Draw the Critical Path Method (CPM) network diagram and highlight the critical path for activities shown in Table 1(a). Perform the CPM calculation using the forward pass and backward pass methods and complete Table 1(b).   Draw a resource profile (histogram) following the scenarios below and determine how to level the resources. Give your comments on the resource profile.   Only 10 labourers available at any time Only 8 labourers available, but a peak use of 10 labourers is allowed for one time (one day) only Table 1(a) / Jadual 1(a) Activity / Aktiviti Activity Description / Penerangan aktiviti IPA* Duration (Days) / Tempoh (Hari) Labour / Buruh A Excavation & foundation / Pengorekan & asas - 6 4 B SOG A 3 3 C Framing / Pembingkaian B 10 4 D Plumbing / Perpaipan B 4 2 E Electrical wiring / Pendawaian elektrik C 3 3 F Drywall / Dinding kering C 5 3 G HVAC C 3 4 H Roof / Bumbung C 5 3 I Paint / Mengecat F 4 2 J HVAC Finish / Kemasan HVAC G, H 2 2 K Flooring / Lantai D, I 4 3 L Electrical finish / Kemasan elektrik E, H 1 2 M Punch list & cleanup / Senarai punch & pembersihan J, K, L 1 2     *Immediately Preceding Activities / Aktiviti Mendahului Serta-merta Table 1(b) / Jadual 1(b)   ID Duration (days)/ Tempoh (hari) ES EF LS LF TF FF A 6             B 3             C 10             D 4             E 3             F 5             G 3             H 5             I 4             J 2             K 4             L 1             M 1

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
  1. Draw the Critical Path Method (CPM) network diagram and highlight the critical path for activities shown in Table 1(a). Perform the CPM calculation using the forward pass and backward pass methods and complete Table 1(b).

 

  1. Draw a resource profile (histogram) following the scenarios below and determine how to level the resources. Give your comments on the resource profile.

 

  1. Only 10 labourers available at any time
  2. Only 8 labourers available, but a peak use of 10 labourers is allowed for one time (one day) only

Table 1(a) / Jadual 1(a)

Activity /

Aktiviti

Activity Description / Penerangan aktiviti

IPA*

Duration (Days) /

Tempoh (Hari)

Labour / Buruh

A

Excavation & foundation / Pengorekan & asas

-

6

4

B

SOG

A

3

3

C

Framing / Pembingkaian

B

10

4

D

Plumbing / Perpaipan

B

4

2

E

Electrical wiring / Pendawaian elektrik

C

3

3

F

Drywall / Dinding kering

C

5

3

G

HVAC

C

3

4

H

Roof / Bumbung

C

5

3

I

Paint / Mengecat

F

4

2

J

HVAC Finish / Kemasan HVAC

G, H

2

2

K

Flooring / Lantai

D, I

4

3

L

Electrical finish / Kemasan elektrik

E, H

1

2

M

Punch list & cleanup / Senarai punch & pembersihan

J, K, L

1

2

 

 

*Immediately Preceding Activities / Aktiviti Mendahului Serta-merta

Table 1(b) / Jadual 1(b)

 

ID

Duration (days)/

Tempoh (hari)

ES

EF

LS

LF

TF

FF

A

6

 

 

 

 

 

 

B

3

 

 

 

 

 

 

C

10

 

 

 

 

 

 

D

4

 

 

 

 

 

 

E

3

 

 

 

 

 

 

F

5

 

 

 

 

 

 

G

3

 

 

 

 

 

 

H

5

 

 

 

 

 

 

I

4

 

 

 

 

 

 

J

2

 

 

 

 

 

 

K

4

 

 

 

 

 

 

L

1

 

 

 

 

 

 

M

1

 

 

 

 

 

 

 

Activity/
Aktiviti
A
B
с
D
E
F
G
H
T
J
K
L
M
Activity Description /
Penerangan aktiviti
Excavation &
foundation /
Pengorekan & asas
SOG
Framing/
Pembingkaian
Plumbing / Perpaipan
Electrical wiring/
Pendawaian elektrik
Drywall / Dinding kering
HVAC
Roof / Bumbung
Paint / Mengecat
HVAC Finish /
Kemasan HVAC
Flooring / Lantai
Electrical finish /
Kemasan elektrik
Punch list & cleanup /
Senarai punch &
pembersihan
IPA*
A
B
B
с
с
с
с
F
G, H
D, I
E, H
J, K, L
Duration (Days)/
Tempoh (Hari)
6
3
10
4
3
5
3
5
4
2
4
1
1
Labour /
Buruh
4
3
4
2
3
3
4
3
2
2
3
2
2
Transcribed Image Text:Activity/ Aktiviti A B с D E F G H T J K L M Activity Description / Penerangan aktiviti Excavation & foundation / Pengorekan & asas SOG Framing/ Pembingkaian Plumbing / Perpaipan Electrical wiring/ Pendawaian elektrik Drywall / Dinding kering HVAC Roof / Bumbung Paint / Mengecat HVAC Finish / Kemasan HVAC Flooring / Lantai Electrical finish / Kemasan elektrik Punch list & cleanup / Senarai punch & pembersihan IPA* A B B с с с с F G, H D, I E, H J, K, L Duration (Days)/ Tempoh (Hari) 6 3 10 4 3 5 3 5 4 2 4 1 1 Labour / Buruh 4 3 4 2 3 3 4 3 2 2 3 2 2
ID
ABCDEFGH
А
с
I
J
K
L
M
*Immediately Preceding Activities / Aktiviti Mendahului Serta-merta
Table 1(b) / Jadual 1 (b)
EF LS
Duration (days)/ ES
Tempoh (hari)
6
3
10
4
3
5
3
5
4
2
4
1
1
LF
TF
FF
Transcribed Image Text:ID ABCDEFGH А с I J K L M *Immediately Preceding Activities / Aktiviti Mendahului Serta-merta Table 1(b) / Jadual 1 (b) EF LS Duration (days)/ ES Tempoh (hari) 6 3 10 4 3 5 3 5 4 2 4 1 1 LF TF FF
Expert Solution
steps

Step by step

Solved in 10 steps with 13 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.