Q1) Choose A or B A/ A leveling process has conducted to construct a tunnel. The following staff readings were observed successively with a level: (0.440), 0.625, 0.846, 0.975, 1.085, (0.685), 0.783, 0.926. The readings between brackets are back sights, and all the readings are inverted except at the first and last points. Enter the above readings in a page of a level book and calculate the R.L of points if the first reading was taken with a staff held on a bench mark of 50.800 m. (Use height of instrument method).

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
Q1) Choose A or B
A/A leveling process has conducted to construct a tunnel. The following staff readings were
observed successively with a level: (0.440), 0.625, 0.846, 0.975, 1.085, (0.685), 0.783,
0.926.
The readings between brackets are back sights, and all the readings are inverted except at the
first and last points. Enter the above readings in a page of a level book and calculate the R.L
of points if the first reading was taken with a staff held on a bench mark of 50.800 m. (Use
height of instrument method).
B/ In a leveling process along a longitudinal suggested profile as shown in table below,
known that the designed elevations of the points A, E, H respectively was ( 31.5 , 29.5 ,
30) m, the project required to connect these points with a straight line, according to these
information , calculate the FILL in each point.
Point
B.S
I.F.S
F.S
Distance ,m
Remark
A
1.25
В
2.18
50
C
1.78
1.93
100
1.91
1.27
150
E
1.86
200
29.02m
F
1.61
250
1.43
300
H
2.7
350
Transcribed Image Text:Q1) Choose A or B A/A leveling process has conducted to construct a tunnel. The following staff readings were observed successively with a level: (0.440), 0.625, 0.846, 0.975, 1.085, (0.685), 0.783, 0.926. The readings between brackets are back sights, and all the readings are inverted except at the first and last points. Enter the above readings in a page of a level book and calculate the R.L of points if the first reading was taken with a staff held on a bench mark of 50.800 m. (Use height of instrument method). B/ In a leveling process along a longitudinal suggested profile as shown in table below, known that the designed elevations of the points A, E, H respectively was ( 31.5 , 29.5 , 30) m, the project required to connect these points with a straight line, according to these information , calculate the FILL in each point. Point B.S I.F.S F.S Distance ,m Remark A 1.25 В 2.18 50 C 1.78 1.93 100 1.91 1.27 150 E 1.86 200 29.02m F 1.61 250 1.43 300 H 2.7 350
Expert Solution
steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Knowledge Booster
Elevations
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning