The demand for subassembly S is 120 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 2 units of V, 2 units of W, and 2 units of X. Finally, each unit of U requires 1 unit of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z.
Q: 3. In the hierarchy of strategy, what purpose do corporate and business level strategies serve? Why…
A: NOTE : “Since you have posted multiple questions, we will provide the solution only to the first…
Q: 1. The drug distribution company LOS PAISAS wants to build a new warehouse in Carretera a Masaya…
A: Linear programming helps us to find the optimal solution/best outcome, given the constraints. Here…
Q: How can the scientific management principles proposed by Frederick Taylor be applied in your…
A: Scientific management principles, pioneered by Frederick Taylor, revolutionized organizational…
Q: 4. Toyco produces a line of Bonnie dolls and accessories at its plants in New York and Baltimore…
A: Find the Given details below:From/ToPittsburghDenverChicagoLos AngelesSupplyNew…
Q: 1. What risk can a business face due to a supplier and explain the foloowing risk control steps…
A: Risk management is a crucial aspect of any business operation, and it becomes even more significant…
Q: rs. On the basis of research at the hospital, Beth e E.3, estimate the time it will take to…
A:
Q: Before setting up any new venture, it is vital that a budding entrepreneur does his groundwork and…
A: To check the viability of a new business idea, a comprehensive study and analysis is done. This…
Q: The following table is a transportation matrix showing the cost ($) per unit of shipping from Plant…
A: Linear programming helps us to find the optimal solution/best outcome, given the constraints. Here…
Q: Most organizations use these to clarify the chain of command, show differentiation across functions…
A: An organisational chart is a graphic depiction of a company's structure that depicts the hierarchy…
Q: Describe how managers can manage workforce diversity.
A: Workforce diversity encompasses the array of distinctions among individuals within an organization.…
Q: What is the relationship between median income and level of education?
A: Education is the aspect of society that is concerned with the process or activity of obtaining or…
Q: The management of Madeira Computing is considering the introduction of a wearable electronic device…
A: Fixed cost$300,000Range of variable costLower$128Upper$192most likely$160Selling cost per…
Q: Cindy Jo's Hair Salon is concerned about its rising costs of supplies, energy, and labor, so it is…
A: Improved productivity helps the organization contribute to a competitive edge in the market.…
Q: The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements…
A: Find the given details below:
Q: How are ethical and legal issues related to patient safety and organizational out
A: Risk management in healthcare encapsulates a systematic approach aimed at identifying, assessing,…
Q: the team at heritage craft is considering outsourcing some of its production activities for…
A: A business that engages with a third-party service provider to manage the manufacturing or…
Q: Valencia Products makes automobile radar detectors and assembles two models: LaserStop and…
A: Max Z =125L+137SSubject to constraints:17L+13S <= 3000 ......Availability of component A6L+8S…
Q: Which of the following statements about organizational missions is FALSE? a. They indicate what a…
A: Organizational missions serve as foundational statements that articulate a company's purpose,…
Q: Know 10 internal weaknesses to see the options to overcome them, and if they are very slight or…
A: SWOT analysis specifies the analysis of the strengths and opportunities for the organization and it…
Q: A supermarket has the following minimum personnel requirements during the week. T W T F S S M 3 7 2…
A: The objective of the question is to determine the minimum number of regular employees required to…
Q: The framing department has five jobs waiting to be processed. It is now time zero and all jobs are…
A: Find the Given details below:
Q: Use the following information for the next 3 questions: A product is to take 30 hours to be…
A: Taguchi Loss FunctionThis question is based on the concept of Taguchi Loss Function. The Taguchi…
Q: Latisha Simmons, a loan processor at Wentworth Bank, has been timed performing four work elements,…
A: ElementsPerformance RatingObservations (min per…
Q: Jill wants to have immediate access to wide scale distribution. The strategy which is best is to,…
A: In the competitive business landscape, having an effective distribution strategy is crucial for any…
Q: Suppose that you solve the LP relaxation of a production problem in which you are trying to minimize…
A: If we solve the LP relaxation of a production problem, here, we will not consider any integer…
Q: Recommend a suitable hierarchical level for the purchasing and supply function at Coca-Cola. Justify…
A: Every organisation needs the purchasing and supply function to be successful, but this is…
Q: Founder of Masodi Organics on how she started a successful local beauty brand ‘We have enjoyed…
A: Masodi Organics is a beauty brand that was launched in 2018 by Liz Letsoalo. The brand aims to…
Q: Q. 1 What risk can a business face due to a supplier and what are the risk control steps that a…
A: Risk Management is the part of management that deals with controlling the risks and threats to the…
Q: Lou's Bakery has established that JIT should be used for chocolate chips due to the high probability…
A: Average demand per week = 140 cupsAverage demand per day = 140/ 5 workimng days = 28 cupsAverage(…
Q: Calculate the single factor productivities and the total productivity. Do not round intermediate…
A:
Q: If the goal is to maximize profits, how many bags of each type should be prepared? Answer is…
A: The Simplex method is a powerful algorithm in linear programming utilized to solve optimization…
Q: The worldwide rate of baggage mishandling reported by SITA (Société Internationale de…
A: Six sigma is a quality managament tool that aims to reduce the number of errors in manufacturing…
Q: You are developing a performance progress report for a project you are managing. The following…
A: Project managers can assess a project's success with the aid of earned value (EV), often referred to…
Q: Africa’s Leading Bulk Maize Supplier and Distributor We are “Amaizing” Maize Suppliers in South…
A: Maize Suppliers, a South African maize supplier, is expanding its business globally and faces…
Q: The reorder point for BB-1 is 60 sets. What level of safety stock should be maintained for BB-1? The…
A: In the question,Here, I will determine the alternative options for safety stock quantity, For each…
Q: Oleg Blokhin Sportwear uses, for the goalkeeper gloves, a time sensitive and unstable chemical…
A: Given question relates to EOQ quantity discount model.
Q: “Inventory control is one of the central activities of procurement and supply management. It is…
A: Masodi Organics is a beauty brand that was launched in 2018 by Liz Letsoalo. The brand aims to…
Q: What are three pros and three cons to current recruitment technology. How has HR technology…
A: Human resource management is an integral part of an organization. There are several functions in…
Q: Write an email of 200 - 250 words and follow the indirect approach. Here is the scenario:
A: Business communication serves as the backbone of successful organizations, enabling the seamless…
Q: DataSpan, Inc., automated its plant at the start of the current year and installed a flexible…
A: ParticularMonth 1Month 2Month 3Month 4 Move time per unit0.40.30.40.4 Process time per…
Q: Peachy Keen, Inc., makes mohair sweaters, blouses with Peter Pan collars, pedal pushers, poodle…
A: Inventory management is the aspect of production management of an organization including storing,…
Q: Identify the main stakeholder groups involved in MUFC and map their power and level of interest.…
A: Organization specifies an entity in which one or more people or individuals work together for…
Q: First Printing has contracts with legal firms in San Francisco to copy their court documents. Daily…
A: Reorder points enable data-driven decisions which helps businesses to decide when to reorder goods…
Q: What is Supply Chain Risk Management? Supply Chain Risk Management (SCRM) is the process of…
A: Supply Chain Risk Management (SCRM) is a comprehensive approach to identifying, assessing, and…
Q: Final Examination925 North Spurgeon Street, Santa Ana, CA 92701Text:…
A: “Since you have posted a question with multiple sub parts, we will provide the solution only to the…
Q: 1. Differentiate between mechanized, semi-automated, automated, and information-directed handling…
A: “Since you have posted multiple questions, we will provide the solution only to the first question…
Q: With the HIPAA law that was enacted, how does this help or hinder the laboratory staff as it relates…
A: The Health Insurance Portability and Accountability Act (HIPAA) was enacted in 1996 with the primary…
Q: Barbara Flynn is in charge of maintaining hospital supplies at General Hospital. During the past…
A: Mean lead time demand = 70 unitsStandard Deviation = 5 unitsService level = 90%
Q: what is the summary of the Ted Radio Hour Is Conflict Good For Progress? and What is Heffernan’s…
A: It takes work to have constructive conflict. It indicates that "we really prefer people who are…
Q: Read the scenario below and answer the questions that follow: Sisal is an abundantly available…
A: Outsourcing allows businesses to get work done at a lower cost, and it ensures consistent and…
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 2 images
- The demand for subassembly Sis 100 units in week 7.Each unit ofS requires 1 unit ofT and 2 units ofU. Each unit ofT requires I unit ofY, 2 units ofW, and 1 unit of X. Finally, eachunit of U requires 2 units of Y and 3 units of Z. One firm manufacturesall items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make Y, 3 weeks to make W,I week to make X, 2 weeks to make Y, and I week to make Z.a) Construct a product structure. Identify all levels, parents, and components.b) Prepare a time-phased product structure.Oh No!, Inc., sells three models of radar detector units. It buys the three basic models (E, F, and G)from a Japanese manufacturer and adds one, two, or four lights (component DLead times are one week for all items except C, which is two weeks. There are ample suppliesof the basic units (E, F, and G) on hand. There are also 10 units of B, 10 units of C, and 25 units ofD on hand. Lot-sizing rules are lot-for-lot ordering for all items except D, which must be ordered inmultiples of 100 units. There is a scheduled receipt of 100 units of D in week 1.The master schedule calls for 40 units of A in week 4, 60 units of B in week 5, and 30 units of Cin week 6. Prepare a material requirements plan for D and its parents) to further differentiate the models. D is bought from a domestic producer.Using the information in Problem(The demand for subassembly Sis 100 units in week 7.Each unit ofS requires 1 unit ofT and 2 units ofU. Each unit ofT requires I unit ofY, 2 units ofW, and 1 unit of X. Finally, eachunit of U requires 2 units of Y and 3 units of Z. One firm manufacturesall items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make Y, 3 weeks to make W,I week to make X, 2 weeks to make Y, and I week to make Z.a) Construct a product structure. Identify all levels, parents, and components.b) Prepare a time-phased product structure. ), construct agross material requirements plan.
- Each A (finished product) requires 1 of component B and 2 of component C. Each B requires 2 of part D and 1 of part E and each C requires 1 of part D and 1 of part F.If the demand for product A is 50 units., and there are 15 units of B on hand and 50 units of C, how many units of Part D will be needed?Using the information in Problem (The demand for subassembly Sis 100 units in week 7.Each unit ofS requires 1 unit ofT and 2 units ofU. Each unit ofT requires I unit ofY, 2 units ofW, and 1 unit of X. Finally, eachunit of U requires 2 units of Y and 3 units of Z. One firm manufacturesall items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make Y, 3 weeks to make W,I week to make X, 2 weeks to make Y, and I week to make Z.a) Construct a product structure. Identify all levels, parents, and components.b) Prepare a time-phased product structure. ), construct a netmaterial requirements plan using the following on-hand inventory.A product (A) consists of a base (B) and a casting (C). The base consists of a plate(P) and three fasteners (F). The lead time, current on-hand inventory and scheduledreceipts are given in the table below. All components are lot for lot. The MasterSchedule requires 100 units of product A be available in week 4 and 150 in week 6. Part Lead time On - Hand inventory Scheduled receipts A 1 20 None B 1 100 50 in Week 1 C 3 30 20 in Week 1, 30 in Week 2 P 2 0 50 in Week 1 F 3 0 30 in Week 1, 40 in Week 3 Required:A. Draw the product structure tree. B. Develop the MRP for Parts A, B, C, P, and F in order to meet the demand. Therows for MRP tables are Gross Requirement (GR), Scheduled Receipt (SR),On-Hand Inventory (OHI), Net Requirement (NR), and Planned Production (PP).
- One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; items A, B, E, and F have two-week lead times; and item D has a lead time of three weeks. Lot-for-lot (L4L) lot sizing is used for items C, E, and F; lots of size 20, 40, and 160 are used for items A, B, and D, respectively. Items A, B, D, and E have on-hand (beginning) inventories of 5, 10, 100, and 100, respectively; all other items have zero beginning inventories. We are scheduled to receive 10 units of A in week 3, 20 units of B in week 7, 40 units of F in week 5, and 60 units of E in week 2; there are no other scheduled receipts. If 20 units of A are required in week 10, use the low-level-coded bill-of-materials (product structure tree) to find thenecessary planned order releases for all components.3. The large parts of a playground A-frame (from which to hang a swing or glider) consist of a ridge pole, four legs, and two side braces. Each leg fastens to the ridge with one fastener set. Each side brace requires two fastener sets for attachment to the legs. There is one order outstanding, to make 180 frame kits. There are 500 legs and 20 ridge poles in inventory. There are no other large items in inventory, and no scheduled receipts. (a) Draw the product structure tree. (b) Calculate the net requirements to fulfill the outstanding order.Courtney Kamauf schedules production of a popular Rustic Coffee Table at Kamauf Enterprises, Inc. The tablerequires a top, four legs, 18 gallon of stain, 116 gallon of glue, 2 shortbraces between the legs and 2 long braces between the legs, anda brass cap that goes on the bottom of each leg. She has 100 gallons of glue in inventory, but none of the other components. Allitems except the brass caps, stain, and glue are ordered on a lotfor-lot basis. The caps are purchased in quantities of 1,000, stainand glue by the gallon. Lead time is 1 day for each item. Schedulethe order releases necessary to produce 640 coffee tables on days5 and 6, and 128 on days 7 and 8.
- One unit of A is made of two units of B and one unit of C. B is made of three units of Dand one unit of F. C is composed of three units of B, one unit of D, and four units of E.D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F havetwo-week lead times; and Item D has a lead time of three weeks. Lot-for-lot (L4L) lot sizingis used for Items C, E, and F; lots of size 20, 40, and 160 are used for Items A, B, andD, respectively. Items A, B, D, and E have on-hand (beginning) inventories of 5, 10, 100,and 100, respectively; all other items have zero beginning inventories. We are scheduledto receive 10 units of A in Week 3, 20 units of B in Week 7, 40 units of F in Week 5, and60 units of E in Week 2; there are no other scheduled receipts. If 20 units of A are requiredin Week 10, use the low-level-coded bill-of-materials (product structure tree) to i nd thenecessary planned order releases for all components.Each A (finished good) requires 1 of component B and 2 of component C. Each B requires 2 of part D and 1 of part E; and each C requires 1 of part D and 1 of part F. If the demand for product A is 30 units, and there are 10 units of B on hand and none of C, how many units of part D will be needed?Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. B is made of three units of E. If 50 units of Z is required to make, then how many units of D do they need? Group of answer choices 250 400 300 150 550