college for…
A: In the given case the revenue from construction of athletic facility for a local college in the…
Q: On January 1, 2021, Gemini Company contracted with a contractor to construct a building for…
A: Note: Since we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit the question…
Q: Abot Company, a private contractor, wins a bid to construct a railway for the government. The terms…
A: Under the Contract costing, there is a contract made between the parties in respect of performing…
Q: RAA recognizes an asset that is reported in the financial statements as a. contract asset. b.…
A: Hi student Since there are multiple questions, we will answer only first question.
Q: in and operate the road for four years. Resurface the road when the original surface has…
A: Net Income for Year three = Total income for the year 3 - Total expenses for the year 3…
Q: On January 1, 2020, San Juan Builders Inc. accepted a long-term construction project to build a…
A: Construction Contract: A construction contract is a legal agreement between a customer and a general…
Q: The terms of the arrangement require the operator to: Construct a road-completing construction…
A: The assets which cannot be touched, non- monetary assets and does not have physical existence are…
Q: A contractor enters into a contract for the expansion of an existing two-lane highway to a…
A: In the given situation, the contractor will recieve the award fee only if he completes the project…
Q: ABC Co. a private contractor, wins a bid to construct a railway for the government. The terms of the…
A: The question is based on the concept of Business Accounting.
Q: ABC Co. a private contractor, wins a bid to construct a railway for the government. The terms of the…
A: All amounts are in P.
Q: On January 1, 20x6, Bad, a real estate company, entered into a contract to construct a subdivision…
A: Revenue = current asset
Q: On January 1, 2019, XYZ Company contracted Y Construction Co. to construct a building for $2,800,000…
A: Required journal entries are given below:
Q: On January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision…
A: While preparing the income statement all the expenditures are deducted from the revenue generated so…
Q: On January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision…
A: Answer- Working Note : Computation of Revenue to be Recognized - Particulars Working Amount P…
Q: Determine carrying amount of the building on December 31, 2020.
A: Cost 5,031,750 - Depreciation (47,172.6)
Q: On January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision…
A: Current assets refer to any form of asset that is monetary beneficial for an individual or an entity…
Q: ABC Co., a private contractor, wins a bid to construct an expressway for a provincial government,…
A: As per the Provision of PFRS 115 revenue from contract with customers, revenue can be recognize on…
Q: ot Company, a private contractor, wins a bid to construct a railway ms of the arrangement are as…
A: Net income is the excess amount of revenue that arises after deducting all the expenses of a…
Q: ABC Co. a private contractor, wins a bid to construct a railway for the government. The terms of the…
A: Net income in year 3 = Income - costs in year 3
Q: The terms of the arrangement require the operator to: Construct a road-completing construction…
A: Opportunity cost refers to the situation of loss extent of profit happened when a business chooses…
Q: A contractor enters into a contract for the expansion of an existing two-lane highway to a…
A: The award fee is dependant on timely completion or non-completion of the contract.
Q: On January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision…
A: Under the contract costing, the contractor is required to complete the assigned project within the…
Q: The terms of the arrangement require the operator to: Construct a road-completing construction…
A: Opportunity cost: It is the cost of gain sacrificed when one alternative is selected over the cost…
Q: and it has acquired and, when construction is complete, to deliver the finished houses to their…
A: As per the fundamental accounting principle a revenue should be recognised only when it is earned.…
Q: The terms of the arrangement require the operator to: Construct a road-completing construction…
A: Statement showing Profit/Loss for the Year 1 and 2 Particulars Year 1 Year 2 Sales…
Q: ABC Co. a private contractor, wins a bid to construct a railway for the government. The terms of the…
A: Under the Contract costing, there is a contract made between two parties known as contractor and…
Step by step
Solved in 2 steps
- The terms of the arrangement require the operator to: a. Construct a road-completing construction within two years b. Maintain and operate the road for three years c. Resurface the road when the original surface has deteriorated below a specified condition. The operator estimates that it will have to undertake the resurfacing at the end of year 4. d. The government grants the operator the right to collect toll fees from road users. e. The contract ends in year 5. е. The operator makes the following estimates: Year Stand-alone selling price Contract Cost Construction Services 1 70 Forecast cost +10% 2 80 Forecast cost +20% Operation Services 3-5 25 Forecast cost +30% Road resurfacing 4 15 Forecast cost +10% Compute the carrying amount of intangible asset at the end of year 2.The terms of the arrangement require the operator to: Construct a road-completing construction within 2 years Maintain and operate the road for 3 years Resurface the road when the original surface has deteriorated below a specified condition. The operator estimates that it will have to undertake the resurfacing at the end of Year 4. The government grants the operator the right to collect toll fees from road users. The contract ends in Year 5. The operator makes the following estimates: Construction cost Stand-alone selling price Forecast cost +10% Forecast cost +20% Forecast cost +30% Forecast cost +10% Construction Services Year 1 70 80 |Operation Services Road Resurfacing 3-5 4 25 15 Compute the carrying amount of intangible asset at the end of Year 2.The terms of the arrangement require the operator to: a. Construct a road-completing construction within two years b. Maintain and operate the road for three years c. Resurface the road at the end of Year 4 d. The government pays the operator P200 per year in Years 3 to 5 for making the road available to the public e. The road is turn-over to the government at the end of Year 5 f. The operators determine that the implied interest rate is 24.42%. g. The operator finances the arrangement entirely with debt. The debt proceeds are taken as the contract cost are paid. The debt is payable as follows: 75 in each of years 3 and 4 and P40 in year 5. The effective interest rate is 25.77% The operator makes the following estimates: Year Contract Cost Stand-alone selling price Construction Services 1 70 Forecast cost +10% 2 80 Forecast cost +20% Operation Services Road resurfacing 3-5 25 Forecast cost +30% 4 15 Forecast cost +10% Compute for the profit for year 2.
- ABC Co. a private contractor, wins a bid to construct a railway for the government. The terms of the arrangement are as follows: Construct a road- completing construction within a year; Maintain and operate the road for four years. Resurface the road when the original surface has deteriorated below specified condition. The operator estimates that it will have to undertake the resurfacing at the end of year 3. The operator collects toll fees of P200,000 per year. The contract ends in year 5. The operator estimates that the resurfacing expenditure increases by P5,000 for each year that the road is used. The appropriate discount rate is 10%. At contract inception, ABC Co. identifies a single performance obligation for construction services. ABC Co. makes the following estimates: YEAR CONTRACT COST STAND ALONE SELLING PRICE CONSTRUCTION SERVICE 1 200,000 FORECAST COST + 25% OPERATION SERVICE 2-5 15,000 N/A ROAD RESURFACE 3 10,000 N/A At the start of year 1, ABC Co. obtains…A contractor enters into a contract for the expansion of an existing two-lane highway to a three-lane highway. The contract price is P65 million plus a P5 million award fee if the expansion is complete before the holiday travel season. The contract is expected to take one year to complete. The contractor has a long history of performing this type of highway work The award fee is binary; that is, if the job is finished before the holiday travel season, the contractor receives the full award fee. The contractor does not receive any award fee if the highway is not finished before the holiday season. The contractor believes, based on its significant past experience, that it is 95 percent likely that the contract will be completed in advance of the holiday travel season. 1. How much should the contractor account for the award fee? 2. How many distinct performance obligations are in the contract? Group of answer choices a.2 b. 3 c.4 d. 1A contractor enters into a contract for the expansion of an existing two-lane highway to a three-lane highway. The contract price is P65 million plus a P5 million award fee if the expansion is complete before the holiday travel season. The contract is expected to take one year to complete. The contractor has a long history of performing this type of highway work. The award fee is binary; that is, if the job is finished before the holiday travel season, the contractor receives the full award fee. The contractor does not receive any award fee if the highway is not finished before the holiday season. The contractor believes, based on its significant past experience, that it is 95 percent likely that the contract will be completed in advance of the holiday travel season. How much should the contractor account for the award fee? ______________
- ABC Co. a private contractor, wins a bid to construct a railway for the government. The terms of the arrangement are as follows: Construct a road- completing construction within a year; • Maintain and operate the road for four years. • Resurface the road when the original surface has deteriorated below specified condition. The operator estimates that it will have to undertake the resurfacing at the end of year 3. The operator collects toll fees of P200,000 per year. The contract ends in year 5. The operator estimates that the resurfacing expenditure increases by P5,000 for each year that the road is used. The appropriate discount rate is 10%. At contract inception, ABC Co. identifies a single performance obligation for construction services. ABC Co. makes the following estimates: YEAR CONTRACT COST Stand Alone Selling Price Construction Service 200,000 15,000 10,000 1 Forecast cost + 25% Operation Services Road Resurface 2 to 5 N/A 3 N/A At the start of year 1, ABC Co. obtains a…The terms of the arrangement require the operator to: Construct a road-completing construction within two years Maintain and operate the road for three years Resurface the road at the end of Year 4 The government pays the operator P200 per year in Years 3 to 5 for making the road available to the public The road is turn-over to the government at the end of Year 5 The operators determine that the implied interest rate is 24.42%. The operator finances the arrangement entirely with debt. The debt proceeds are taken as the contract cost are paid. The debt is payable as follows: 75 in each of years 3 and 4 and P40 in year 5. The effective interest rate is 25.77% The operator makes the following estimates: Contract Cost Stand-alone selling price Forecast cost +10% Forecast cost +20% Forecast cost +30% Forecast cost +10% Year Construction Services 70 1 2 80 Operation Services Road resurfacing 3-5 25 4 15 TAM Compute for the profit for year 2.The terms of the arrangement require the operator to: Construct a road-completing construction within 2 years Maintain and operate the road for 3 years Resurface the road at the end of Year 4 The government pays the operator P200 per year in Years 3 to 5 for making the road available to the public The road is turnover to the government at the end of Year 5 The operators determine that the implied interest rate is 24.42% The operator finances the arrangement entirely with debt. The debt proceeds are taken as the contract cost are paid. The debt is payable as follows: P75 in each Years of 3 and 4 and P40 in Year 5. The effective interest rate is 25.77% The operator makes the following estimates: YEAR CONSTRUCTION COST STAND-ALONE SELLING PRICE Forecast cost +10% Construction Services 1 70 80 Forecast cost +20% Operation Services Road Resurfacing Compute for the profit for Year 2. 3-5 4 25 Forecast cost +30% 15 Forecast cost +10% (With two decimal places for the final answer)
- The terms of the arrangement require the operator to: Construct a road-completing construction within two years Maintain and operate the road for three years Resurface the road at the end of Year 4 The government pays the operator P200 per year in Years 3 to 5 for making the road available to the public The road is turn-over to the government at the end of Year 5 The operators determine that the implied interest rate is 24.42%. The operator finances the arrangement entirely with debt. The debt proceeds are taken as the contract cost are paid. The debt is payable as follows: 75 in each of years 3 and 4 and P40 in year 5. The effective interest rate is 25.77% The operator makes the following estimates: Year Contract Cost Stand-alone selling price Construction Service 1 70 Forecast cost + 10% 2 80 Forecast cost + 20% Operation Services 3-5 25 Forecast cost + 30% Road resurfacing 4 15 Forecast cost + 10% Compute for the profit for…The terms of the arrangement require the operator to: Construct a road-completing construction within two years Maintain and operate the road for three years Resurface the road at the end of Year 4 The government pays the operator P200 per year in Years 3 to 5 for making the road available to the public The road is turn-over to the government at the end of Year 5 The operators determine that the implied interest rate is 24.42%. The operator finances the arrangement entirely with debt. The debt proceeds are taken as the contract cost are paid. The debt is payable as follows: 75 in each of years 3 and 4 and P40 in year 5. The effective interest rate is 25.77% The operator makes the following estimates: Year Contract Cost Stand-alone selling price Construction Services 1 70 Forecast cost +10% 2 80 Forecast cost +20% Operation Services Road resurfacing 3-5 25 Forecast cost +30% 4 15 Forecast cost +10% Compute for the profit for year 2.The terms of the arrangement require the operator to: Construct a road-completing construction within two years Maintain and operate the road for three years Resurface the road at the end of Year 4 The government pays the operator P200 per year in Years 3 to 5 for making the road available to the public The road is turn-over to the government at the end of Year 5 The operators determine that the implied interest rate is 24.42%. The operator finances the arrangement entirely with debt. The debt proceeds are taken as the contract cost are paid. The debt is payable as follows: 75 in each of years 3 and 4 and P40 in year 5. The effective interest rate is 25.77% The operator makes the following estimates: Stand-alone selling price Forecast cost +10% Forecast cost +20% Forecast cost +30% Forecast cost +10% Year Contract Cost Construction Services 70 2 80 Operation Services Road resurfacing 25 15 35 4. Compute for the carrying amount of intangible asset at the end of year 2.