Question 1. Answer the following question based on the data from the data of a project in Table-1 Table 1: Project activities and durations Description Predecessors Build internal components Modify roof and floor Construct collection stack Pour concrete and install frame Build high-temperature burner Install pollution control system Install air pollution device Commissioning Activity P Q R S T U V W P, Q Q R, S b) What is the total duration of this project? The total duration of this project.... T T U Duration (days) 4 c) Identify the Critical Activities and Non-Critical Activities for this project. Critical Activities of this project. Non-Critical Activities of this project .... 4 6 10 6 5 3 a) Draw AON Network Diagram of this project and calculate the ES, EF, LS, LF and SLACKS of each activity. 5

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%
Question 1.
Answer the following question based on the data from the data of a project in Table-1
Table 1: Project activities and durations
Description
Predecessors
Build internal components
Modify roof and floor
Construct collection stack
Pour concrete and install frame
Build high-temperature burner
Install pollution control system
Install air pollution device
Commissioning
Activity
P
Q
R
S
T
U
V
W
P, Q
Q
R, S
T
b) What is the total duration of this project?
The total duration of this project.....
T
U
Duration (days)
4
c) Identify the Critical Activities and Non-Critical Activities for this project.
Critical Activities of this project.........
Non-Critical Activities of this project.
4
6
10
6
5
3
a) Draw AON Network Diagram of this project and calculate the ES, EF, LS, LF and
SLACKS of each activity.
5
Transcribed Image Text:Question 1. Answer the following question based on the data from the data of a project in Table-1 Table 1: Project activities and durations Description Predecessors Build internal components Modify roof and floor Construct collection stack Pour concrete and install frame Build high-temperature burner Install pollution control system Install air pollution device Commissioning Activity P Q R S T U V W P, Q Q R, S T b) What is the total duration of this project? The total duration of this project..... T U Duration (days) 4 c) Identify the Critical Activities and Non-Critical Activities for this project. Critical Activities of this project......... Non-Critical Activities of this project. 4 6 10 6 5 3 a) Draw AON Network Diagram of this project and calculate the ES, EF, LS, LF and SLACKS of each activity. 5
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.