-SELECTION IN PRESENT ECONOMY PROBLEMS Problem 1 A contractor has a construction company that is currently handling a 2- storey residential building construction that should be completed 150 days. At present the said contractor has 100 men on the job and it is estimated that they will finish the work in 216 days. If of the 100 men, 60 are paid Php 300 a day, 30 are paid Php 350 a day and 10 are paid Php 550 a day and if for each day beyond the original 100 days, the contractor has to pay Php 1,800 liquidated damages. How many total men should the contractor have to complete the work on time and without paying any liquidated damages? If the additional men of 10 are paid Php 550 a day and the rest are paid Php 300 a day, would the contractor save money by employing more men and not paying the fine?

ENGR.ECONOMIC ANALYSIS
14th Edition
ISBN:9780190931919
Author:NEWNAN
Publisher:NEWNAN
Chapter1: Making Economics Decisions
Section: Chapter Questions
Problem 1QTC
Question
-SELECTION IN PRESENT ECONOMY PROBLEMS
Problem 1
A contractor has a construction company that is currently handling a 2-
storey residential building construction that should be completed 150 days. At
present the said contractor has 100 men on the job and it is estimated that they
will finish the work in 216 days. If of the 100 men, 60 are paid Php 300 a day, 30 are
paid Php 350 a day and 10 are paid Php 550 a day and if for each day beyond
the original 100 days, the contractor has to pay Php 1,800 liquidated damages.
How many total men should the contractor have to complete the work on time
and without paying any liquidated damages? If the additional men of 10 are paid
Php 550 a day and the rest are paid Php 300 a day, would the contractor save
money by employing more men and not paying the fine?
Transcribed Image Text:-SELECTION IN PRESENT ECONOMY PROBLEMS Problem 1 A contractor has a construction company that is currently handling a 2- storey residential building construction that should be completed 150 days. At present the said contractor has 100 men on the job and it is estimated that they will finish the work in 216 days. If of the 100 men, 60 are paid Php 300 a day, 30 are paid Php 350 a day and 10 are paid Php 550 a day and if for each day beyond the original 100 days, the contractor has to pay Php 1,800 liquidated damages. How many total men should the contractor have to complete the work on time and without paying any liquidated damages? If the additional men of 10 are paid Php 550 a day and the rest are paid Php 300 a day, would the contractor save money by employing more men and not paying the fine?
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
ENGR.ECONOMIC ANALYSIS
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:
9780190931919
Author:
NEWNAN
Publisher:
Oxford University Press
Principles of Economics (12th Edition)
Principles of Economics (12th Edition)
Economics
ISBN:
9780134078779
Author:
Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:
PEARSON
Engineering Economy (17th Edition)
Engineering Economy (17th Edition)
Economics
ISBN:
9780134870069
Author:
William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:
PEARSON
Principles of Economics (MindTap Course List)
Principles of Economics (MindTap Course List)
Economics
ISBN:
9781305585126
Author:
N. Gregory Mankiw
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-…
Managerial Economics & Business Strategy (Mcgraw-…
Economics
ISBN:
9781259290619
Author:
Michael Baye, Jeff Prince
Publisher:
McGraw-Hill Education