I NEED D AND E BE ANSWERED I answered a,b,c (a) First-come-first-serve ANS: Mean flow time =17.4 Mean Process time=5,2 The number of jobs in the system =Mean flow time /Mean Process time=17.4/5.2=3.34 days (b) Earliest due date ANS Mean flow time =12.2 Mean days past due date=0 No. of jobs in the system=61/26=3.24 (c) Shortest processing time ANS Mean flow time =11.2 Mean days past due date=1.2 No. of jobs in system=56/26=2.153

Algebra: Structure And Method, Book 1
(REV)00th Edition
ISBN:9780395977224
Author:Richard G. Brown, Mary P. Dolciani, Robert H. Sorgenfrey, William L. Cole
Publisher:Richard G. Brown, Mary P. Dolciani, Robert H. Sorgenfrey, William L. Cole
Chapter2: Working With Real Numbers
Section2.3: Rules For Addition
Problem 8P
icon
Related questions
Topic Video
Question

I NEED D AND E BE ANSWERED I answered a,b,c

(a) First-come-first-serve

ANS:

Mean flow time =17.4

Mean Process time=5,2

The number of jobs in the system =Mean flow time /Mean Process time=17.4/5.2=3.34 days


(b) Earliest due date

ANS

Mean flow time =12.2

Mean days past due date=0

No. of jobs in the system=61/26=3.24


(c) Shortest processing time

ANS

Mean flow time =11.2

Mean days past due date=1.2

No. of jobs in system=56/26=2.153


(d) Which rule should be used, in your opinion? Why?
(e) The head mechanic at the production facility wants to perform maintenance
on the bottleneck workstation used to process the jobs above. The
mechanic insists the maintenance needs to be performed before day 45,
and has indicated that the maintenance will take 3 days to complete and
will take the workstation offline. Considering it is still day 13, when is
the best time to perform the maintenance? (Hint: Treat the maintenance
as though it is a new job.)

1.
A company has five jobs awaiting processing at a bottleneck work-
station in a production facility. The day the job was received, its processing
time and due date are given in the following table. It is now the beginning of
day 13.
Day Job
Job was Received
ITTI
Job Processing Job Due
Time (days)
Day
1
45
B
8
28
7
2
23
10
9.
35
12
1
21
Calculate the average throughput time and, for each job, the number of days
overdue using the following priority sequencing rules:
Transcribed Image Text:1. A company has five jobs awaiting processing at a bottleneck work- station in a production facility. The day the job was received, its processing time and due date are given in the following table. It is now the beginning of day 13. Day Job Job was Received ITTI Job Processing Job Due Time (days) Day 1 45 B 8 28 7 2 23 10 9. 35 12 1 21 Calculate the average throughput time and, for each job, the number of days overdue using the following priority sequencing rules:
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Hypothesis Tests and Confidence Intervals for Means
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, statistics and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Algebra: Structure And Method, Book 1
Algebra: Structure And Method, Book 1
Algebra
ISBN:
9780395977224
Author:
Richard G. Brown, Mary P. Dolciani, Robert H. Sorgenfrey, William L. Cole
Publisher:
McDougal Littell
Intermediate Algebra
Intermediate Algebra
Algebra
ISBN:
9780998625720
Author:
Lynn Marecek
Publisher:
OpenStax College