The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: Code Description A BCDEFGH C D Find location; determine resource requirements Requisition of lumber and sand H I Dig and grade Saw lumber into appropriate sizes Position lumber in correct locations F Nail lumber together G Put sand in and under the equipment Put dirt around the equipment Put grass all over the garden, landscape, paint Time (hrs) 20 60 100 35 20 10 20 5 30 Immediate Predecessor(s) None A << D, C F- G, H Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activities E through I of the project. ***

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter5: Network Models
Section5.3: Assignment Models
Problem 10P
icon
Related questions
Question
The City Commission of Nashville has decided to build a botanical garden and picnic area in the
heart of the city for the recreation of its citizens. The precedence table for all the activities required
to construct this area successfully is as follows:
Code Description
A
BCDEFGH
G
I
Find location; determine resource
requirements
Requisition of lumber and sand
Dig and grade
Saw lumber into appropriate sizes
Position lumber in correct locations
Nail lumber together
Put sand in and under the equipment
Put dirt around the equipment
Put grass all over the garden, landscape,
paint
Time
(hrs)
20
60
100
35
20
10
20
30
Immediate Predecessor(s)
None
A
A
B
D, C
E
F
F-
G, H
Refer to the legend for the activity that corresponds to each code.
Using the line drawing tool, draw a Gantt chart for activities E through I of the project.
Transcribed Image Text:The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: Code Description A BCDEFGH G I Find location; determine resource requirements Requisition of lumber and sand Dig and grade Saw lumber into appropriate sizes Position lumber in correct locations Nail lumber together Put sand in and under the equipment Put dirt around the equipment Put grass all over the garden, landscape, paint Time (hrs) 20 60 100 35 20 10 20 30 Immediate Predecessor(s) None A A B D, C E F F- G, H Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activities E through I of the project.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 5 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,