The following jobs are waiting to be processed at a small machine center: According to the LPT rule, the sequence of jobs should be 50, 20, 10, 30, 40. b) What is the average completion (flow) time? The average completion (flow) time is c) What is the average job lateness? The average job lateness is d) What in the JOB DUE DATE DURATION (DAYS) 260 18 IIT 254 22 260 14 265 275 10 20 number of inho in the custom? 30 40 50 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 (yesterday) in the order shown but are not scheduled to begin until day 201 (today). a) Sequence the jobs according to LPT. days (round your response to one decimal place). days (round your response to one decimal place). 4 32

Elements Of Electromagnetics
7th Edition
ISBN:9780190698614
Author:Sadiku, Matthew N. O.
Publisher:Sadiku, Matthew N. O.
ChapterMA: Math Assessment
Section: Chapter Questions
Problem 1.1MA
icon
Related questions
Question
The following jobs are waiting to be processed at a small machine center:
JOB
10
20
30
40
50
DUE DATE
260
254
260
265
275
days (round your response to one decimal place).
days (round your response to one decimal place).
DURATION (DAYS)
18
T
22
14
32
All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 (yesterday) in the order shown but are not scheduled to begin until day 201 (today).
a) Sequence the jobs according to LPT.
According to the LPT rule, the sequence of jobs should be 50, 20, 10, 30, 40
b) What is the average completion (flow) time?
The average completion (flow) time is
c) What is the average job lateness?
The average job lateness is
d) What is the average number of jobs in the system?
The average number of jobs in the system is jobs (round your response to one decimal place).
62446
Transcribed Image Text:The following jobs are waiting to be processed at a small machine center: JOB 10 20 30 40 50 DUE DATE 260 254 260 265 275 days (round your response to one decimal place). days (round your response to one decimal place). DURATION (DAYS) 18 T 22 14 32 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 (yesterday) in the order shown but are not scheduled to begin until day 201 (today). a) Sequence the jobs according to LPT. According to the LPT rule, the sequence of jobs should be 50, 20, 10, 30, 40 b) What is the average completion (flow) time? The average completion (flow) time is c) What is the average job lateness? The average job lateness is d) What is the average number of jobs in the system? The average number of jobs in the system is jobs (round your response to one decimal place). 62446
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Dimensional Analysis
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, mechanical-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Elements Of Electromagnetics
Elements Of Electromagnetics
Mechanical Engineering
ISBN:
9780190698614
Author:
Sadiku, Matthew N. O.
Publisher:
Oxford University Press
Mechanics of Materials (10th Edition)
Mechanics of Materials (10th Edition)
Mechanical Engineering
ISBN:
9780134319650
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Thermodynamics: An Engineering Approach
Thermodynamics: An Engineering Approach
Mechanical Engineering
ISBN:
9781259822674
Author:
Yunus A. Cengel Dr., Michael A. Boles
Publisher:
McGraw-Hill Education
Control Systems Engineering
Control Systems Engineering
Mechanical Engineering
ISBN:
9781118170519
Author:
Norman S. Nise
Publisher:
WILEY
Mechanics of Materials (MindTap Course List)
Mechanics of Materials (MindTap Course List)
Mechanical Engineering
ISBN:
9781337093347
Author:
Barry J. Goodno, James M. Gere
Publisher:
Cengage Learning
Engineering Mechanics: Statics
Engineering Mechanics: Statics
Mechanical Engineering
ISBN:
9781118807330
Author:
James L. Meriam, L. G. Kraige, J. N. Bolton
Publisher:
WILEY