Refer to the Table 1 and do the following:   Calculate the Expected time, mean time. Develop the Network diagram using the expected time and use PERT Analysis to know the mean and Sd of the project. Based on these estimates and the resultant expected project duration of 69 days. The executive committee wants to know what is the probability of completing the project before a scheduled time of 68 days? How do you measure project risk exposure? Explain and propose ways to reduce the project risk exposure.

Foundations of Business (MindTap Course List)
6th Edition
ISBN:9781337386920
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Chapter9: Attracting And Retaining The Best Employees
Section: Chapter Questions
Problem 13DQ
icon
Related questions
icon
Concept explainers
Topic Video
Question

Refer to the Table 1 and do the following:

 

  1. Calculate the Expected time, mean time.
  2. Develop the Network diagram using the expected time and use PERT Analysis to know the mean and Sd of the project.
  3. Based on these estimates and the resultant expected project duration of 69 days. The executive committee wants to know what is the probability of completing the project before a scheduled time of 68 days?
  4. How do you measure project risk exposure? Explain and propose ways to reduce the project risk exposure.
Table 1: All 0,ML,P are in work days.
Most
Pessimisti
Optimistic
Duration(
0)
Activi
Likely
Durati Duration(P Predecessor
on(ML)
1
Immediate
Task Name
ty No
1 Team meeting
2 Hire Contractors
3 Network Design
4 Order Ventilation system
5 Install Ventilation system
6 Order new racks
7 Install racks
Order power supplies and
8 cables
9 Install power supplies
0.5
1.5
6
7
8
1
12
14
16
1
18
21
30
1
7
9
13
14
21
1
17
21
25
6
7
8
1
5
11
8,12
8,12
10 Install cables
6
8
10
11 Renovation of data centre
12 City inspection
13 Facilities
14 Operations/System
Operations/Telecommunicatio
15 ns
19
20
27
2,3
2,5,7
3
7
8
9
10
7
6.
10
7
8
10
16 System & applications
17 Customer service
18 Power check
7
13
10
5
6.
13
10
9,10,11
1,2,13,14,15,1
0.5
1
1.5
5
7
9
19 Install test servers
6
20 Management safety check
21 Primary systems check
22| Set date for move
23 Complete move
1
2
3
5,18,19
1.5
2
2.5
20
1
1
21
1
2
3
22
5,
Transcribed Image Text:Table 1: All 0,ML,P are in work days. Most Pessimisti Optimistic Duration( 0) Activi Likely Durati Duration(P Predecessor on(ML) 1 Immediate Task Name ty No 1 Team meeting 2 Hire Contractors 3 Network Design 4 Order Ventilation system 5 Install Ventilation system 6 Order new racks 7 Install racks Order power supplies and 8 cables 9 Install power supplies 0.5 1.5 6 7 8 1 12 14 16 1 18 21 30 1 7 9 13 14 21 1 17 21 25 6 7 8 1 5 11 8,12 8,12 10 Install cables 6 8 10 11 Renovation of data centre 12 City inspection 13 Facilities 14 Operations/System Operations/Telecommunicatio 15 ns 19 20 27 2,3 2,5,7 3 7 8 9 10 7 6. 10 7 8 10 16 System & applications 17 Customer service 18 Power check 7 13 10 5 6. 13 10 9,10,11 1,2,13,14,15,1 0.5 1 1.5 5 7 9 19 Install test servers 6 20 Management safety check 21 Primary systems check 22| Set date for move 23 Complete move 1 2 3 5,18,19 1.5 2 2.5 20 1 1 21 1 2 3 22 5,
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Foundations of Business (MindTap Course List)
Foundations of Business (MindTap Course List)
Marketing
ISBN:
9781337386920
Author:
William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:
Cengage Learning
Foundations of Business - Standalone book (MindTa…
Foundations of Business - Standalone book (MindTa…
Marketing
ISBN:
9781285193946
Author:
William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:
Cengage Learning