The minimum time (in days) for completion of the project
Q: 2. (a) Define the physical processes which comprise the four stroke cycle AND Define the…
A:
Q: Define the friction losses in pipes, what are the parameters that effect on friction in the pipe?…
A: Friction losses in pipe: It is defined as the head loss in the fluid flow due to effect of fluid…
Q: j) k) Solve for x (x-coordinate of the composite area's Centroid) Solve for y(y-coordinate of the…
A: (j) Write the x-coordinate of centroid for each shape. x1=200-4r3π=200-42003π=115.12…
Q: 4. A pair of gears with a reduction ratio of 2.32 operating on 83mm cen- tres is required. The…
A:
Q: Determine the mass flow rate on an ideal Brayton cycle whose heat addition is 500 kW and 300 kW on…
A:
Q: For the state of plane stress as shown in the Figure: Construct the Mohr's circle. Determine the…
A:
Q: Oil is being pumped from an Open Tank A (elev = 110m) to another Open Tank B (elev = 220m) with a…
A:
Q: What are the types of thermodynamic cycle as to the type of output? Define each
A: Any closed system that experiences numerous changes owing to temperature, pressure, and volume,…
Q: Replace the distributed loading with an equivalent resultant force, and specify its location on the…
A: Equivalent resultant force, FR= ∫0Lf(x)dx. It's location, x¯= ∫0Lxf(x) dx∫0Lf(x) dx Given: f(x)=…
Q: Each of three identical bodies satisfies the equation U = CT, where C is the heat capacity of each…
A:
Q: 2. Write in detail the process plan of the following turning part in Fig. 2. Design the toolpath and…
A:
Q: Find the loss of head when pipe of diameter 30 cm is suddenly enlarged to a diameter of 40 cm. The…
A: Given:d1=30 cmd2=40 cmQ=300 L/sec
Q: H.W3 Determine the slope and deflection of end A of the cantilevered beam. E = 200 GPa and I =…
A:
Q: Figure -2 ft 2 ft 2 in. 2P 2 ft 1 of 1 > B Part A If the beam is made from wood having an allowable…
A:
Q: Q4 - Determine the reactions at the supports. 500 N/m 4 m
A:
Q: the correct order of
A: Given; Correct order of efficiencies for otto, dual and diesel cycle is ? where, For the same…
Q: A 6-in-wide and 8-in-high vertical hot surface in 78°F air is to be cooled by a heat sink with…
A: In thermodynamics when the energy from the high temperature medium to the low temperature medium…
Q: At a temperature of 15˚C, a steel bar just fits between two rigid supports. Its length is L = 5 m,…
A:
Q: An unknown mass m is attached to two identical springs. Each spring has a stiffness k = 10 N/m and…
A: Given Stiffness, k = 10 N/m Amplitude, A = 3 m Length, L = 4 m Find Acceleration, a Mass, m…
Q: 27. 1.8 kg of steam at 1.65 MPa, 300 deg C is compressed isothermically until it becomes ssaturated.…
A:
Q: A horse is used to help stack hay in a barn. At the instant shown, the length of rope, r, is 7 m,…
A: Given data as per the question Length of rope =7 m Mass of horse =750 kg velocity =1.5 m/s Mass of…
Q: Sketch diagrams (including a coordinate system) showing the planes represented by the following…
A:
Q: In a fixed-geometry wind tunnel, air is drawn in by means of a fan. In the supply reservoir, the…
A:
Q: 1. What are the problems with Offshore Power Plant, explain each.
A: Problems with offshore Power turbine ****AS per company policy we are supposed to do only 1…
Q: amplitude of vibration (in m) is approximately
A: Given; Sinusoidal force=10 N amplitude Frequency w along the axis of the spring. Stiffness of…
Q: The overhanging beam ABC in Figure supports a concentrated load and a uniformly distributed load.…
A:
Q: 4. A pair of gears with a reduction ratio of 2.32 operating on 83mm cen- tres is required. The…
A: Given data Reduction ratio= 2.32 Centre distance = 83mm Module = 2mm Find (f) the forces on the…
Q: 2. (a) Define the physical processes which comprise the four stroke cycle AND Define the…
A: Delay period is also called as ignition delay in diesel engine combusion. It is defined as the time…
Q: 4. A pair of gears with a reduction ratio of 2.32 operating on 83mm cen- tres is required. The…
A: given; gear reduction ratio(G)=2.32center distance(d)=83mmmodule(m)=2mm
Q: 4-A round-nosed projectile travels through air at a temperature of a pressure of 1.8 ×104 pa . The…
A:
Q: Draw the shear and moment diagrams of the beam given in Figure 4. 10 kN 2 kN/m B -5 m Figure 4 3 m…
A:
Q: The maximum principle stress for the stress state shown in the figure is (b) 20 (a) o (c) 30 (d) 1.5…
A: From the data given in question, Normal stress along x direction = σx = σ Normal stress along y…
Q: ASAP
A: Isolate the cylinder with its weight acting at the middle of G, tensions from cables AB and CD, and…
Q: An S-N plot from fatigue testing of a steel is provided below. Use the plot to determine the…
A: INTRODUCTION: S–N curves can be measured by applying a constant amplitude and mean, harmonic load on…
Q: 4. A pair of gears with a reduction ratio of 2.32 operating on 83mm cen- tres is required. The…
A: Given data Reduction ratio = 2.32 Center distance = 83mm Module = 2mm Find the total no of teeth…
Q: nd support a load of 3925N when running at the design The radial clearance has been specified as…
A: d=80mm , r=40mml=40mmP=3925NW=1197rpmCr=0.0565mmT=55C To-Find:- 1) Temperature-Raise 2) Minimum film…
Q: Q¹/ If the fitting symbol between the shaft and hole is (8G7/h6), find? 1-The upper and lower…
A: 18 G7/h6 Basic size of shaft, D = 18 mm, Fundamental deviation of hole = 0, Tolerance,…
Q: If the maximum resisting moment at point A is 150 N.m about the x-axis. Determine the largest…
A:
Q: Tank A which is completely insulated contains 1 kg of oxygen at 15°C and 300 kPa. It is connected…
A:
Q: s) What is the distance, d3x, of shape 3’s centroid from axis Xo? t) What is the distance, d6x, of…
A: The following table shows the centroid values of the various shapes presented in the given problem.…
Q: 2. When s = 0.6 m, the spring is unstretched and the 10-kg block has a speed of 5 m/s down the…
A:
Q: Where did the 107.11 came from
A: Given Weight, W1 = 500 N W2 = 1000 N Find The angle 107.11o
Q: 3. (a) A 3200c.c. Spark Ignition (SI) V6 engine operates on a four stroke cycle at 7800RPM. The…
A:
Q: Q2) A piston/cylinder has ammonia at 1600 kPa, 100°C with a volume of 0.1 m3. The piston is loaded…
A:
Q: 32. Saturated steam at 4.6 MPa undergoes a polytropic compression process where n= 1.2 to saturated…
A:
Q: 3=DF=20-032 N d=12m Find work done.
A:
Q: operating mm cen- tres is required. The module is 2.0mm of PCD per tooth, the pres- sure angle is…
A:
Q: The outside diameter (in mm) of the 10/14
A: Given; A hollow shaft; length,l=1m Max permissible twist in the shaft is=10 Inner dia of the…
Q: Determine the quality (if saturated) or temperature (if superheated) of the following substances at…
A: Water: 1 Given that, T= 120∘C and v= 1 m3/kg. Find vg at T= 120∘C from steam tables. ⇒vg= 0.89133…
Q: what is 6 to 10 po?
A:
Step by step
Solved in 2 steps
- 9.5.29 Question He Find the work W done by a force of 3 pounds acting in the direction 45 to the horizontal in moving an object 7 feet from (0 0) to (7,0) . foot-pounds Round to the nearest whole number as needed) %3D 用 Enter your answer in the answer box and then click Check Answer All parts showing School a for nk6xemh85d.execute-api.us-east-1.amazonaws.com... EXUsing the information in Table 1, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible: Activity Duration (Days) Predecessor A 1 B 3 A 2 A 5 4 D 2 B 5 D H 4 2 H J 3 J а. Cakulate the ES, EF, LS, LF. Determine the critical path of the project.t с. Calculate the planned duration of the project in weeksConsider the following two mutually exclusive projects being considered by an agency. The agency's MARR is 4% per year and the projects have a service life of 5 years. Answer the following questions. Initial cost Annual revenues Present Worth (PW) Project 1 $14,600 $3,901 $2,767 Project 2 $22,100 $5,638 a. Based on the PW, the project that is more economical is Project b. Calculate the IRR of each alternative (use the trial-and-error method) % (Round to the nearest one decimal place) The IRR of Project 1 is The IRR of Project 2 is % (Round to the nearest one decimal place) $2,999 (Enter the project number). c. Perform the incremental IRR analysis to determine the project that is more economical: Incremental IRR =% (Round to the nearest one decimal place); Therefore, based on the incremental IRR, Project is more economical. d. Do the two methods produce the same recomendation for the most economical project?
- A man pays P 114,100 every end of the quarter for a car bought on installment terms. If the man wishes to pay every end of the month instead of every end of the quarter, how much should he pay if the interest is 12% compounded monthly? pls answer 10 mins deadlineSave The planning department of Abstract Office Supplies has been asked to determine whether the company should introduce a new computer desk next year. The department estimates that $7.00o of new manufacturing equipment will need to be purchased and that the cost of constructing each desk will be $200. The department also estimates that the revenue from each desk will be $550 a. Determine the revenue function R(x) from the sale of x desks. R(x) = 550x b. Determine the cost function C(x) for manufacturing x desks. C(x) =| Help me solve this View an example Get more help - Clear all Check answer 9:47 PM 1/24/2022 De Home End Insert Esc F7 FB F9 F10 @ %23 24 & 2 3 6 E T QA project has the following activities; the activities and precedence relationships are given in below network diagram. Consider the Duration of activities in Days. 1) Find critical path 2) Find the expected project completion time B C (9) (10) G (9) H(6) A (3) D (8) F (9) E (6) hp
- Specific fuel consumption of a four-stroke internal combustion engine at a given rotational speed is 0.322 kg/kW-h value is minimum. Spindle power at this rotation rate is 123 kW, volumetric efficiency is 95% and air-fuel rate is 15. The number of rotations of this engine is calculated by subtracting 1.5 from the number of rotations giving the minimum specific fuel consumption. time, spindle power 162 kW, specific fuel consumption 0.394 kg/kW-h and volumetric efficiency 85%. a) Calculate the air-fuel ratio in this case. and By what percent has the efficiency of the engine changed?RRIVING TIME You need to buy groceries at the supermarket, deposit a check at the credit union, and purchase a book at the bookstore. You can complete the errands in any order; however, you must start and end at your home. The driving time in minutes between each of these locations is given in the following figure. Credit union 8.5 Bookstore 4.5 11 Supermarket Home lQuestion: Find the least possible time to complete the TASK?Q1. The data shown in the table below is given for a small project: 1. Draw the network diagram (Pert Chart) for this project. 2. Identify all paths in the network. 3. Find the duration of each path. 4. Find the earliest and latest time for activities using forward and backward pass. 5. Determine the critical path. Activity Preceded by Duration (Week) 5 487 218 5 13 14 36 4 ABCDEFGHIJKLM N 0 AAAAB BC BC D,EEF HIG,K KG,L J.N.M 2
- The annual demand for an item is 10,000 units. The unit cost is Rs. 100 and inventory carrying charges are 14.4% of the unit cost per annum. The cost of one procurement is Rs. 2000. the time between two consecutive orders to meet the above demand is _month(s).11.161 Robots with telescoping arms are sometimes used to perform tasks (e.g., welding or placing screws) where access may be difficult for other robotic types. During a test run, a robot arm is programmed to extend according to the relationship r = 3 + 0.5 cos(40) and the arm rotates according to the relationship + лt, where r is in feet, is in radians, and t is in seconds. Determine (a) the velocity and acceleration of the robot tip A at t = 3 s and (b) use a computer program to plot the path of tip A in x and y coordinates for 0 ≤ t ≤ 4s. = π 2 4Lemar Supermarket sells about 200 000 kilos of milk annually. The milk ispurchased for 4 MU/kg. Holding costs are 1.40 MU/kg/yr. Each order costs 35 MU. If theshelf life of the milk is only 5 days, how many kilos should be ordered at a time. Please mention formulas and do it in detail so I can understand.