A maintenance building construction project also includes an external electrical generator and water tank. The first activity is to excavate which requires two weeks. Following excavation, the maintenance building will be built, and then both the generator and the water tank can be installed. These three activities, building, generator, and tank, require six, four, and two weeks, respectively. Once this set of three activities is completed, the tank and generator can be connected to the building, an activity that requires five weeks. After the maintenance building is built, maintenance equipment can also be installed inside the building and this activity takes four weeks. Painting the maintenance building is also required, following its construction, and this takes three weeks. Finally, after the maintenance equipment is installed and the connection is completed, it will take two weeks to inspect the new maintenance facility.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question

A. $25,000

B. $450,000  

C. $500,000 
 
D. $550,000
 
E. None of the answers are correct
A Construction Project
A maintenance building construction project also includes an external electrical
generator and water tank. The first activity is to excavate which requires two weeks.
Following excavation, the maintenance building will be built, and then both the
generator and the water tank can be installed. These three activities, building,
generator, and tank, require six, four, and two weeks, respectively.
Once this set of three activities is completed, the tank and generator can be
connected to the building, an activity that requires five weeks. After the maintenance
building is built, maintenance equipment can also be installed inside the building and
this activity takes four weeks. Painting the maintenance building is also required,
following its construction, and this takes three weeks. Finally, after the maintenance
equipment is installed and the connection is completed, it will take two weeks to
inspect the new maintenance facility.
Suppose the costs of the activities are:
Activity
Excavate
Construct Building
Install Generator
Install Tank
Connect
Install Maintenance
Paint
Inspect
Cost ($1000s)
$50
$150
$120
$50
$40
$30
$30
$10
What is the total project cost given this cost information?
Transcribed Image Text:A Construction Project A maintenance building construction project also includes an external electrical generator and water tank. The first activity is to excavate which requires two weeks. Following excavation, the maintenance building will be built, and then both the generator and the water tank can be installed. These three activities, building, generator, and tank, require six, four, and two weeks, respectively. Once this set of three activities is completed, the tank and generator can be connected to the building, an activity that requires five weeks. After the maintenance building is built, maintenance equipment can also be installed inside the building and this activity takes four weeks. Painting the maintenance building is also required, following its construction, and this takes three weeks. Finally, after the maintenance equipment is installed and the connection is completed, it will take two weeks to inspect the new maintenance facility. Suppose the costs of the activities are: Activity Excavate Construct Building Install Generator Install Tank Connect Install Maintenance Paint Inspect Cost ($1000s) $50 $150 $120 $50 $40 $30 $30 $10 What is the total project cost given this cost information?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,