ation [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Balance Sheet (Partial) Current assets: Accounts receivable Construction in progress Less: Billings 2024 2025 2026 $ 2,100,000 $ 2,450,000 $ 2,695,000 2,450,000 2,350,000 2,300,000 Current liabilities: Billings in excess of CIP 3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract. Note: Do not round intermediate calculations. 2024 4,900,000 2,200,000 1,900,000 0 2025 0 0 5,450,000 5,800,000

CONCEPTS IN FED.TAX.,2020-W/ACCESS
20th Edition
ISBN:9780357110362
Author:Murphy
Publisher:Murphy
Chapter3: Income Sources
Section: Chapter Questions
Problem 88P
icon
Related questions
Question

Please help me 

Required information
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2026. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Balance Sheet (Partial)
Current assets:
Accounts receivable
Construction in progress
Less: Billings
2024
$ 2,100,000
4,900,000
2,200,000
1,900,000
Current liabilities:
Billings in excess of CIP
2024
2025
$ 2,450,000
2,450,000
2,350,000
2,300,000
3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the
contract.
Note: Do not round intermediate calculations.
0
2025
2026
$ 2,695,000
0
0
5,450,000
5,800,000
Transcribed Image Text:Required information [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Balance Sheet (Partial) Current assets: Accounts receivable Construction in progress Less: Billings 2024 $ 2,100,000 4,900,000 2,200,000 1,900,000 Current liabilities: Billings in excess of CIP 2024 2025 $ 2,450,000 2,450,000 2,350,000 2,300,000 3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract. Note: Do not round intermediate calculations. 0 2025 2026 $ 2,695,000 0 0 5,450,000 5,800,000
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
CONCEPTS IN FED.TAX., 2020-W/ACCESS
CONCEPTS IN FED.TAX., 2020-W/ACCESS
Accounting
ISBN:
9780357110362
Author:
Murphy
Publisher:
CENGAGE L