Colorado Construction Co., a private company that reports under ASPE, was contracted by a provincial government to build a bridge over a river. The government owns the land on both sides of the river and it agreed to pay Colorado a fixed fee of $29,750,000 for the bridge. Colorado initially estimated the cost to build the bridge to be $21,500,000. Colorado's year end is December 31. Work began under the contract on July 1, 2019 and was completed on September 30, 2021. Construction activities are summarized below by year: Year Construction costs Estimated costs to Progress billings during the year collected during Amount incurred during complete (excludes already incurred costs the year the year 2019 $8,250,000 $13,000,000 $10,000,000 $12,000,000 2020 12,000,000 5,000,000 10,000,000 6,000,000 2021 5,250,000 9,750,000 11,750,000
Q: __________1. Loss on repayment of government grant on January 1, 2023 if the company accounts for…
A: Answer 1. If the government grant is accounted as deferred income, then deferred income will be…
Q: On January 1, 2018, Liquid Company accepted a long-term construction project for an initial contract…
A: The revenue of reporting period should be recognized in the current reporting period. Timeliness…
Q: Indiana Co. began a construction project in 2021 with a contract price of $160 million to be…
A: Calculate the gross profit recognized in 2021. Working note: Calculate the percentage of…
Q: On December 10, 2020 the Elm Street project was completed and the contractor for the project…
A: Journal entries in Street improvement fund Date Particulars Debit Credit December 10 Reserve…
Q: displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a…
A: Solution 5: Computation of revenue and gross profit for given situation is as under:
Q: On January 1, 2022, Annibelle Company received a grant of P9,000,000 from the foreign government in…
A: Government grants are grants received by the company from government in monetary form, where these…
Q: In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Requirement 4 : 2018 2019 2020 Revenue $ 2,800,000 $ 3,692,964 $…
Q: ABC Co., a private contractor, wins a bid to construct an expressway for provincial government,…
A:
Q: YEYE Company began operations on January 2, 2021. During the year, the company entered into a…
A: Percentage of Completion Method In the percentage of completion method the benefits which are…
Q: Abot Company, a private contractor, wins a bid to construct a railway for the government. The terms…
A: All amounts are in P.
Q: Indiana Co. began a construction project in 2021 with a contract price of $150 million to be…
A: Indiana Co. began a construction project in 2021 with a contract price of $150 million to be…
Q: At the beginning of 2021, Florida Road Construction entered into a contract to build a road for the…
A: Under Completed contract method , all revenue and gross profit is recognised only after completion…
Q: On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to…
A:
Q: In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Introduction Accounting for Construction costs Works under construction is usually carried out in…
Q: On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to…
A: Working Note: Year 2018 2019 Accounts receivable at beginning $ - $…
Q: Hermes Co., a private company, enters into a service concession arrangement whereby Hermes…
A: In this problem we have given the contract cost of building…
Q: On January 1, 2020, San Juan Builders Inc. accepted a long-term construction project to build a…
A: SOLUTION- CONSTRUCTION CONTRACT IS A MUTUAL OR LEGALLY BINDING AGREEMENT BETWEEN TWO PARTIES BASED…
Q: Diamond Construction which has a calendar year end, has entered into a non-cancellable fixed priced…
A: Calculation for percentage of completion 2019 2020 2021 Cost incurred upto date (A) 1,850,000…
Q: Abot Company, a private contractor, wins a bid to construct a railway for the government. The terms…
A: Under the Contract costing, there is a contract made between the parties in respect of performing…
Q: On January 1, 2020, San Juan Builders Inc. accepted a long-term construction project to build a…
A: Construction Contract: A construction contract is a legal agreement between a customer and a general…
Q: The terms of the arrangement require the operator to: Construct a road-completing construction…
A: The assets which cannot be touched, non- monetary assets and does not have physical existence are…
Q: On January 1, 2018 The Village of Port Jefferson engaged to Frog Construction company to construct a…
A: Answer A)
Q: Indiana Co. began a construction project in 2018 with a contract price of $162 million to be…
A: Cost Accounting- It is branch of that ascertains cost associated with the production of certain…
Q: A contractor enters into a contract for the expansion of an existing two-lane highway to a…
A: In the given situation, the contractor will recieve the award fee only if he completes the project…
Q: What amount of income from the government grant is recognized for the current year?
A: Grant is the government aid which is given by the government to the company in order to support and…
Q: On January 1, 2019, Munich Co. received a grant of P10,000,000 from the government of USA for the…
A: solution concept under the gross method the grant received is shown as the deferred income and the…
Q: On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to…
A: NOTE : As per BARTLEBY guidelines, when multiple sub parts of the question are given, then first…
Q: On January 1, 2018, Liquid Company accepted a long-term construction project for an initial contract…
A: Contract Revenue = % of completed during the year/ Total Contract value % of completed during the…
Q: As of Jan. 1, 2020, ABC Corporation is constructing a new facility located in a community that has…
A: Government Grant related to assets recognized in profit & loss account over the useful life of…
Q: On January 1, 2015, MERKS Company received a grant of P25,000,000 form the American government in…
A: Expenditures are the total expenses incurred by the firm during an accounting period. It includes…
Q: To encourage entities to expand their operations in a specified development zone, where it is…
A: The accrual concept is one of the key concepts in accounting and it is based on the belief that the…
Q: ABC Co., a private contractor, wins a bid to construct an expressway for a provincial government,…
A: As per the Provision of PFRS 115 revenue from contract with customers, revenue can be recognize on…
Q: A contractor enters into a contract for the expansion of an existing two-lane highway to a…
A: The award fee is dependant on timely completion or non-completion of the contract.
Q: In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Construction Contract: An agreement for construction reflects, according to the general conditions…
Q: Taylor Construction Inc. signed a contract with FSU to build a student residential building with two…
A: Accounting is a process of recording transactions and preparing financial statements of the firm. It…
Q: [The following information applies to the questions displayed below.] In 2021, the Westgate…
A:
Q: If Dr. Superhook uses IRR to evaluate its opportunities, under what values of the discount rate…
A: Internal rate of return (IRR) refers to the rate of an opportunity at which the Net present value…
Q: On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to…
A: "Since you have posted a question with multiple sub parts, we will solve first three sub parts for…
Q: On March 1, 2021, AST Corporation contracted to build two buildings for a total contract price of…
A: Solution: Lumpsum price allocated to Building no 1 = P27*20 / 30 = P18 M
Q: In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Capital wip=Cost incurred/total expected cost*total revenue
Q: On January 1, 2021, MARCOS Company entered into a contract for the construction of a building at an…
A: Contract price: Original price 2,000,000 + Increased by 2,500,000 Contract…
Q: [The following information applies to the questions displayed below.] In 2021, the Westgate…
A: Step 2 in solution
Q: In 2019, Tarlo Company agrees to construct a highway for Brice County over a 3-year period (2019…
A:
Q: On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to…
A: “Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to…
A: Note: “Since you have posted a question with multiple sub-parts, we will solve first three sub-parts…
Q: On January 1, 2021, Citimart Company was granted by a local government authority 5,000 hectares of…
A: Government Grants: Government grants or assistance are usually provided to enterprises in cash or…
Q: In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Journal entries refers to the systematic documentation of the financial transactions of a company in…
Q: On January 1, 2021, Annibelle Company received a grant of P9,000,000 from the foreign government in…
A: Government grants are the amounts or assistance that is received by organisation from the…
Step by step
Solved in 5 steps with 5 images
- In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed In 2026. Information related to the contract is as follows: Cost Incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the Journal below, complete the necessary Journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs Incurred). 2-b. In the Journal below, complete the necessary Journal entries for the year 2025 (credit "Cash, Materials, etc." for construction costs Incurred). Cost Incurred during the year Estimated costs to complete as of year-end 2-c. In the Journal below, complete the necessary…The terms of the arrangement require the operator to: Construct a road-completing construction within two years Maintain and operate the road for three years Resurface the road when the original surface has deteriorated below a specified condition. The operator estimates that it will have to undertake the resurfacing at the end of year 4. The government grants the operator the right to collect toll fees from road users. The contract ends in year 5. The operator makes the following estimates: Year Contract Cost Stand-alone selling price Construction Services 1 70 Forecast cost +10% 2 80 Forecast cost +20% Operation Services Road resurfacing 3-5 25 Forecast cost +30% 4 15 Forecast cost +10% Compute the carrying amount of intangible asset at the end of year 2.The terms of the arrangement require the operator to: Construct a road-completing construction within 2 years Maintain and operate the road for 3 years Resurface the road when the original surface has deteriorated below a specified condition. The operator estimates that it will have to undertake the resurfacing at the end of Year 4. The government grants the operator the right to collect toll fees from road users. The contract ends in Year 5. The operator makes the following estimates: Construction cost Stand-alone selling price Forecast cost +10% Forecast cost +20% Forecast cost +30% Forecast cost +10% Construction Services Year 1 70 80 |Operation Services Road Resurfacing 3-5 4 25 15 Compute the carrying amount of intangible asset at the end of Year 2.
- In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs incurred). 2024 $ 2,739,000 5,561,000 2,300,000 2,100,000 Cost incurred during the year Estimated costs to complete as of year-end 2025 $ 3,735,000 1,826,000 4,174,000 3,900,000 2024 $ 2,430,000 5,630,000 2-b. In the journal below, complete the necessary journal entries for the year…On January 1, 2018 The Village of Port Jefferson engaged to Frog Construction company to construct amunicipal office complex. The three-year a to receive 10 million in cash payments from the city in threeinstallments: 25% when the project was 30% complete; 25% when the project was 60% complete; and50%when the project was fully complete. The contract required that Frog's completion estimates be certifiedby an independent consultant before payments were made.During the first year of the contract, Frog completed 30% of the contract and incurred costs of 2,490,000.During the second year, the project was certified as being 60% complete and Frog incurred costs of3,100,000.During the third year, Frog completed the project and incurred costs of 3,110,000.Assuming Frog had no other revenues or expenses, determine the profit on construction for 2018, 2019,and 2020 under the following methods: A. Percentage Calculation B. Completed ContractSupplier Corp. enters into a government contract during the year to provide computer equipment for $4,400,000. The contract consists of a single performance obligation to provide specified equipment in three years. Total costs estimated by Supplier Corp. for the contract are $3,080,000 . The equipment is highly specialized and has no alternative uses. As negotiated in the contract, any costs incurred by Supplier Corp. plus a specified profit margin will be paid to Supplier Corp. in the event of a contract cancellation. Actual costs incurred during the year were $1,408,000 including unexpected cost overruns of $176,000 due to labor inefficiencies. a. Would revenue be recognized over time or at a point in time for this contract? Answer Recognize revenue over time b. Calculate (1) recognized revenue, (2) the gross profit, and (3) adjusted contract margin to be recorded during the year. 1. Recognized revenue Answer 2. Gross profit Answer 3. Adjusted contract margin Answer Note:- Do not…
- CN started a three-year contract to build a new university campus on 1 April 20X4. The contract had a fixed price of $90 million. CN will satisfy the performance obligation over time. CN incurred costs to 31 March 20X5 of $77 million and estimated that a further $33 million would need to be spent to complete the contract. CN measures the progress of contracts using work completed compared to contract price. At 31 March 20X5, a surveyor valued the work completed to date at $63 million. Select the correct amounts to be shown in revenue and cost of sales in the statement of profit or loss for the year ended 31 March 20X5? Revenue Cost of sales $63 million $77 million $57 million $83 millionSupplier Corp, enters into a government contract during the year to provide computer equipment for $2,000,000. The contract consists of a single performance obligation to provide specified equipment in three years. Total costs estimated by Supplier Corp. for the contract are $1,400,000. The equipment is highly specialized and has no alternative uses. As negotiated in the contract, any costs incurred by Supplier Corp. plus a specified profit margin will be paid to Supplier Corp. in the event of a contract cancellation. Actual costs incurred during the first year of the contract were $640,000 including unexpected cost overruns of $80,000 due to labor inefficiencies. Assume that at the end of the second year of the contract, the estimate of total costs has increased to $1,500,000 million due to an increase in cost of materials. Actual costs incurred to date are $1,125,000, excluding year one inefficiencies. a. Calculate (1) recognized revenue, (2) the gross profit, and (3) adjusted…A contractor enters into a contract for the expansion of an existing two-lane highway to a three-lane highway. The contract price is P65 million plus a P5 million award fee if the expansion is complete before the holiday travel season. The contract is expected to take one year to complete. The contractor has a long history of performing this type of highway work. The award fee is binary; that is, if the job is finished before the holiday travel season, the contractor receives the full award fee. The contractor does not receive any award fee if the highway is not finished before the holiday season. The contractor believes, based on its significant past experience, that it is 95 percent likely that the contract will be completed in advance of the holiday travel season. How much should the contractor account for the award fee? ______________
- Captain Construction Company is engaged in a road construction contract to build a highway over a three-year period. Captain will receive $22,000,000 for building five miles of highway Captain estimates that it will incur $20,000,000 of costs before the contract is completed. As of the end of the first year Captain incurred $5,000,000 of costs allocated to the contract Read the requirements. Requirement a. How much income from the contract must Captain report during the first year? (Do not round interim calculations. Only round the amount you input in the cell to the nearest dollar Enter a loss with a minus sign or parentheses.) Year 1 Revenue Costs Income (loss)Supplier Corp. enters into a government contract during the year to provide computer equipment for $3,200,000. The contract consists of a single performance obligation to provide specified equipment in three years. Total costs estimated by Supplier Corp. for the contract are $2,240,000. The equipment is highly specialized and has no alternative uses. As negotiated in the contract, any costs incurred by Supplier Corp. plus a specified profit margin will be paid to Supplier Corp. in the event of a contract cancellation. Actual costs incurred during the first year of the contract were $1,024,000 including unexpected cost overruns of $128,000 due to labor inefficiencies. Assume that at the end of the second year of the contract, the estimate of total costs has increased to $2,400,000 million due to an increase in cost of materials. Actual costs incurred to date are $1,800,000, excluding year one inefficiencies. a. Calculate (1) recognized revenue, (2) the gross profit, and (3) adjusted…JPIA Company began operations on January 2, 2021. During the year, the company entered into a contract with PUP Company to construct a manufacturing facility. At that time JPIA estimated that it would take five years to complete the facility at a cost of P4,812,500. The total contract price for the construction of the facility is P5,468,750. During the year, the company incurred P962,500 in construction costs related to the construction project. At year end, the total estimated cost to complete the contract is P4,375,000. PUP was billed and paid 30% of the contract price subject to a 10% retention. Using the percentage of completion method, how much is Contract Liability to be presented in the Statement of Financial Position for the year just ended?Required to answer. Single line text.