In 2024, KP Building Incorporated began work on a four-year construction project (called Cincy One). The contract price is $460 million. KP recognizes revenue on this contract over time according to percentage of completion. At the end of 2024, the following financial statement information indicates the results to date for Cincy One: INCOME STATEMENT: Gross profit (before-taxes) recognized in 2024 $ 43 million BALANCE SHEET: Accounts receivable from construction billings $ 30 million Construction in progress $ 86 million Less: Billings on construction $ (96 million) Net billings in excess of construction in progress $ 10 million Required: Compute the following, placing your answer in the spaces provided and showing supporting computations below. Note: Round your percentage answer to the nearest whole number. Enter your answers in millions (i.e., 10,000,000 should be entered as 10).
In 2024, KP Building Incorporated began work on a four-year construction project (called Cincy One). The contract price is $460 million. KP recognizes revenue on this contract over time according to percentage of completion. At the end of 2024, the following financial statement information indicates the results to date for Cincy One: INCOME STATEMENT: Gross profit (before-taxes) recognized in 2024 $ 43 million BALANCE SHEET: Accounts receivable from construction billings $ 30 million Construction in progress $ 86 million Less: Billings on construction $ (96 million) Net billings in excess of construction in progress $ 10 million Required: Compute the following, placing your answer in the spaces provided and showing supporting computations below. Note: Round your percentage answer to the nearest whole number. Enter your answers in millions (i.e., 10,000,000 should be entered as 10).
Financial Accounting Intro Concepts Meth/Uses
14th Edition
ISBN:9781285595047
Author:Weil
Publisher:Weil
Chapter8: Revenue Recognition, Receivables, And Advances From Customers
Section: Chapter Questions
Problem 48P
Related questions
Question
In 2024, KP Building Incorporated began work on a four-year construction project (called Cincy One). The contract price is $460 million. KP recognizes revenue on this contract over time according to percentage of completion. At the end of 2024, the following financial statement information indicates the results to date for Cincy One:
INCOME STATEMENT: | ||||
---|---|---|---|---|
Gross profit (before-taxes) recognized in 2024 | $ 43 | million | ||
BALANCE SHEET: | ||||
Accounts receivable from construction billings | $ 30 | million | ||
Construction in progress | $ 86 | million | ||
Less: Billings on construction | $ (96 | million) | ||
Net billings in excess of construction in progress | $ 10 | million |
Required:
Compute the following, placing your answer in the spaces provided and showing supporting computations below.
Note: Round your percentage answer to the nearest whole number. Enter your answers in millions (i.e., 10,000,000 should be entered as 10).
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 1 steps
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
Financial Reporting, Financial Statement Analysis…
Finance
ISBN:
9781285190907
Author:
James M. Wahlen, Stephen P. Baginski, Mark Bradshaw
Publisher:
Cengage Learning
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
Financial Reporting, Financial Statement Analysis…
Finance
ISBN:
9781285190907
Author:
James M. Wahlen, Stephen P. Baginski, Mark Bradshaw
Publisher:
Cengage Learning