Pina Construction Company uses the percentage-of-completion method of accounting. In 2020, Pina began work under contract #E2- D2, which provided for a contract price of $2,219,000. Other details follow: Costs incurred during the year Estimated costs to complete, as of December 31 Billings during the year Collections during the year 2020 $620,490 970,510 428,000 350,000 2021 $1,429,000 -0- 2,219,000 1,471,000

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 9MC
icon
Related questions
Question

Please help me 

Pina Construction Company uses the percentage-of-completion method of accounting. In 2020, Pina began work under contract #E2-
D2, which provided for a contract price of $2,219,000. Other details follow:
Costs incurred during the year
Estimated costs to complete, as of December 31
Billings during the year
Collections during the year
2020
$620,490
970,510
428,000
350,000
2021
$1,429,000
-0-
2,219,000
1,471,000
Transcribed Image Text:Pina Construction Company uses the percentage-of-completion method of accounting. In 2020, Pina began work under contract #E2- D2, which provided for a contract price of $2,219,000. Other details follow: Costs incurred during the year Estimated costs to complete, as of December 31 Billings during the year Collections during the year 2020 $620,490 970,510 428,000 350,000 2021 $1,429,000 -0- 2,219,000 1,471,000
Prepare a complete set of journal entries for 2020 (using the percentage-of-completion method). (Credit account titles are
automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and
enter o for the amounts. For costs incurred use account Materials, Cash, Payables.)
Account Titles and Explanation
(To record cost of of construction.)
(To record progress billings.)
Debit
Credit
Transcribed Image Text:Prepare a complete set of journal entries for 2020 (using the percentage-of-completion method). (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter o for the amounts. For costs incurred use account Materials, Cash, Payables.) Account Titles and Explanation (To record cost of of construction.) (To record progress billings.) Debit Credit
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
SWFT Comprehensive Vol 2020
SWFT Comprehensive Vol 2020
Accounting
ISBN:
9780357391723
Author:
Maloney
Publisher:
Cengage
Individual Income Taxes
Individual Income Taxes
Accounting
ISBN:
9780357109731
Author:
Hoffman
Publisher:
CENGAGE LEARNING - CONSIGNMENT
SWFT Individual Income Taxes
SWFT Individual Income Taxes
Accounting
ISBN:
9780357391365
Author:
YOUNG
Publisher:
Cengage
SWFT Comprehensive Volume 2019
SWFT Comprehensive Volume 2019
Accounting
ISBN:
9780357233306
Author:
Maloney
Publisher:
Cengage