A production process at South Plains Manufacturing is shown below. The drilling operation occurs separately from, and simultaneously with, sawing and sanding, which are independent and sequential operations. A product needs to go through only one of three assembly operations (the operations are in parallel). If the firm operates 8 hours per day, 20 days per month, what is the monthly capacity of the manufacturing process? IMPORTANT NOTE: given below is the Capacity per Operation. You need to convert each one of them to Process Times (min/unit)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question
A production process at South Plains Manufacturing is shown below. The drilling operation occurs separately from, and
simultaneously with, sawing and sanding, which are independent and sequential operations. A product needs to go through only
one of three assembly operations (the operations are in parallel).
If the firm operates 8 hours per day, 20 days per month, what is the monthly capacity of the manufacturing process?
IMPORTANT NOTE: given below is the Capacity per Operation. You need to convert each one of them to Process Times (min/unit)
Sawing
6 units/hr
a
b
Select an answer and submit. For keyboard navigation, use the up/down arrow keys to select an answer.
C
d
e
320 units per month
370 units per month
430 units
per month
460 units per month
Sanding
6 units/hr
490 units per month
Drilling
2.4 units/hr
Welding
2 units/hr
Assembly
Assembly
Assembly
0.7 units/hr
0.7 units/hr
0.7 units/hr
Transcribed Image Text:A production process at South Plains Manufacturing is shown below. The drilling operation occurs separately from, and simultaneously with, sawing and sanding, which are independent and sequential operations. A product needs to go through only one of three assembly operations (the operations are in parallel). If the firm operates 8 hours per day, 20 days per month, what is the monthly capacity of the manufacturing process? IMPORTANT NOTE: given below is the Capacity per Operation. You need to convert each one of them to Process Times (min/unit) Sawing 6 units/hr a b Select an answer and submit. For keyboard navigation, use the up/down arrow keys to select an answer. C d e 320 units per month 370 units per month 430 units per month 460 units per month Sanding 6 units/hr 490 units per month Drilling 2.4 units/hr Welding 2 units/hr Assembly Assembly Assembly 0.7 units/hr 0.7 units/hr 0.7 units/hr
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 6 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,