What is the critical path of the project?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

please solve within 30 minutes.

Normal Crash Normal Crash
duration
duration
cost
Activity Precedent (days)
(days)
(PHP)
A
120
100
14000
20
15
2800
40
30
30
20
50
40
60
45
B
с
D
E
F
B
с
D
B
What is the critical path of the project?
A) B-A-F-E
B) B-C-D-E
C) B-F-D-E
D) A-B-F-D-E
cost
(PHP)
12000
1800
16000
1400
3600
13500
OE) A-B-C-D-E
22000
2000
4800
18000
Transcribed Image Text:Normal Crash Normal Crash duration duration cost Activity Precedent (days) (days) (PHP) A 120 100 14000 20 15 2800 40 30 30 20 50 40 60 45 B с D E F B с D B What is the critical path of the project? A) B-A-F-E B) B-C-D-E C) B-F-D-E D) A-B-F-D-E cost (PHP) 12000 1800 16000 1400 3600 13500 OE) A-B-C-D-E 22000 2000 4800 18000
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.