A bank receives loan applications from 6 customers a day. The bank has promised customers that applications will be processed in the order they are received. The table below shows the applications in the order they were received, the processing time for each loan application, and the due date that customers need to hear about their application status: Customer Processing time (days) Due date (days) A 9 13 B 11 18 C 8 11 D 7 13 E 10 22 F 12 28 Average flow time   days Average tardiness   days Average number of jobs   applications

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question
100%

A bank receives loan applications from 6 customers a day. The bank has promised customers that applications will be processed in the order they are received. The table below shows the applications in the order they were received, the processing time for each loan application, and the due date that customers need to hear about their application status:

Customer Processing time (days) Due date (days)
A 9 13
B 11 18
C 8 11
D 7 13
E 10 22
F 12 28
Average flow time   days
Average tardiness   days
Average number of jobs   applications
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Knowledge Booster
Optimization models
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,