Egay Construction Corporation contracted with the province of Pampanga to construct a bridge at a contract price of P16,000,000. Egay Corporation expects to earn P1,520,000 on the contract. The percentage of completion method is to be used and the completion stage is to be determined by estimates made by the engineer. The following schedule summarizes the activities of the contract for years x0-x2. Cost Year xo x1 x2. Estimate Cost to Incurred Complete P4,600,000 P9,640,000 4,500,000 5,100,000 5,250,000 0 Engineer's Estimate of Billings xo a. P545,600; p b. P545,600; c. P1,760,000; d. P1,760,000; Completion 31% 58% 100%) A 10% retainer accounts for the difference between billings and collections. Under the percentage of completion method, using the engineer's estimate as the measure of completion to be applied to revenues and costs, how much is the gross profit earned each year? P1,044,000; P6,400,000; P1,800,000; x1 x2 P 498,400; P 606,000 Collection on Contract on Billings P5,000,000 P4,500,000 6,000,000 5,400,000* 5,000,000 6,100,000 P1,044,000 P1,650,000 P1,650,000

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
Egay Construction Corporation contracted with the province of
Pampanga to construct a bridge at a contract price of P16,000,000. Egay
Corporation expects to earn P1,520,000 on the contract. The percentage
of completion method is to be used and the completion stage is to be
determined by estimates made by the engineer. The following schedule
'summarizes the activities of the contract for years x0-x2.
Estimate
Cost to
Cost
Year Incurred
х0
P4,600,000
4,500,000
5,250,000
xl
x2
Engineer's
Estimate of
Complete
P9,640,000
5,100,000
-0-
x0
a. P545,600;
b. P545,600;
Billings
Completion
31% 71
58%
100%
60
*A 10% retainer accounts for the difference
collections.
between billings and
br
Under the percentage of completion method, using the engineer's estimate
as the measure of completion to be applied to revenues and costs, how
much is the gross profit earned each year?id
x1
x2
P 498,400; P 606,000
P1,044,000;
c. P1,760,000;
P6,400,000;
d. P1,760,000; P1,800,000;
Collection
on Contract on Billings
P5,000,000 P4,500,000*
6,000,000 5,400,000*
5,000,000. 6,100,000
P1,044,000
P1,650,000
P1,650,000
Transcribed Image Text:Egay Construction Corporation contracted with the province of Pampanga to construct a bridge at a contract price of P16,000,000. Egay Corporation expects to earn P1,520,000 on the contract. The percentage of completion method is to be used and the completion stage is to be determined by estimates made by the engineer. The following schedule 'summarizes the activities of the contract for years x0-x2. Estimate Cost to Cost Year Incurred х0 P4,600,000 4,500,000 5,250,000 xl x2 Engineer's Estimate of Complete P9,640,000 5,100,000 -0- x0 a. P545,600; b. P545,600; Billings Completion 31% 71 58% 100% 60 *A 10% retainer accounts for the difference collections. between billings and br Under the percentage of completion method, using the engineer's estimate as the measure of completion to be applied to revenues and costs, how much is the gross profit earned each year?id x1 x2 P 498,400; P 606,000 P1,044,000; c. P1,760,000; P6,400,000; d. P1,760,000; P1,800,000; Collection on Contract on Billings P5,000,000 P4,500,000* 6,000,000 5,400,000* 5,000,000. 6,100,000 P1,044,000 P1,650,000 P1,650,000
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education