Consider 8 jobs with processing times, due dates as shown below: Find the optimal sequence using the four sequencing rules; (FIFO, DD, SOT, LIFO). Based on minimizing the jobs average time as well as meeting the deadlines (Due Date) allocated to each job, Explain your final decision. Job(1) Processing time (days) Due Date (days) 1 5 15 2 8 10 3 6 13 4 3 25 5 10 20 6 14 40 7 8 7 3 45 50
Q: I only need help with part C please.... The Metropolitan Bus Company (MBC) purchases diesel fuel…
A: Maximum inventory is largest stock level hold in the company. It is calculated with following…
Q: Source nodes 1 2 3 4 1000 O 1000 Sink nodes O 950 1 O 975 O 900 10 Demand 25 16 18 17 2 20 15 22 9…
A: Find the Given details below: Transportation table Source node Sink node 1 2 3 Supply 1…
Q: a) Using a 2-year moving average, the forecast for year 6= 3750 miles (round your response to the…
A: Forecasting is a technique used to predict future outcomes on the basis of past data. Business…
Q: Question No. 14 A stock item has a count of 792 units, a cost of R3 and carrying charge of 20%. If…
A: Given: Days of supply = Average inventory / Daily consumption Average inventory = 792 Daily…
Q: Demand for walnut fudge ice cream at the Sweet Cream Dairy can be approximated by a normal…
A: 1.28 Given: Mean weekly demand = 21 Standard deviation (s) = 5 Lead time (L) = 8 Z- score…
Q: Imagine a company that has a corporate strategic goal of operating a new food delivery service line.…
A: Imagine a company that has a corporate strategic goal of operating a new food delivery service line.…
Q: A wallpaper company estimates the demand for a certain pattern to be 925 rolls per year. It costs…
A: Given: Annual demand (D) = 925 Setup cost (S) = 750+150 Holding cost (H)= 4
Q: Office Automation Inc., developed a proposal for implementing a software system that will…
A: NOTE: We are allowed to do first 3 sub-parts only. In project management, a critical path is the…
Q: The following gives the number of accidents that occurred on Florida State Highway 101 during the…
A: Given data is
Q: The Axis car rental company allows its customers to pick up a rental car at one location and return…
A: The transportation model is used to calculate the minimum cost of the route by selecting different…
Q: A project is scheduled to complete in six months duration. There are two activities in the project.…
A: Actual cost of Activity 1 = AC1 = SAR 300,000 Actual cost of Activity 2 = AC2 = SAR 200,000 Planned…
Q: 3. Southeastern Bell stocks a certain switch connector at its central warehouse for supplying…
A: Given data is Annual demand (D) = 15000 units Holding cost (H) = $24 Ordering cost (S) = $75 Working…
Q: Hart Manufacturing makes three products. Each product requires manufacturing operations in three…
A: As per the given instructions, the decision variables are as follows. P1 = Units of product 1…
Q: 1) A construction company needs to move heavy equipment from city 1 to city 9, where the numbers on…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: The average daily demand and standard deviation of daily demand for a product is 800 and 12…
A: Daily demand = d = 800 units Standard deviation of daily demand = σ = 12 Replenishment lead time = L…
Q: Arnold Tofu owns and operates a chain of 12 vegetable protein “hamburger” restaurants in northern…
A: An estimate of the line that depicts the actual but unidentified linear connection between the two…
Q: What is the tool used by a project manager to check whether the resources are allocated correctly…
A: There are several tools available nowadays for resource management and overall every tool is similar…
Q: Question 8 Part G A large company is planning to purchase equipment costing $220,000 and will…
A:
Q: The following data relates to the number of passengers the Mussina border post between Zimbabwe and…
A: Find the given details below: Given details Maximum Passengers (Design Capacity) 5000…
Q: A renovation of the gift shop at Orlando Amway Center has six activities (in hours). In the…
A: Given Data-
Q: 1. Supplier management in a lean system A. means an increase in the number of suppliers for each…
A: Supplier management is one of the most important aspects of manufacturing. It is a critical part of…
Q: An Assembly line with 17 tasks is to be balanced. The longest task is 2.2 minutes, and the total…
A: An assembly line indicating the task allocation to the workstation based on different heuristics.…
Q: Identify the decision alternatives and uncertain conditions surrounding them? What is the optimal…
A: Decision-making is the process of selecting a course of action from among multiple choices. This can…
Q: Consider the following model. Maximize subject to x₂ + x₂ x1 x₂ + x3 Z = 4x₁ + 8x₂ + 10x3 + 6x4 x3 +…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: I am not sure why i got it marked incorrect
A: Given data is Battery pack Production quantity PT-100 202,000 PT-200 101,000 PT-300 149,000…
Q: 1.What are the decision variables 2.What is the objective functions 3. What are the constraints and…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: Find the optimal solution to this linear programming problem. 5X + 3Y (x, y) = Max s.t. 2X + 3Y≤ 35…
A: Given data:
Q: a) Using a 2-year moving average, the forecast for year 6 = number). miles (round your response to…
A: Moving averages are a type of average that is computed by taking the average of a set of…
Q: a. Determine each alternative's break-even point in units. b. At what volume of output would the two…
A: Breakeven units are the units that need to be sold in order to break even. Breakeven units are…
Q: describe how puchasing interfaces with other departments
A: The Purchasing interfaces with departments, the other departments includes, marketing department…
Q: What factors can affect the selection of manufacturing process of a firm ?
A: Introduction: Process selection is one of the most important decisions in every commercial…
Q: What type of inventory are groceries?
A: Grocery stores are a place where people can find food and other products. They are places where…
Q: d Minimization problems ***When using the simplex method, what is the difference between ma
A: The Simplex method is a technique for manually solving linear programming models employing pivot…
Q: 17. Which of the following is true for a critical activity?
A: Critical activity refers to an activity that has a slack value of 0. Slack = LS - ES or LF - EF
Q: 13.2 A company manufactures component parts for machine tools in North America and ships then to…
A:
Q: analyse the role of operations management capacity planning and control in a clothing business and…
A: Operations management is the process of designing, implementing, and controlling the production and…
Q: The Brew House needs to decide which of two coffee maker designs is better environmentally. Using…
A: Revenue is limited to earnings from core company operations. Because it is the large figure at the…
Q: When a company in the U.S. contracts some of their jobs to other firms. These firms may be in the…
A: Manufacturing Offshoring is the act of locating parts of a company's operations or services abroad…
Q: 8. The capacity of a process is determined by OA. the flow of materials. OB. the maximum of the…
A: A process is any sequence of steps that produces a specific outcome.
Q: C&A's production sequence is making 200 pounds of wheat first, then switching to 100 pounds of white…
A: Given that the initial Inventory for white bread=200 pounds The Ending inventory for white bread=100…
Q: Project management tools and techniques........................ Are used to select the…
A: Are used to select the appropriate and potential projects:- Project management tools and techniques…
Q: Zokit Industries (ZI) is a New York City based company that manufactures and distributes Turkish…
A: No is the number of boxes of Ortakoy flavor NB is the number of boxes of Beyoglu flavor The…
Q: An accounting firm is capable of processing 20 EZ tax forms per day, and the average number of forms…
A: Queuing theory is the study of waiting for lines/queues. This model helps to determine the length…
Q: Indicate three companies in which internal and external quality controls are carried out; the…
A: https://portal.bartleby.com/questions/7b37d639-1260-4d59-8a99-22eb85ac4d06/answer Indicate three…
Q: analyse the role of operations management capacity planning and control for Ford motors and explain…
A: Capacity planning is the process of forecasting the demand for a product or service and determining…
Q: 2. Production Schedule is a Mess Henry Gantt greatly contributed to the classical management system…
A: Henry Gantt was a famous mechanical engineer who derived many concepts and contributed to the field…
Q: With the aid of a Diagram explain the transformation process in Operation Management.
A: Any process that takes one or more inputs, modifies and adds value to them, and then produces…
Q: In the problem on excel : 1.What are the decision variables 2.What is the objective functions 3.…
A:
Q: The production process shown below consists of five stages. The numbers in parentheses are the times…
A: Find the Given details below: Given details: Stage Time taken for an unit A 4 minutes B 3…
Q: 8. One bag of "Fertilizer A" contains 2 units of phosphorus, 5 units of nitrogen, and 3 units of…
A: Based on the given information, the LP formulation will be as follows. Objective Function:Minimize…
Step by step
Solved in 6 steps with 6 images
- At the campus copy shop, six jobs have arrived in the order shown (A, B, C, D, E, and F) at the beginning of the day 1 (today, which is a work day). All of the jobs are due at various times today. Your job is to evaluate four common sequencing rules. JOB DUE (IN HOURS) DURATION (HOURS REQUIRED) A 8 (this job is due in 8 hours) 1.65 B 5.5 (this job is due in 5.5 hours) 1.20 C 4.5 (this job is due after lunch in 4.5 hours) 0.85 D 6 (this job is due in 6…What are the advantages and disadvantages of the shortest processing time (SPT) rule?Currently a company that designs Web sites has six customers in its backlog. The time since the order arrived, processing time, and promised due dates are given in the following table. Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 6 18 48 B 4 22 52 C 1 30 70 D 10 14 28 E 7 12 56 F 5 20 62 Develop a schedule by using the first-come, first-served (FCFS) rule and calculate the average flow time and average days past due for the schedule. Develop a schedule by using the earliest due date (EDD) rule and calculate the average flow time and average days past due for the schedule. Comment on the performance of the FCFS and EDD rules relative to average flow time and average days past due.
- The following six jobs are to be scheduled on a single machine: Job 1 2 3 4 5 6 Processing time (min.) 110 120 220 90 180 80 Suppose the jobs are processed in FCFS numerical order. Compute the makespan, flow time for each job, and overall average flow time. Round your answers to the nearest whole number. Job Flow Time (min) 1 2 3 4 5 6 Makespan: minutes Average flow time: minutes In what order would the jobs be processed using the SPT rule? The SPT sequence is - - - - - . Compute the average flow time after each job is completed. Round your answer to the nearest whole number. Average flow time: minutes Compare this answer with your answer to part a. The minimizes flow time and gets the most work done in the least amount of time.At the University Hospital, five blood samples must bescheduled through a blood-testing laboratory. Eachsample goes through up to four different testing stations.The times for each test and the due dates for eachsample are as follows:Sample Test Station/Hours Due Date (hours)1 A/1, B/2, C/3, D/1 62 B/2, C/3, A/1, D/4 103 C/2, A/3, D/1, C/2 84 A/2, D/2, C/3, B/1 145 D/2, C/1, A/2, B/4 12a. Using a Gantt chart, schedule these five samples in priority order of earliest due date first.b. Assume that the capacity of each test station (A, B, C and D) is doubled. Prepare an FCS for this situation.c. What are the bottleneck work centers in part a of the problem. Suggest capacity additions that might be needed.In her last semester at SPC, Polly Hedron needs to take Statistics, Composition 2, Ethics, and Physics. Because Polly is registering early, she has 14 choices for her section of Statistics, 19 choices for her section of Composition, 17 choices for her section of Ethics, and 18 choices for her section of Physics. From how many possible schedules can Polly choose? (You may presume that none of these sections interfere with each other) Your Answer:
- The following 5 overhaul jobs are waiting to be processed at Avianic's Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days. Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.) Job CR Job Due Date Duration (days) 103 103 214 10 205 205 223 309 309 217 11 412 219 412 517 216 15 517 Assume that all jobs arrived on day 180; today's date is 200.In her last semester at SPC, Polly Hedron needs to take Statistics, Composition 2, and Ethics. Because Polly is registering early, she has 17 choices for her section of Statistics, 11 choices for her section of Composition, and 19 choices for her section of Ethics. From how many possible schedules can Polly choose? (You may presume that none of these sections interfere with each other) Your Answer:A machine center in a job shop for a local fabrication company has five unprocessed jobs remaining at a particular point in time. The jobs are labeled A, B, C, D, and E in the order that they entered the shop. The respective processing times and due dates are given in the table below. What is the sequence the of jobs by CR rules? Job Processing Time Due Date A 10 32 B. 55 34 C. 11 31 60 35
- Dan's Auto Detailing business performs two major activities: exterior cleanup and interior detailing. Based on the size of car and condition, time estimates for six cars on Monday morning are as shown in the accompanying table. Car Number 1 5 6 Exterior Interior 55 75 4 65 35 50 60 45 90 35 40 a. Sequence the cars so that all exterior cleanup is done first and total completion time is minimized. The sequence is -Select-- -Select- -Select- -Select- -Select-- -Select- 2 3 80 20At an auto shop, six jobs are currently in queue. Job A B C D E F Arrival order 1 2 3 4 5 6 Processing time (minutes) 33 27 36 28 21 23 Using the shortest processing time scheduling approach, what is the average inventory of jobs in the system? Assume that processing of jobs will start immediately. Note: Round your answer to 2 decimal places.The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: Job W X Y Z Processing Time (hrs) 4 3 2 1 If he uses the shortest processing time first priority rule to schedule these jobs, what will be the average number of jobs in his shop today? Multiple Choice 0 1 2 3 Due (hrs from now) 4 5 2 1 4