- The approved critical path passes through the following critical activities *
Q: 3. Review the PERT diagram below, and discuss how you would find the critical path.
A: PERT diagram is the diagram used for scheduling and organising the project activities of the…
Q: 1. Prepare the Activity Node Diagram and identify the Critical Path 2. Prepare Gantt Chart Thankss
A: Given data is
Q: The VOX Cinema is installing a new system to enhance the quality of movies shown. Several things…
A: First I have formulated the table, this table is presented below: Formula:
Q: Explain the latest start time in critical path method
A: The concept "late start" depends on the final point in time when the plan's action will begin in…
Q: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has…
A: A resource-utilization approach called the Critical path method (CPM) is used to schedule a group of…
Q: i) ii) Draw the Network Diagram and find the Critical Path. If Dummy Activity occurs then find the…
A: As per Bartleby guidelines, we can only solve one question at a time...Kindly upload the other…
Q: Define Critical Path?
A: Critical path method is an algorithmic method used to schedule project activities in a manner so…
Q: What is the critical path
A: A critical path is a path which indicating the highest duration from all available paths. A critical…
Q: How do PERT and CPM differ?
A: Project management includes planning and coordinating a company's resources to move toward the…
Q: What activities are on the critical path that must be crashed?
A: Project crashing is a practice in project management to rush up the project time by reducing the…
Q: I need a project scope management plan and not a list of what should be included in the plan
A: A Project Scope Management Plan outlines the processes involved in executing your project and serve…
Q: How do PERT and CPM differ from each other?
A: Project management requires the preparation and organization of the resources of a business to move…
Q: AN INNOVATIVE BUSINESS IDEA – STORY FROM OMANI YOUNG ENTREPRENEUR Khalid Al Suwaid is a 22 years old…
A: The growth and productivity of a newly established business largely depend on its ability to remain…
Q: Given the tabulated data shown, prepare the PERT / CPM or arrow diagram and identify the critical…
A: THE ANSWER IS AS BELOW:
Q: What is the theory of limitations, in a nutshell?
A: Its Theory of Constraints provides a logical foundation for process optimization. Each dynamic…
Q: What is the significance of identifying the critical activities?
A: Project management is the management in which different types of knowledge and skills are needed to…
Q: a) What are the critical activities?
A: The expected activity time is the time taken by the particular activity to complete the project…
Q: Describe how operations managers use the critical path method to manage projects. What is the…
A: Critical paths:Critical paths are the path or sequence of activities that form the longest chain in…
Q: Q3.When we start a project how we know this project or program is feasible for our future? Explain…
A: Project selection is a critical task and therefore generally leaders or people without past…
Q: How may the project team that recommends an ERP design strategy defend its selection in comparison…
A: ERP stands for Enterprise resource planning that is used for the integration and management of…
Q: Given the tabulated data shown, prepare the PERT / CPM or arrow diagram and identify the critical…
A: PERT/CPM diagram will helps to identify the critical path using forward and backward passing…
Q: Determine the manufacturing cycle efficiency (MCE) for the recent month. (Round your answer to 1…
A: Processing time is the time incurred to process the product item manufactured in an organization.
Q: A professional organization for project management specialists
A: The Project Management Institute is a professional organization for project management specialists.…
Q: Q.No.3. When we start a project how we know this project or program is feasible for our future?…
A: Before starting a project, its feasibility for the future is understood by the feasibility study.…
Q: Differentiate between Service Projects and Revenue Projects?
A: One of the main differences between revenue projects and service projects is that, in the case of…
Q: The VOX Cinema is installing a new system to enhance the quality of movies shown. Several things…
A: Formula:
Q: a. Find the critical path.
A: A network diagram is a visual representation of a project which identifying the activity…
Q: Q1:Find the critical path, total permittivity, and time period required to complete the construction…
A: Answer is as below:
Q: Schedule the following activities using CPM: АСTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 2 B A 3 A…
A: ES = maximum (EF of all immediate predecessor) EF = ES + duration Minimum project duration = largest…
Q: Hershey Chocolate Corporation was the first company that produced milk chocolate in America. With…
A: Hershey Chocolate Corporation was the primary company that produced chocolate in America. With the…
Q: Hiw Y Design the network represents the following activities and then finds the critical Path?…
A: Given data is
Q: DEFINE Critical path analysis
A: Critical path analysis is the project management tool used for scheduling, organizing, planning and…
Q: What are some tactical projects that can be initiated because of complaints that arise from…
A: A facility manager's responsibility is to maximize building performance and guarantee efficient…
Q: Q.1. Draw AOA diagram and find the critical path. Q.2. What will be the project duration?
A: AOA diagram
Q: Qno 6. Write a note explaining your project and include all the functions used in your project?
A: Introduction: The term Business refers to an exchange of goods and services between the buyer and…
Q: In order to improve the efficiency of the Ghana Association of Susu Collectors (GASCoperations, )'s…
A: Enterprise resource planning helps the GASC to increase efficiency and productivity of work by…
Q: Make an analysis of Critical Path Method (CPM) in four steps?
A: The critical path methods (CPM) refers to the step-by-step process of the project management to…
Q: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has…
A: In assembly line balancing, each task is assigned to a workstation in order to meet the specified…
Q: find the Critical path, using the available paths technique:
A: The critical path depicts the path with the total duration to complete all the activities in the…
Q: Explain how to deal effectively with problems that could arise with areas such as quality, safety,…
A: A well-documented system is the foundation of any formal agreement or process.
Q: Based on the Project Oxygen at Google: What are limits/ dangers of implementing project oxygen…
A: Project oxygen of Google: Project oxygen was launched as a multiyear research initiative. It is an…
Q: DEFINE Critical path method (CPM)
A: Critical path method is a project modeling technique which is used to determine the deadlines and…
Q: As the project manager, discuss the risk management process you think might have identified the…
A: Introduction to risk analysis: It is the process which help to access the potential risk which could…
Q: Refer to the table given to answer the following question: 1. Which PERT diagram best represents the…
A: Given data is
Q: Describe what is meant by the forward pass in critical path method ?
A: The critical path method's both forward-backward passage steps have been used to determine the…
Q: Create a PERT diagram and find the critical path for the same
A: A PERT chart, now and then called a PERT graph, is a project the board instrument used to plan,…
Step by step
Solved in 3 steps with 3 images
- Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Immediate Predecessor(s) Activity A B C D E F G This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are A-E-G c) The project length for the leadership training program development project = 22 days. d) Slack time for each of the activities is: B A, D C E, F Activity A B Slack Time 0 Time (days) 10 6 3 2 4 8Preceding Activity Crashed Cost per week $600 $700 $400 Activity Normal Completion Time (week) Crashed Completion time (week) A 7 5 B 12 10 A 8 2 $800 $300 $500 E C, D 5 4 F E 9 8 D. F 10 10 i. Draw the network diagram linking all the activities in a way that it shows if there exist any preceding activity/activities before starting each of the mentioned activities in the above table, ii. Showing the earliest start time, the earliest finish time, the latest start time and the latest finish time of each of the activities in the project determine the completion time of the project and the critical path. ii. Find the slack time (delay time) of each of the activities, the critical and the non-critical activities. Find the minimum possible completion time of the project by considering the crashed completion times and the minimal total cost of that crashing the project. iv. Need proper handwritten answers. Thank you!Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre-decessors, and times appear in the accompanying table: A—2 B—5 C—1 D B 10 E A, D 3 FC6 G E, F 8 A) Develop an AON network for this problem.b) What is the critical path?c) What is the total project completion time? Please answer A B C and show work
- Chuck’s Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a wealthy customer. Relevant data are shown in the table below. The complication is that the customer wants delivery in 32 weeks or he will impose a penalty of $375 for each week his yacht is late. Activity Immediate Predecessor Normal Time (NT) Weeks Crashing Cost 1st Week 2nd Week A ― 9 $410 $415 B A 7 125 -- C A 5 45 45 D B 4 300 350 E C 6 50 -- F D, E 5 200 225 G F 8 -- -- H F 7 85 90 I G 6 90 -- Construct a network diagram for the project Indicate the critical path when normal activity times are used. Develop a crashing schedule. Note: No activity can be crashed more than two weeks. Show breakdown of workRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) A BCDEFG с This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are c) The project length for the leadership training program development project = d) Slack time for each of the activities is: days. Activity A B C ס ח ד 0 F B A, D C E, F G Slack Time Time (days) 4 6 1 103510Draw a network diagram showing the linkage between these activities from start to finish. For the diagram, each activity should be labelled alphabetically ie. A, B, C… etc. PERT Formula: TE = (O + 4T + P) / 6 TE = Pert Expected Time Duration, O = Optimistic estimate, P = Pessimistic estimate, T = Most Likely (Typical) estimate Activity Predecessor Optimistic Most Likely Pessimistic Duration Duration in Weeks A — 2 3 4 B — 4 5 7 C B 1 2 3 D C & E 0.5 1 1.5 E B 0.5 1 1.5 F C 2 3 4 G F 2 3 4
- The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS ACTIVITY A ABCDEFGH B-E-G-H b. What is the critical path? A-C-F-H OA-D-F-H A-D-G-H A A B C,D D, E F,G Project completion time a LLL23312 TIMES (DAYS) m •WNNW: 3 2 2 3 4 4 4 4 b 5 3 3 4 11 c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 2 decimal places. days 565Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) B A, D C E, F This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B - D - E - G. c) The project length for the leadership training program development project = 28 days. d) Slack time for each of the activities is: ABCDEFG Activity A Slack Time ∞ or w w w 10Image of Diagram included Using the diagram, find: The critical path. How long it will take to complete the project? How does simulation determine the probabilities of various project completion times? What is "slack" and why is it important? Why is activity-on-arrow (AOA) or activity-on-node (AON) of significant value to the project manager? How is the uncertainty in project scheduling dealt with? Should the critical path activities be managed differently from noncritical path activities? Explain.
- Example: Undertaking by a contractor to implement a contracting for excavation works according to the scheme below, undertaking to complete the work within a period of 36 weeks with a probability of 99% between in light of the contractor's probability. The actual time period for the completion of the project within the PERT technology? Act. a b te u C.P 1-2 7 8. 6.33 1 1 *1,2 2-3 6. 9 6.33 0.66 0.443 *2 2-4 3 7 8. 6.5 0.83 .693 *1 2-5 4 6. 0.33 3-6 9. 10 8.66 0.66 0.443 *2 4-7 6. 8 11 8.166 0.83 .693 *1 5-7 4 7 5.83 0.5 6-8 7 10 7.16 0.83 .693 *2 7-8 4 8 7.5 0.83 .693 *1 8-9 4 7 9 6.83 0.83 .693 *1,2for the following project, assume the quantity for the project Equal 37, use LSM to determine the finish date for the project. Productio Activity IPA n Rate Relation [Day/m] A 1 В A 3 FF 2 SS Answer:The table below contains data for the installation of new equipment in a manufacturing process for a steel corporation. Your company is responsible for the installation project. Indirect costs are $6,000 per week, and a penalty cost of $10,000 per week will be incurred by your company for every week the project is delayed beyond week 15. Activity Immediate Predecessor(s) Normal Time (weeks) Crash Time (weeks) Normal Cost ($) Crash Cost ($) A None 2 1 7,000 10,000 B None 2 2 3,000 3,000 C A 3 1 12,000 40,000 D B 3 2 12,000 28,000 E C 1 1 8,000 8,000 F D, E 5 3 5,000 15,000 G E 3 2 9,000 18,000 H F, G 8 6 14,000 32,000 Construct a network diagram for the project. What are the project completion time and the total cost under normal conditions? What is the shortest time duration for this project regardless of cost? What is the resulting total cost? What is the…