Operations - Lesson 2 Problem Set: Solution
Part 1
A small four-step process runs with four employees, each one operating one step of the process. The cycle times are shown in the following table:
Steps
Employee
Cycle Time (Seconds/Customer)
1
Bob
10
2
Jim
15
3
Mary
8
4
Liz
12
1.
Draw the process flow diagram. (2 points)
2.
Calculate the capacity of each step in customers per minute. (5 points)
Steps
Employee
Customers per Minute
1
Bob
___6____
2
Jim
___4____
3
Mary ___7.5____
4
Liz
___5____
3.
Step __2_ is the bottleneck. (3 points)
Step 1
Bob
10 sec.
Step 2
Jim
15 sec.
Step 3
Mary
8 sec.
Step 4
Liz
12 sec.
4.
The capacity of the entire process is: _4___ customers per minute. (3 points)
5.
One day Jim called in sick. Mary agreed to do both his step and hers, but she can only do one step at a time. She is just as fast as Jim, and can also do Step 2 in 15 seconds per customer. Does the capacity of the whole process change on this day? If yes, calculate the new capacity. If no, briefly explain why not. (Must decide on yes or no, not an argument for both.) (4 points)
a.
Yes, it changes. Mary’s new capacity is 60/(15+8) = 2.6 customers/min. This is also the capacity of the entire process in Jim’s absence. b.
No, it does not change.
Part 2
A small Starbucks in middle America serves, on average, 60 customers a night. A typical night in this town is long, about 10 hours. There’s not much else to do. The manager observed customers in the store all night and she is wondering if she is allowing them to stay too long, just
using the free internet. She has gathered data on how many customers are in the store at any one time, and believes this average to be 18 customers. These customers are eating food they purchased and drinking coffee, but she has calculated that each customer could finish eating and drinking in 30 minutes.
1.
Calculate IN. There is an average of _18___ customers in the store at any point in time. (4 points)
2.
Calculate TH. Arrivals are _60/10 = 6___ customers per hour on average. (6 points)
3.
Calculate FT. The average customer spends _18/6 = 3___ hours in the store. (4 points)
4.
The average customer is spending an extra _3-0.5 = 2.5___ hour(s) more in the store than they need to eat and drink. (2 points)
Part 3
Don’s Donuts makes donuts using a three-step process as shown in the table. Each dozen (dz) costs $5 to make and is priced at $10, giving the company a margin of $5/dz. Don’s Donuts is
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Questions
kindly do question 5 & 6 pls. thx
Kiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40 teddy bears per hour on its assembly line. The following information will assist in answering the questions that follow:
Task Information for Kiko Teddy Bear
Work Element
Task Description
Immediate Predecessor
Task Time (in seconds)
A
Cut teddy bear pattern
None
90
B
Sew teddy bear cloth
A
75
C
Stuff teddy bear
B
50
D
Glue on eyes
C
20
E
Glue on nose
C
15
F
Sew on mouth
C
35
G
Attach manufacturer’s label
B
15
H
Inspect and pack teddy bear
D,E,F,G
40
Draw a precedence diagram.
What cycle time would provide the desired output?
What is the maximum possible output of the line?…
arrow_forward
The Henry Street Mission uses volunteers to assemble carepackages for needy families during the holiday season. Themission would like to organize the work as efficiently as
possible. A list of tasks, task times, and precedence re-quirements follows:
a. If the mission wants to complete a care package every10 minutes, how many volunteers should be called in?Balance the line and calculate the efficiency. How manypackages can be assembled in a four-hour period?b. Suppose that volunteers are plentiful. Balance the lineto maximize output. What is the efficiency of the line?
How many care packages can be assembled in a four-hour period?
arrow_forward
iChange Management Plan Part 2: Peppercorn Dining AnalysisBackground:Revisit the mini-case study Peppercorn Dining from Module 7, and review the discussion posts in response to each mini-case question. How consultants see organizational issues will, in part, determine how the feedback process will be designed. Choosing a diagnostic/analytic model is no small issue. There is no evidence in the case that a particular diagnostic model is driving the data collection process (a potential problem), and there are at least two models that would work. First, the consultants could use an individual based model—such as the one described in Chapter 5. For each job at Peppercorn, the consultants could ask what their data reveals about task identity, skill variety, task significance, autonomy, and feedback in the context of Peppercorn’s structure. But this is a more limited perspective and not as good a choice. Perhaps more relevant in this case, would be an organization-level diagnostic model such…
arrow_forward
Given the following information, answer the following:
Task
Description
Immediate predecessors
Optimistic time
Most likely time
Pessimistic time
Expected Time
A
Identify equipment requirements
None
4
6
8
6
B
Solicit bids from vendors
None
6
8
16
9
C
Select a system/vendor
A,B
2
4
6
4
D
Place order for system
C
8
10
24
12
E
redesign warehouse layout
C
7
10
13
10
F
Implement new warehouse design
E
4
6
8
6
G
Design system interfaced
c
4
6
20
8
H
Integrate the interface into the system
D, F, G
4
6
8
6
I
Install the system
D, F
4
6
14
7
J
train system operators
H
3
4
5
4
k
test system
I, J
2
4
6
4
Task
Normal cost
Crashed time
Additional cost to crash 1 week
A
1000
4
450
B
1000
7
400
C
1500
2
600
D
2000
8
300
E
5000
7
1000
F
3000…
arrow_forward
Question. The following table is given for the line balancing. The target is to produce 520 units per day within an 8 hour of shift.
Do the followings:
(a) Draw the precedence diagram (use the MSWord template provided).
(b) Calculate the desired cycle time. Use the rounding to make the answer a whole number (Use MSExcel template provided).
(c) What is the theoretical minimum number of stations? (Use MSExcel template provided).
(d) Find the positional weight and the number of following tasks for each task (Use MSExcel template provided).
(e) Assign tasks according to the greatest positional weight rule (Use MSExcel template provided).
(f) Find the efficiency of this operation (Use MSExcel template provided).
Task
Immediate predecessor
Task time (second)
A
11
B
A
25
C
A
33
D
A
13
E
B
17
F
B
22
G
B
5
H
D
34
I
D
17
J
C,G,H
25
K
E,F
6
L
I,J
15
M
J,K
21…
arrow_forward
1. work flow diagram on personal accomplishments/career advancement.Please no copy paste.
arrow_forward
Let’s assume you are the new full time manager that the school has hired to take over running the wellness center and create 2 new programs to bring in more students/faculty to use the facilities. You’ve been given permission and budget to hire 2 assistant managers, 1 personal trainer, 2 employees (desk attendant/operations/floor coverage for safety) and 2 student workers (desk/attendant/operations). You need to create a proposal to give to the school on ways to improve the wellness center.
What are the hours of the fitness center? Are they different from the current hours? Why or Why not? Are there times for the teams to work out without students/faculty? What is the schedule for employees?
Proposed Hours: ____________________________________
Reasoning:
Team Work out times ( if applicable): ___________________
Employee Schedule:
Sun
Mon
Tues
Wed
Thurs
Fri
Sat
Manager
Asst. Manager 1
Asst. Manager 2…
arrow_forward
Foo1602 assignment 2 food preparatio practical 1
arrow_forward
Activity: Job Bank Scavenger Hunt This activity requires you to explore the Job Bank website's trends section to find information associated with two job roles that are of interest to you. Go to : https://www.jobbank.gc.ca/home opens in new window Instructions: 1. Find the NOC code for each position 2. Using Toronto, ON as your intended location indicate the following: • Prospects (star rating) • Low, Median, and High Wages • How many jobs are currently posted?
3 . Review the job description and skills list for each of these positions
4 . Copy and paste the expertise and skills list in your journal . Highlight the skills and expertise that you have developed through work experience in green , skills and expertise obtained through your studies in purple and missing skills / expertise in blue .
5 . Answer the following questions : • What obstacles are standing between you and the two job titles that you have just researched ? Do you have the skills and expertise…
arrow_forward
5.
Marta works on an auto assembly line. Last year she was responsible for welding the upper panel of the wheel well onto the left rear wheel area. This year, she is also responsible for welding all parts of the entire left rear wheel area and checking for quality workmanship. Marta's position underwent a job redesign using
a)
job specialization.
b)
job enlargement.
c)
job rotation.
d)
job enrichment.
arrow_forward
1. Explain human resources management in drink powder factory.
2. Explain labor specialization in drink powder factory with diagram.
3. Explain job expansion in drink powder factory with diagram.
arrow_forward
The following table details the tasks required for Indiana-based Frank Pianki Industries to manufacture a fully portable industrial vacuum cleaner. The times in the table are in minutes. Demand forecasts indicate a need to operate with a cycle time of
11
minutes.
Activity
Activity Description
Performance Time (mins)
Predecessors
A
Attach wheels to tub
5.0
−
B
Attach motor to lid
1.5
−
C
Attach battery pack
2.8
B
D
Attach safety cutoff
4.0
C
E
Attach filters
3.0
B
F
Attach lid to tub
2.0
A, E
G
Assemble attachments
3.0
−
H
Function test
3.7
D, F, G
I
Final inspection
2.0
H
J
Packing
2.0
I
a-b) One of the possible assignment of tasks to workstations is shown correctly in…
arrow_forward
what is the diagram for the below table?
task
performance time(min)
task must follow task listed below
followers
station
time
a
1
-
3
1
3
b
1
a
3
1
3
c
2
a
2
2
2
d
1
c
2
2
2
e
3
c
2
3
4
f
1
c
2
3
4
g
1
d, e, f
1
4
4
h
2
b
1
4
4
i
1
g, h
0
4
4
arrow_forward
Given the operation times provided:a. Develop a job sequence that minimizes idle time at the two work centers.b. Construct a chart of the activities at the two centers, and determine each one’s idle time,assuming no other activities are involved.JOB TIMES (minutes)A B C D E FCenter 1 20 16 43 60 35 42Center 2 27 30 51 12 28 24
arrow_forward
Question 1Rock View Restaurant is a new fast food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks:Tasks Description Task Time(InSeconds) PredecessorsA Take order 25 NoneB Receive payment 20 AC Gather drinks 35 AD Gather food 32 AE Put food etc. in bag 25 C,DF Give food to customer 10 B,E
Currently, Rock View Restaurant has a single window with one person who takes the order,gather the food, collects the money and gives the food to the customer. This takes an average of147 seconds per customer so only 25.5…
arrow_forward
Use the information in the table below (image 1):
a. Construct the Precedence Diagram.
b.The productive operating time is 55 minutes per hour for an 8-hour work. Compute the cycle time, CT, needed to obtain 50 units per hour.
OT=_____
D= ________
CT= ____________
c. Determine the minimum number of workstation, Nmin.
d. Assign tasks to workstations using the longest task-time Use the table format below. (IMAGE 2)
e. Compute the Percentage Idle Time.
f. Compute the Efficiency of the line.
g. Draw the Balanced Line.
arrow_forward
How can management planning and controlling solve the issue in an organization. solution to solve the below:
Paper work has grown exponentially with the growth in a business; while the locations are connected by email, all processes are still paper based; the accounting system in particular is a nightmare when taxes are to be paid, involving many hours and sleepless nights,
arrow_forward
Question 2:
A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly output of 28 units. Assume the shop works a 56-minute hour. Assign the tasks shown in the accompanying precedence diagram (times are in minutes) to workstations using the following rules: (SEE PHOTO)
a. What is Cycle time? (Round your answer to 1 decimal place.)
In order of most following tasks. Tiebreaker: greatest positional weight. (Use your rounded cycle time. Enter your tasks in the order they were assigned at each station as a letter between a and h in lowercase with no other text or symbols. Round your numerical answers to 1 decimal place.)
What is Efficiency? (Use your rounded cycle time in the denominator of your efficiency calculation. Round your answer to 1 decimal place.)
b. In order of greatest positional weight. Tiebreaker: most following tasks. (Use your rounded cycle time. Enter your tasks in the order they were assigned at each station as a letter between a and…
arrow_forward
There are 7 new employees starting work at the hotel today. Which of the following describes the process they will be involved in on their first day at work?
Question 5 options:
a)
Selection
b)
Orientation
c)
Recruitment
d)
Training
arrow_forward
Tip Top Staffing staffs hundreds of IT organizations with project-specific capabilities. DFDs, a data dictionary, and process descriptions are helping Lisa Nuevo and Bill Goodman build Tip Top's billing and records system's logical model. Lisa thought Tip Top's job application data forms might be improved while working on the system's logical model. Improved forms—physical implementation issue? Is Lisa straying from the task at hand by thinking how it will be done?
arrow_forward
Provide me with writing sample ideas of a brief operations end of shift report
arrow_forward
2. Jamila wants to set up a manufacturing unit, so she meets with Rashid, a humanresource manager at her company. Rashid explains that in order to decide on thehuman resource needs for the unit, they should conduct a workflow analysis. Shesuggests they start by defining the outputs of the process. To do this, what shouldJamila define?A) the processes that will be involved in manufacturingB) the number of people required for productionC) the type of products that will need to be manufacturedD) the special equipment, facilities, and systems needed for productionE) the data and information needed by the work unit
arrow_forward
Activity
Description
Predecessor
Duration (Days)
A
Send application forms
–
7
B
Get volunteer workers
–
18
C
Line up referees
–
10
D
Reserve fields
–
21
E
Receive and process forms
A
30
F
Determine age divisions
B, C, D, E
9
G
Assign fields to divisions
F
7
H
Sell program ads
B
2
I
Acquire donated items for team gift bags
B
20
J
Schedule games
G
14
K
Design ads
H
80
L
Fill gift bags
I
12
M
Process team t-shirt orders
E
10
N
Send acceptance letters
F
7
O
Design and print programs
J, K, L, N
18
P
Put together registration boxes (programs, gifts, etc.)
O
7
Q
Send out game schedules
J, K, L, N
8
R
Assign referees to games
J, K, L, N
7
S
Get trophies
F
8
T
Silk-screen t-shirts
M
17
U
Package team t-shirt orders
T
8
a) Develop a project network Activity-on-Arrow (AOA) for…
arrow_forward
Topic 4 - PROCESS&TECHNOLOGY AND CAPACITY&FACILITY DESIGNa.Discuss a few objectives of facility layout, and why capacity needed to be understood?b. Elaborate the meaning of process innovation, and how did/can you apply it in your group project given during the academic semesterc.Define in brief about; i. Process Designii. Process Strategyiii. Process Planningiv.Capital Intensityv. Process Flexibility
arrow_forward
Describe what is meant by “loading” work centers. What are
the two ways work centers can be loaded? What are two tech-niques used in loading?
arrow_forward
Explain the difference between horizontal and vertical jobenlargement and how these concepts might work at a business like McDonalds or Starbucks.
arrow_forward
For each of the problems listed, indicate precisely what or who would correspondto jobs and who or what would correspond to machines. In each case discuss whatobjectives might be appropriate and special priorities that might exist.d. Transferring long-distance phone calls from one city to another
arrow_forward
A company is setting up an assembly line to produce phones cell phones. They intend to use line balancing with time heuristics longer task. They know that the demand per hour is 40 phones and the productive time per hour is 54 minutes. Below are the data collected on the precedence and duration of tasks (in minutes):
** IMAGE ATTACHED **
A. Draw a diagram of precedence relationships.B. Compute the cycle duration per hamburger (cycle time), in minutes. C. Compute the minimum number of workstations required. D. How would you allocate tasks to workstations to minimize time idle? Evaluate your proposal.
arrow_forward
The AJAX Company is considering implementing anew accounting system, which will automate salesprocessing, cash receipts, accounts payable, andcash disbursement procedures. Roger Moore,AJAX’s CIO sent an announcement letter to theAJAX community. In the letter, Moore said: “Ihave contracted with Spartan Consulting Group todo the needs analysis, system selection, and designwork. The programming and implementation willbe performed in-house using existing IT departmentstaff. The development process will be unobtrusive touser departments because Spartan knows what needsto be done. They will work independently, in thebackground, and will not disrupt departmental andinternal audit work flow with time-consuming interviews,surveys, and questionnaires. This promises tobe an efficient process that will produce a systemthat will be appreciated by all users.”RequiredDraft a memo from George Jones, Director of InternalAudits, in response to Moore’s letter.
arrow_forward
(1) Enter the number of the following tasks for each of the tasks shown in the table below.
Task
Number of Following Task
a
b
c
d
e
f
g
h
(2)Assign tasks to stations in order of the greatest number of following tasks. Use greatest positional weight as a tiebreaker rule.
Work Station
Task Assigned
I
II
III
IV
(3) What is the daily output under this arrangement a using the cycle time from Part b(1)? (Round your answer to 2 decimal places.)
Percentage of idle time
________ %
(4) Determine the output rate that would be associated with using the maximum cycle time. (Round your answer to 2 decimal places.)
Rate of output
______________ units per day
b. (1) What is the shortest cycle time that will permit use of only two workstations? (Round your answer to 1 decimal place.)
Shortest cycle time
___________ minutes
(2) Determine the percentage of idle time that would result if two stations were used…
arrow_forward
Mr. Ahmad is a fresh graduate and he is employed at ABC Company. He is a fresh graduate and it’s his first professional job. The job pays him pretty well but he is still unhappy with job. Questions: a. What could be the possible reasons behind Mr. Ahmad being unhappy with his job? b. What will be the consequences and what adverse effects will it cause?
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON
Related Questions
- kindly do question 5 & 6 pls. thx Kiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40 teddy bears per hour on its assembly line. The following information will assist in answering the questions that follow: Task Information for Kiko Teddy Bear Work Element Task Description Immediate Predecessor Task Time (in seconds) A Cut teddy bear pattern None 90 B Sew teddy bear cloth A 75 C Stuff teddy bear B 50 D Glue on eyes C 20 E Glue on nose C 15 F Sew on mouth C 35 G Attach manufacturer’s label B 15 H Inspect and pack teddy bear D,E,F,G 40 Draw a precedence diagram. What cycle time would provide the desired output? What is the maximum possible output of the line?…arrow_forwardThe Henry Street Mission uses volunteers to assemble carepackages for needy families during the holiday season. Themission would like to organize the work as efficiently as possible. A list of tasks, task times, and precedence re-quirements follows: a. If the mission wants to complete a care package every10 minutes, how many volunteers should be called in?Balance the line and calculate the efficiency. How manypackages can be assembled in a four-hour period?b. Suppose that volunteers are plentiful. Balance the lineto maximize output. What is the efficiency of the line? How many care packages can be assembled in a four-hour period?arrow_forwardiChange Management Plan Part 2: Peppercorn Dining AnalysisBackground:Revisit the mini-case study Peppercorn Dining from Module 7, and review the discussion posts in response to each mini-case question. How consultants see organizational issues will, in part, determine how the feedback process will be designed. Choosing a diagnostic/analytic model is no small issue. There is no evidence in the case that a particular diagnostic model is driving the data collection process (a potential problem), and there are at least two models that would work. First, the consultants could use an individual based model—such as the one described in Chapter 5. For each job at Peppercorn, the consultants could ask what their data reveals about task identity, skill variety, task significance, autonomy, and feedback in the context of Peppercorn’s structure. But this is a more limited perspective and not as good a choice. Perhaps more relevant in this case, would be an organization-level diagnostic model such…arrow_forward
- Given the following information, answer the following: Task Description Immediate predecessors Optimistic time Most likely time Pessimistic time Expected Time A Identify equipment requirements None 4 6 8 6 B Solicit bids from vendors None 6 8 16 9 C Select a system/vendor A,B 2 4 6 4 D Place order for system C 8 10 24 12 E redesign warehouse layout C 7 10 13 10 F Implement new warehouse design E 4 6 8 6 G Design system interfaced c 4 6 20 8 H Integrate the interface into the system D, F, G 4 6 8 6 I Install the system D, F 4 6 14 7 J train system operators H 3 4 5 4 k test system I, J 2 4 6 4 Task Normal cost Crashed time Additional cost to crash 1 week A 1000 4 450 B 1000 7 400 C 1500 2 600 D 2000 8 300 E 5000 7 1000 F 3000…arrow_forwardQuestion. The following table is given for the line balancing. The target is to produce 520 units per day within an 8 hour of shift. Do the followings: (a) Draw the precedence diagram (use the MSWord template provided). (b) Calculate the desired cycle time. Use the rounding to make the answer a whole number (Use MSExcel template provided). (c) What is the theoretical minimum number of stations? (Use MSExcel template provided). (d) Find the positional weight and the number of following tasks for each task (Use MSExcel template provided). (e) Assign tasks according to the greatest positional weight rule (Use MSExcel template provided). (f) Find the efficiency of this operation (Use MSExcel template provided). Task Immediate predecessor Task time (second) A 11 B A 25 C A 33 D A 13 E B 17 F B 22 G B 5 H D 34 I D 17 J C,G,H 25 K E,F 6 L I,J 15 M J,K 21…arrow_forward1. work flow diagram on personal accomplishments/career advancement.Please no copy paste.arrow_forward
- Let’s assume you are the new full time manager that the school has hired to take over running the wellness center and create 2 new programs to bring in more students/faculty to use the facilities. You’ve been given permission and budget to hire 2 assistant managers, 1 personal trainer, 2 employees (desk attendant/operations/floor coverage for safety) and 2 student workers (desk/attendant/operations). You need to create a proposal to give to the school on ways to improve the wellness center. What are the hours of the fitness center? Are they different from the current hours? Why or Why not? Are there times for the teams to work out without students/faculty? What is the schedule for employees? Proposed Hours: ____________________________________ Reasoning: Team Work out times ( if applicable): ___________________ Employee Schedule: Sun Mon Tues Wed Thurs Fri Sat Manager Asst. Manager 1 Asst. Manager 2…arrow_forwardFoo1602 assignment 2 food preparatio practical 1arrow_forwardActivity: Job Bank Scavenger Hunt This activity requires you to explore the Job Bank website's trends section to find information associated with two job roles that are of interest to you. Go to : https://www.jobbank.gc.ca/home opens in new window Instructions: 1. Find the NOC code for each position 2. Using Toronto, ON as your intended location indicate the following: • Prospects (star rating) • Low, Median, and High Wages • How many jobs are currently posted? 3 . Review the job description and skills list for each of these positions 4 . Copy and paste the expertise and skills list in your journal . Highlight the skills and expertise that you have developed through work experience in green , skills and expertise obtained through your studies in purple and missing skills / expertise in blue . 5 . Answer the following questions : • What obstacles are standing between you and the two job titles that you have just researched ? Do you have the skills and expertise…arrow_forward
- 5. Marta works on an auto assembly line. Last year she was responsible for welding the upper panel of the wheel well onto the left rear wheel area. This year, she is also responsible for welding all parts of the entire left rear wheel area and checking for quality workmanship. Marta's position underwent a job redesign using a) job specialization. b) job enlargement. c) job rotation. d) job enrichment.arrow_forward1. Explain human resources management in drink powder factory. 2. Explain labor specialization in drink powder factory with diagram. 3. Explain job expansion in drink powder factory with diagram.arrow_forwardThe following table details the tasks required for Indiana-based Frank Pianki Industries to manufacture a fully portable industrial vacuum cleaner. The times in the table are in minutes. Demand forecasts indicate a need to operate with a cycle time of 11 minutes. Activity Activity Description Performance Time (mins) Predecessors A Attach wheels to tub 5.0 − B Attach motor to lid 1.5 − C Attach battery pack 2.8 B D Attach safety cutoff 4.0 C E Attach filters 3.0 B F Attach lid to tub 2.0 A, E G Assemble attachments 3.0 − H Function test 3.7 D, F, G I Final inspection 2.0 H J Packing 2.0 I a-b) One of the possible assignment of tasks to workstations is shown correctly in…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON