What is the idle time at the paint work center for the optimal schedule?
Q: The flew House needs to decide which of two coffee maker designes is better environmentally. Using…
A: To determine the model has a better design alternative, by which model shows more revenue retrieval…
Q: www.
A: According to the Michigan Leadership Studies, the leadership styles that resulted in the highest…
Q: An important consideration in establishing a measure map includes determining the a. mission of…
A: An important factor in the context of the measured map is nothing but the balanced scorecard…
Q: You are a vendor selling programs in front of the stadium of a certain pro football team that has…
A:
Q: Q1: A manufacturer wishes to determine how to produce two products A and B, so as to realize the…
A: Here the information is given for every 100 units. But in the optimal product mix, it is necessary…
Q: analysis of the output of a process has suggested that the variability is nonrandom on several…
A: Non-random variation - also named special cause variation. This sort of variation happens when a…
Q: Compare and contrast the similarities and differences between (a) multisource feedback workshops and…
A: Over time, many ways for evaluating an individual's performance have been created. Many of them have…
Q: What are professional ethics that an individual must have with a career in the area of Operations…
A: Operation management is defined as the process of managing the organization's operations and all the…
Q: A firm uses 48,700 widgets per year and can produce 300 per day. Carrying costs are $2 and setup…
A:
Q: As a part of the quality control procedures, an audit firm may maintain records indicating which…
A: The quality control system of a company entails the company's organisational structure as well as…
Q: At present, migrants from rural areas are most likely pushed to urban areas because of better…
A: Migrants refers to the people who migrates from there birth place to some other place in search of…
Q: 6. ABC foam Incorporated is a supplier of dual seat for Motorcycle company. The production will…
A: 500 pieces = 150 hours 1 piece = 150 /500 = 0.3 hour current production level 500 desired…
Q: . Describe the price–quality relationship of Food Network’s programming and its cookware products at…
A: Entrepreneurs have referred to purchaser demands for specific food sources that they have seen…
Q: Money on a credit card is borrowed and must be paid back. O True False
A: Credit Card: A credit card is a small rectangular piece of plastic or metal provided by a bank or…
Q: What are the ten hazards associated with IT project management?
A: The projects which are related to the IT (Information Technology) infrastructure, automation system,…
Q: 2. How many candy machines should you buy if market demand is 5,000 candies per day. The plant will…
A: Downtime means the time in which machine is not in running mode i.e. no production in this duration…
Q: What are the three project management limitations and how do they relate to the idea of project…
A: Project Limitations are those which display an effect on the team production, delivery procedure,…
Q: Describe any five risks that small businesses are exposed to in their operations.
A: The vast majority of small company owners consider themselves to be risk takers. Taking too many…
Q: Based on what parameters the decision of undertaking a motion and time study is made?
A: When a buyer wants to buy anything, he frequently compares the costs to those of similar items made…
Q: Ten-risks linked with IT project management?
A: IT infrastructure, information systems, and computer technology are all common topics in IT…
Q: An airline employee responsible for quarterly schedules was measured for the following repetitions.…
A:
Q: 1. A businessman needs 5 cabinets, 12 desks, and 18 shelves cleaned out. He has two part-time…
A: Note: - Since it is specified to answer question number 2 we will answer question 2 here. If answer…
Q: Very Favorable Market Unfavorable Average Market $180,000 Alternatives Market $250,000 Build new…
A: Maximax criteria are the criteria in which the best payoff of each decision alternative is…
Q: Consider a firm with a daily demand of 100 units, a production rate per day of 550 units, a setup…
A: Given data: Daily demand (d)= 100 units Number of working days per year = 300 Daily production (p)=…
Q: Drew Rosen Automation Company estimates the data entry and verifying times for four jobs as follows:…
A: Two jobs that need to be parallelly scheduled should be scheduled using Johnson-Johnson's rule. The…
Q: A logistics company applies the EOQ model to manage its inventory of spare parts used for…
A: EOQ is an ordering technique under which a company orders a determined amount of units and gets to…
Q: The catering manager of LaVista Hotel, Lisa Ferguson, is disturbed by the amount of silverware she…
A:
Q: Question 1 All of the following factors are directly or indirectly associated with declines in…
A: As per Bartleby's guidelines, we only solve one question in case multiple questions are asked…
Q: Use this table as inputs to answer the questions below: Activity Total Budgeted Duration (months)…
A: Possible paths and duration: A-G = 4 B-E-F = 9 A-D = 5 C = 2 The critical path would be B-E-F with 9…
Q: PERT and CPM techniques are used to determine the "critical path" for completing a series of related…
A: The PERT and CPM techniques are used to determine the critical path and we could also determine the…
Q: A larger and more modern main post office is to be constructed at a new location in Davis,…
A: Given data: Mail source point X Y Round trip per day 1 4 6 4 2 8 4 7 3 3 14 1 4 6 10 11…
Q: Atlanta $1,650,000 $35.00 $5.00 a. Use break-even point analysis to determine where Darren should…
A:
Q: Which of the following statements is correct for Activity G's schedule? Activity G has a slack time…
A: A project schedule network diagram shows the tasks that are to be performed in the defined sequence.…
Q: What factors an organization must consider to align with their initiative to fulfill the five…
A: An organization consists of five principles such as planning, organizing, staffing, leading and…
Q: 2) Model the following problem with integer programming. Breezy Airlines is considering the purchase…
A: since they can train 30 pilots only this means that any extra plane will not be used because there…
Q: 3. Assign trucks to delivery routes so that total costs are minimized, given the cost data shown.…
A:
Q: What is the difference between Maximum Foreseeable Loss(MFL), Probable Maximum Loss(PML), and…
A: The difference between Maximum Foreseeable Loss(MFL), Probable Maximum Loss(PML), and Estimated…
Q: In the early stages of COVID-19, the VP of Supply Chain Operations for a large international tech…
A: ANSWER : Supply chain mapping (SCM) is the most common way of documenting information across…
Q: Which of the following statements is correct for Activity G's schedule? Activity G has a slack time…
A: The early and late timings of an activity can be found by drawing the network diagram and conducting…
Q: How did you find all the points
A: To find the points, remove inequality with equality for constraints. Constraint 1 will become…
Q: Ram Roy's firm has developed the following supply, demand, cost, and inventory data. Supply…
A: Find the Given data below: Given details: Period 1 Period 2 Period 3 Demand 40 55 55…
Q: Define reliability and validity and explain how they affect the evaluation of a measure.
A: Reliability means the state of being consistent or reliable or possibility that the result will be…
Q: Q1: A manufacturer wishes to determine how to produce two products A and B, so as to realize the…
A: Here, It is an LP problem, so, we would formulate the Lp model, this is written below: Decision…
Q: Suppose a technological improvement lowers the cost of producing guava candy. At the same time,…
A: The equilibrium price is the market price where quantity supplied of goods is equal to the…
Q: Question 33 All of the following are reasons for the shift toward greater use of promotions and less…
A: Promotion refers to the activities in which a firm makes efforts to promote its products into the…
Q: 分站层和66 6665 aus of Sha合合花
A: Organizational objectives are described as the medium-term and short-term goals that are sought…
Q: H3 . Why is it important to keep potential output (Yn) steadily increasing over time?
A: Output refers to the overall production by the firm by employing all its resources and materials in…
Q: (c) In class we talked about how to model constraints like "either condition A holds or condition B…
A: 3x1 + x2 >= 5 2x1 + 2x2 >= 4 x1 + 3x2 >= 5 convert the constraints into <= as…
Q: What is the number of customers waiting in the queue on average?
A: Arrival Rate (Lambda) = 12 per hour Average Service Rate (Mu) = 60/4 = 15 per hour
Q: 1. Use the assignment method to determine the best way to assign workers to jobs, given the…
A: In assignment method we need to assign a worker to each job in such aa way that the total cost is…
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- The following jobs are waiting to be processed at JulieMorel’s machine center:JOB DATE ORDER RECEIVED PRODUCTIONDAYS NEEDED DATE ORDER DUEA 110 20 180B 120 30 200C 122 10 175D 125 16 230E 130 18 210 In what sequence would the jobs be ranked according to the fol-lowing rules: (a) FCFS, (b) EDD, (c) SPT, and (d) LPT? All dates are according to shop calendar days. Today on the planning cal-endar is day 130, and none of the jobs have been started or sched-uled. Which rule is best?TIme lert 1:08:20 tion A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 120 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task C and task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task E to be completed. Finally, task G can out of start only once task F is completed.What is the minimum number of workstations needed? O a. 8 O b. 6 O c. 5 O d. None of them e. 4 Fir NEXT PAGE EVIOUS PAGEChristine has three cars that must be overhauled by her ace mechanic, Megan. Given the following data about the cars, use least slack per remaining operation to determine Megan’s scheduling priority for each:Customer Pick-Up Remaining Overhaul Car Time (hours hence) Time (hours) Remaining Operation A 10 4 PaintingB 17 5 Wheel alignment, painting C 15 1 Chrome plating, painting, seat repair
- If the cycle time is 65.4 seconds and A is assigned as the first task in Workstation #1, what is the idle time after assigning task A? Task Task Time (seconds) Tasks That Must Precede Other Tasks Number of Following Tasks A 28 - 7 B 13 - 8 C 35 B 7 D 11 A 6 E 20 C 6 F 6 D, E 5 G 23 F 3 H 25 F 2 I 37 G 1 J 11 G, H 1 K 27 I, J 0 Total 236 a. 26.9 minutes b. 37.4 seconds c. 28.5 seconds d. 31.6 seconds e. 57.6 secondsThe following jobs are waiting to be processed at thesame machine center. Jobs are logged as they arrive:JOB DUE DATE DURATION (DAYS)A 313 8B 312 16C 325 40D 314 5E 314 3 In what sequence would the jobs be ranked according to the follow-ing decision rules: (a) FCFS, (b) EDD, (c) SPT, and (d) LPT? All dates are specified as manufacturing planning calendar days. Assumethat all jobs arrive on day 275. Which decision is best and why?The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the makespan to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are as follows: Car A B C D E Body Work (hrs) 10 5 7 3 1 Multiple Choice Where in the optimum sequence should car A be scheduled? O O O O first second third fourth Paint (hrs) 2 4 fifth 5 6 7
- Provide the difference between Slack time and Cycle-time efficiency. There are how many ways to compute the Cycle time? Explain only one way.Christine has three cars that must be overhauled by her ace mechanic, Megan. Given the following data about the cars. CUSTOMER PICK-UP REMAINING TIME (HOURS HENCE) OVERHAUL CAR TIME (HOURS) REMAINING OPERATION A 19 1 Painting Wheel alignment, painting Chrome plating, painting, seat B 26 2 14 2 repair Use least slack per remaining operation to determine Megan's scheduling priority for each. (Round your answers to 1 decimal place.) Slack Per Car Priority Remaining Operations A В C ם0 >>1.Explain the concepts of scheduling and sequencing 2.Describe staff scheduling and appointment system decisions 3.Describe how to solve two-resource sequencing problems.
- Glaudious is 45 years old university internship coordinator. He is handling 80 interns and he would like to perform the following tasks in an easy and fast way. He also encountered an accident a year ago which caused his right leg to have a bone minor fracture which caused him to limit the place he can go. He would like that he can perform the tasks anytime and anywhere. Below are the tasks of Prof Glaudios. 1) He registers the students undergoing internship, this includes the term in a schoolyear, the company name where the student is undergoing internship, directsupervisor of the intern, start of duty, Number of Hours of duty per day, andthe Job of the student-intern in the company. 2) He will also view the following: a) Individual internship record in a term-sem-school year b) Interns details in a company Based on the scenario above, model the tasks of Prof Glaudious by creating a Task Analysis.Glaudious is 45 years old university internship coordinator. He is handling 80 interns and he would like to perform the following tasks in an easy and fast way. He also encountered an accident a year ago which caused his right leg to have a bone minor fracture which caused him to limit the place he can go. He would like that he can perform the tasks anytime and anywhere. Below are the tasks of Prof Glaudios. 1) He registers the students undergoing internship, this includes the term in a schoolyear, the company name where the student is undergoing internship, directsupervisor of the intern, start of duty, Number of Hours of duty per day, andthe Job of the student-intern in the company. 2) He will also view the following: a) Individual internship record in a term-sem-school year b) Interns details in a company using the Professor Glaudious Scenario, provide the requirements specification: a. Functional b. Data c. Environmental d. User e. UsabilityThe following 5 overhaul jobs are waiting to be pro-cessed at Avianic’s Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days.Assume that all jobs arrived on day 180; today’s date is 200.JOB DUE DATE REMAINING TIME (DAYS)103 214 10205 223 7309 217 11412 219 5517 217 15Using the critical ratio scheduling rule, in what sequence wouldthe jobs be processed?