The durations and direct costs for each activity in the network of a small construction contract under both normal and crash conditions are given in below table. Establish the least cost for expediting the contract. Determine the optimum duration of the contract assuming the indirect cost amounts to SR 125/week. Activity ABCDE F G H I Preceded by A A B B с E.C F D. G. H Normal Duration (weeks) 12 8 15 23 5 5 20 13 12 Cost (SR) 7000 5000 4000 5000 1000 3000 6000 2500 3000 36500 Duration (weeks) 10 6 12 23 4 4 15 Crash 10 Cost (SR) 7200 5300 4600 5000 1050 3300 6300 2580 3150 38470

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Give typing answer with explanation and conclusion 

The durations and direct costs for each activity in the network of a small construction
contract under both normal and crash conditions are given in below table. Establish the
least cost for expediting the contract. Determine the optimum duration of the contract
assuming the indirect cost amounts to SR 125/week.
Activity
A
B
C
D
E
F
G
H
I
Preceded
by
.
A
A
B
B
с
E.C
F
D, G, H
Duration
(weeks)
12
8
15
23
5
5
20
Normal
13
12
Cost
(SR)
7000
5000
4000
5000
1000
3000
6000
2500
3000
36500
Duration
(weeks)
10
6
12
Crash
23
4
4
15
11
10
Cost
(SR)
7200
5300
4600
5000
1050
3300
6300
2580
3150
38470
Transcribed Image Text:The durations and direct costs for each activity in the network of a small construction contract under both normal and crash conditions are given in below table. Establish the least cost for expediting the contract. Determine the optimum duration of the contract assuming the indirect cost amounts to SR 125/week. Activity A B C D E F G H I Preceded by . A A B B с E.C F D, G, H Duration (weeks) 12 8 15 23 5 5 20 Normal 13 12 Cost (SR) 7000 5000 4000 5000 1000 3000 6000 2500 3000 36500 Duration (weeks) 10 6 12 Crash 23 4 4 15 11 10 Cost (SR) 7200 5300 4600 5000 1050 3300 6300 2580 3150 38470
Expert Solution
steps

Step by step

Solved in 4 steps with 7 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.