The grading works of a portion of the proposed expressway shows the following notes. Limits of free haul distance is from STA 1+272 to STA 1+322 Limits of economical haul is from STA 1+052 to STA 1+502 STATION CUT (m²) FILL (m²) 1+000 40 1+052 33 1+272 3.021 1+300 Balancing point 1+322 3.845 1+502 40.18 1+600 60

Traffic and Highway Engineering
5th Edition
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Garber, Nicholas J.
Chapter14: Highway Surveys And Location
Section: Chapter Questions
Problem 17P: The following table shows the stations and ordinates for a mass diagram. The free-haul distance is...
icon
Related questions
Question

Determine the volume of waste

The grading works of a portion of the proposed expressway shows the following notes.
Limits of free haul distance is from
STA 1+272 to STA 1+322
Limits of economical haul is from
STA 1+052 to STA 1+502
STATION
CUT (m²)
FILL (m?)
1+000
40
1+052
33
1+272
3.021
1+300
Balancing point
1+322
3.845
1+502
40.18
1+600
60
Transcribed Image Text:The grading works of a portion of the proposed expressway shows the following notes. Limits of free haul distance is from STA 1+272 to STA 1+322 Limits of economical haul is from STA 1+052 to STA 1+502 STATION CUT (m²) FILL (m?) 1+000 40 1+052 33 1+272 3.021 1+300 Balancing point 1+322 3.845 1+502 40.18 1+600 60
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Mechanical processes
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning