Ahead of schedule Behind schedule a. The status of the project in terms of schedule: Under budget Over budget b. The status of the project in terms of cost:
Q: Construct a project network for the following project. The project is completed when activities F…
A: A project network diagram can be stated as a visual indication of the workflow of any project. A…
Q: The following represents a project with known activity times. All times are in weeks. Activity…
A: Critical path, Total float, Free float, Independent float A - 4 B - 3 C A 2 D B 7 E C, D…
Q: The following table lists the activities for a small part of a project with various durations and…
A: PERT is the project management technique used to schedule the tasks flow and predict the completion…
Q: 1- Total project finishing time 2- Critical path, 3- Free float for each task. • 4- If Activity B is…
A: The critical path is the path with the longest duration.
Q: A project's activities must be completed in the sequence indicated below. Activity Duration…
A: A network diagram is a visual representation of a project which helps to identify the critical path…
Q: 1. How is the project performing from a schedule perspective? 2. How is the project performing…
A: For this IT project, we could see that total project duration =6 months, Project team would…
Q: The activity times are 3, 4, 2, 5, 7, 2, 2, and 3 days for activities A1 through A8,respectively.…
A:
Q: A new project is to be completed. The following activities need to be completed in the order shown,…
A: Find the estimated time calculation below:
Q: Three recent college graduates have formed a partnership and have opened an advertising firm. Their…
A: Precedence DiagramThe precedence diagram is as shown in the diagram below:
Q: Project is usually a special one-time operation that must be completed over a liraited time period?…
A: Completing a project on schedule benefits the firm in a variety of ways. It assists the organization…
Q: Q1- The schedule for one of the projects was as in Table No. (1), answer the following- 1- Draw the…
A: Below is the solution:-
Q: A project's activities must be completed in the sequence indicated below. Activity Immediately…
A: Here, It is CPM or critical path method problem, for this problem, I have following data like…
Q: A project schedule has the following characteristics as shown in table 2 Table 2 Activities 1-2 |…
A: AON diagram
Q: 11. Building a backyard swimming pool consists of nine major activities. The activities and their…
A: As you have posted multiple questions, we will provide the answers to the first question. Kindly…
Q: (c) Compute the earliest start, earliest finish, latest start and latest finish time and the slack…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: You are provided with the following information for a project, with activity durations given in…
A: Given that: Activity Immediate Predecessor Optimistic Time (a) Most Likely Time (m)…
Q: Consider the following activity information and the constraint that the project must be completed in…
A: The Network diagram is as shown-
Q: Solve the following project by hand and submit your notes: Activity Normal Time Crash Time Normal…
A: Please find the attached network diagram below-
Q: The following activities are part of a project to be scheduled using CPM: АсTIVITY IMMEDIATE…
A: This question is related to the topic - Project Management and this topic fall under the operations…
Q: The following represents a project that should be scheduled using CPM: TIMES (DAYS) IMMEDIATE…
A: Given Information:
Q: a) Draw an AON diagram of the project, including activity durations. b) Define the critical path,…
A: In project management, there are two types of networks. One is AON and the second is AOA. AON…
Q: Project ALPHA has 6 Acivities from A to F as follows: Activity Duration Preceded By A 3 A A F The…
A: The question is to find a number of the critical paths. In the project of the executives, the…
Q: Task Duration (Weeks) Follows A 3 B 7 A C 9 A D 3 C E 11 B, D F 3 E G 2 F H 3 C F I 5…
A: We use the forward and backward methods to calculate the critical path.
Q: Suppose you have a project with a Budget at Completion (BAC) of $250,000 and a projected length of…
A: Given, Budget at Completion (BAC) of $250,000 Time- 10 months
Q: A project has been defined to contain the following list of activities, along with their required…
A: The a, b and c part answers are shown in the diagram below-
Q: The aritical path for the network activities shown below is with completion time of weeks. Activity…
A: Answer: For determining the critical path, we have to draw the network diagram of the mentioned…
Q: I need assistance with the following questions in: Project Scheduling. This is a follow up to a…
A: Given the activity sequence and timings the following are the paths (in AOA notation):A-D (length…
Q: а. Draw a project network. What are the critical activities? c. What activity has the most slack…
A: The network diagram is as follows:
Q: Consider the following project network and activity times (in weeks): a. Identify the critical…
A: a) A-D-F-H b) Adding all the critical path A+D+F+H = 5+6+3+8 =22
Q: 2- A project to develop technology training seminars is 5 days behind schedule at day 65. It had a…
A: From the above given information, The number of planned scheduled days, S =65…
Q: Three recent college graduates have formed a partnership and have opened an advertising firm.Their…
A: Since we only answer up to 3 sub-parts, we'll answer the first 3. Please resubmit the question and…
Q: In reference to the attached image: Draw the project network, and determine the normal time to…
A: Network diagram is prepared using the forward and backward path analysis, This diagram is presented…
Q: I need a detailed explanation and assistance to solve this problem: A company decides to plan a…
A: Drawing the project network as shown in the diagram using AOA convention we represent the activities…
Q: If the first activity in a given project is D which precedes A, B. And activity A precedes H,G. And…
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts(1, 2,…
Q: (i) Construct a network diagram showing the various logical activity relationships from this…
A: For each activity, we have immediate predecessor data and Time in days, using the above table,…
Q: How can we determine the probability that a project will be completed by a certain date? What…
A: PERT: it stands for Project Evaluation and Review Technique. It shows the network of the project by…
Q: an the following table the activities with their precedence sequence and expected time (days) are…
A: Network Diagram :
Q: G This exercise contains only parts b, c, and d. b) The critical activities for the leadership…
A: The critical activities are the activities that lie on the critical path of a project. In a project,…
Q: If an activity has a zero slack, it: A. Is on the critical path. B. Must be a noncritical activity.…
A: Question: If an activity has a zero slack, it: A. Is on the critical path.B. Must be a noncritical…
Q: A project consists of five activities listed below. The project network is shown for the activities.…
A: Formulae used: Expected time of an activity= ( O + 4.M + P )6 Where, O=OptimisticM= Most…
Q: · Construct the project network comprised of activities A to P that satisfies the following…
A: Given data is
Q: Part 1: Building a backyard swimming pool consists of nine major activities. The activities and…
A: From the given data the network diagram is drawn below-
Q: A.Find the critical path and the entire project completion time. B.Which task has the most slack…
A: Below is the solution:-
Q: Use the Program Evaluation and Review Technique to represent the project in an activity network. In…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: Project ALPHA has 6 activities from A to Fas follows: Activity Duration Preceded By B A D Legend:…
A: Given data is
Q: Project ALPHA has 6 activities from A to F as follows: Activity Duration Preceded By A A A B E F E…
A: Answer: A as A is the merged activity of the correct network diagram.
Q: In the following table the activities with their precedence sequence and expected time (days) are…
A: Critical path investigation (CPA) can be defined as a venture the executive's method that requires…
Q: For each of the following network diagrams, determine both the critical path and the expected…
A: Since we only answer up to 3 sub-parts, we'll answer the first 3. Please resubmit the question and…
Q: The data below represent a project that can be completed at normal cost in 15 days. The project can…
A: Find the Given details below: Activity Predecessor Normal Time (NT) (Days) Crash Time (CT) (Days)…
Q: Which activities can be delayed?
A: Since you have asked multiple questions, we will answer the first question for you. If you want a…
Step by step
Solved in 2 steps with 2 images
- 1. The activities involved in the construction of a certain project are given in Table 1. One resource type will be used during the contract. Determine minimum level of the resource required to complete the project. a) Draw the precedence network and perform the CPM calculations. b) Prepare the Bar chart, Resource load table and and resource histogram (for both Early start time and Late start time) c) Allocate the required resources, then level them so that the contractor does not use more than six laborers at any time. Preceded Duration by Activity Laborers (Days) A 5 7 4 А D A,B 5 C,D 2 2. m3 3. 2. B.Teloxy Engineering (A) Teloxy Engineering has received a onetime contract to design and build 10 000 units of a new product. During the proposal process, management felt that the new product could be designed and manufactured at a low cost. Some members felt that it would be more economical to purchase the product for R200 each in the marketplace, with an extra R20 per unit handling of the 10 000 units. The Management team set up a meeting with the manufacturing team to see if they can manufacture the component at a cheaper price than buying it from the outside. The manufacturing team informs them that it can produce a maximum of 10,000 units, just enough to fulfil the contract. The setup cost will be R100 000 and the raw material cost is R120 per component. Since Teloxy has never manufactured this product before, manufacturing expects the following defects: % defective 10 20 30 40 Probability of occurrence (%) 10 20 30 25 15 All defective units must be removed and repaired at a cost…What role does a business analyst play in the requirement analysis phase of a project?
- Hoosier Burger Juan Rodriquez has assigned you the task of requirements determination for the Hoosier Burger project. You are looking forward to this opportunity because it will allow you to meet and interact with Hoosier Burger employees. Besides interviewing Bob and Thelma Mellankamp, you decide to collect information from Hoosier Burger’s waiters, cooks, and customers. Mr. Rodriquez suggests that you formally interview Bob and Thelma Mellankamp and perhaps observe them performing their daily management tasks. You decide that the best way to collect requirements from the waiters and cooks is to interview and observe them. You realize that discussing the order-taking process with Hoosier Burger employees and then observing them in action will provide you with a better idea of where potential system improvements can be made. You also decide to prepare a questionnaire to distribute to Hoosier Burger customers. Because Hoosier Burger has a large customer base, it would be impossible to…Create an AOA diagram based on the information Task A, duration 6, dependent on noneTask B, duration 5, dependent on noneTask C, duration 3, dependent on noneTask D, duration 12, dependent on Task B and Task C Task E, duration 2, dependent on Task ATask F, duration 5, dependent on Task BTask G, duration 1, dependent on Task BTask H, duration 9, dependent on Task E and Task FTask I, duration 7, dependent on Task GTask J, duration 7, dependent on Task HTask K, duration 3, dependent on Task ITask L, duration 5, dependent on Task DRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) B A, D C E, F This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B - D - E - G. c) The project length for the leadership training program development project = 28 days. d) Slack time for each of the activities is: ABCDEFG Activity A Slack Time ∞ or w w w 10
- Make a sources of funding Project Needs and Costs Tools and Equipment Item Quantity Price / unit Total Amount Doughnut Machines 3 P 1,829.00 5,487.00 Dough Mixer 3 2,749.00 8,247.00 Doughnut Pan 5 226.00 1,130.00 Deep Fry-Thermometer 5 177.00 885.00 Doughnut Cutter 5 262.00 1,310.00 Kitchen Scale 3 99.00 297.00 Oven Proofer Combos 1 2,699.00 2,699.00 Doughnut Pastry Bag 2 88.00 176.00 Donut Baskets and Screen Racks 2 3,000.00 6,000.00 Measuring cups & spoons 3 sets 150.00 450.00 Funnels 4 545.00 2,180.00 Mixing Bowls 5 100.00 500.00 Trash Bins 2 190.00 380.00 TOTAL P 12,114.00 P 29,741.00 Ingredients Item Quantity Price / unit Total Amount Flour 2 sacks P 1,250 P 2,500.00 Egg 10 trays 212.00 2,120.00 Honey 5 bottles 150.00 750.00 Butter 20 bars…3- For the following test marketing project at week 6:a. Ignore the far right “% Complete” column and using the 50–50 percent completion rule for PV and EV, calculate the cost, schedule, and time variances. Also calculate the CPI, SPI, CSI, and the ETC and EAC. b. Repeat the calculations in a, but now using the “% Complete” column. Assume that the PV values are based on time proportionality but the “% Complete” values for EV are from the workers actually doing the tasks.Prepare a WBS for a spaghetti with meatballs dinner thatincludes a Caesar salad, a loaf of Italian bread, and wine.(Include the different components of the dinner at theupper level and the various detailed work activitiesrequired by each component at the lower level.)
- At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing to host its first rock concert of the school year. To successfully produce this rock concert, SCOPE has listed the requisite activities and related information in the following table (duration estimates measured in days). Already found the times, expected times, variances, and slacks. Need help with the rest. Thanks. ^.^Heather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 "Ultima Steppers," to be shipped in week 8. The subscripts indicate the quantity needed for each parent. Information on the "steppers" is shown below: Develop a product structure (BOM) (product structural tree). Develop a time phase structure (Gantt chart).Develop a net material requirements plan (MRP) for E.A competitor of Kozar International Inc. has begun marketing a new, instant-developing film project. Kozar has had a similar product under study in its research and development (R&D) department but has not yet been able to begin production. Because of the competitor’s action, top managers have asked for a speedup of R&D activities so that Kozar can produce and market instant film at the earliest possible date. The predecessor information and activity time estimates in months are as follows: A: Draw the Project Network B: Develop an activity schedule for this project using early and late start and finish times, compute activity slack time, and define the critical activities.