The normal duration and normal cost of an activity are 18 days and Rs. 36,000 Respectively. The activity crash duration is 15 days and indirect cost is Rs. 800 per day. If cost slope is Rs. 1200 per day, then the crash cost of the activity will be
The normal duration and normal cost of an activity are 18 days and Rs. 36,000 Respectively. The activity crash duration is 15 days and indirect cost is Rs. 800 per day. If cost slope is Rs. 1200 per day, then the crash cost of the activity will be
Traffic and Highway Engineering
5th Edition
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Garber, Nicholas J.
Chapter13: Evaluating Transportation Alternatives
Section: Chapter Questions
Problem 10P
Related questions
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning