Consider 8 jobs with processing times, due dates as shown below: Find the optimal sequence using the four sequencing rules; (FIFO, DD, SOT, LIFO). Based on minimizing the jobs average time as well as meeting the deadlines (Due Date) allocated to each job, Explain your final decision. Job(1) Processing time (days) Due Date (days) 1 5 15 2 8 10 3 6 13 4 3 25 5 10 20 6 14 40 7 8 7 3 45 50

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question
Consider 8 jobs with processing times, due dates as shown below: Find the optimal sequence
using the four sequencing rules; (FIFO, DD, SOT, LIFO).
Based on minimizing the jobs average time as well as meeting the deadlines (Due Date) allocated to each
job, Explain your final decision.
Job(1)
Processing time (days)
Due Date (days)
1
5
15
2
8
10
3
6
13
4
3
25
5
10
20
619
14
40
7
8
7
3
45 50
Transcribed Image Text:Consider 8 jobs with processing times, due dates as shown below: Find the optimal sequence using the four sequencing rules; (FIFO, DD, SOT, LIFO). Based on minimizing the jobs average time as well as meeting the deadlines (Due Date) allocated to each job, Explain your final decision. Job(1) Processing time (days) Due Date (days) 1 5 15 2 8 10 3 6 13 4 3 25 5 10 20 619 14 40 7 8 7 3 45 50
Expert Solution
steps

Step by step

Solved in 6 steps with 6 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,