The Basics of Capital Budgeting: Evaluating Cash Flows: NPV The net present value (NPV) method estimates how much a potential project will contribute to -Select- ✓, and it is the best selection criterion. The-Select-the NPV, the more value the project adds; and added value means a [-Select- stock price. In equation form, the NPV is defined as: CF₁ CFN CF₂ CF₁ NPV = CFO + + 2 N (1+r) ¹ (1+x)² (1+r)^ ' (1+x) ' CFt is the expected net cash flow at Time t, r is the project's risk-adjusted cost of capital, N is its life, and cash outflows are treated as negative cash flows. The NPV calculation assumes that cash inflows can be reinvested at the project's risk-adjusted -Select- . When the firm is considering independent projects, if the project's NPV exceeds zero the firm should -Select-the project. When the firm is considering mutually exclusive projects, the firm should accept the project with the -Select- ✓ NPV. Project A Project B Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 10%. 0 1 3 4 -1,070 -1,070 What is Project A's NPV? Do not round intermediate calculations. Round your answer to the nearest cent. $ What is Project B's NPV? Do not round intermediate calculations. Round your answer to the nearest cent. $ 2 680 280 -Select- 300 235 + ... + 280 430 330 780 If the projects were independent, which project(s) would be accepted? would be accepted. =t=0

Managerial Accounting
15th Edition
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:Carl Warren, Ph.d. Cma William B. Tayler
Chapter12: Capital Investment Analysis
Section: Chapter Questions
Problem 1CMA
icon
Related questions
Question
The net present value (NPV) method estimates how much a potential project will contribute to Business ethics/Shareholders Wealth/Employee Benefits, and it is the best selection criterion. The Smaller/Larger the NPV, the more value the project adds; and added value means a Higher/Larger stock price. In equation form, the NPV is defined as:

 

CFt is the expected net cash flow at Time t, r is the project's risk-adjusted cost of capital, N is its life, and cash outflows are treated as negative cash flows. The NPV calculation assumes that cash inflows can be reinvested at the project's risk-adjusted RD/RS/WACC. When the firm is considering independent projects, if the project's NPV exceeds zero the firm should Accept/Reject the project. When the firm is considering mutually exclusive projects, the firm should accept the project with the Lowest Positive/Lowest Negative/Highest Postive/ Highest Negative NPV.

Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 10%.
  0 1 2 3 4
                     
Project A -1,070 680 300 280 330
Project B -1,070 280 235 430 780

What is Project A's NPV? Do not round intermediate calculations. Round your answer to the nearest cent.

$  

What is Project B's NPV? Do not round intermediate calculations. Round your answer to the nearest cent.

$  

 

If the projects were independent, which project(s) would be accepted?

Neither project / Project  A / Project B / Both Project A and B would be accepted.

If the projects were mutually exclusive, which project(s) would be accepted?

Neither project / Project  A / Project B / Both Project A and B  would be accepted.

 

The Basics of Capital Budgeting: Evaluating Cash Flows: NPV
The net present value (NPV) method estimates how much a potential project will contribute to [-Select-
and it is the best selection criterion. The -Select-the NPV,
the more value the project adds; and added value means a -Select- stock price. In equation form, the NPV is defined as:
CF1
CF₂
CFN
N CFt
NPV = CFO +
+
+
2
N
t=0
(1+r)
(1+1)^
(1+x)
Project A
Project B
CFt is the expected net cash flow at Time t, r is the project's risk-adjusted cost of capital, N is its life, and cash outflows are treated as negative cash flows. The NPV calculation
assumes that cash inflows can be reinvested at the project's risk-adjusted [-Select- When the firm is considering independent projects, if the project's NPV exceeds zero the firm
should -Select- the project. When the firm is considering mutually exclusive projects, the firm should accept the project with the -Select-
✓ NPV.
2
$
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash
flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects
have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 10%.
0
1
4
3
-1,070
-1,070
680
280
What is Project A's NPV? Do not round intermediate calculations. Round your answer to the nearest cent.
300
235
-Select-
1
280
430
+
330
780
1+r
If the projects were independent, which project(s) would be accepted?
would be accepted.
What is Project B's NPV? Do not round intermediate calculations. Round your answer to the nearest cent.
=
t
Transcribed Image Text:The Basics of Capital Budgeting: Evaluating Cash Flows: NPV The net present value (NPV) method estimates how much a potential project will contribute to [-Select- and it is the best selection criterion. The -Select-the NPV, the more value the project adds; and added value means a -Select- stock price. In equation form, the NPV is defined as: CF1 CF₂ CFN N CFt NPV = CFO + + + 2 N t=0 (1+r) (1+1)^ (1+x) Project A Project B CFt is the expected net cash flow at Time t, r is the project's risk-adjusted cost of capital, N is its life, and cash outflows are treated as negative cash flows. The NPV calculation assumes that cash inflows can be reinvested at the project's risk-adjusted [-Select- When the firm is considering independent projects, if the project's NPV exceeds zero the firm should -Select- the project. When the firm is considering mutually exclusive projects, the firm should accept the project with the -Select- ✓ NPV. 2 $ Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 10%. 0 1 4 3 -1,070 -1,070 680 280 What is Project A's NPV? Do not round intermediate calculations. Round your answer to the nearest cent. 300 235 -Select- 1 280 430 + 330 780 1+r If the projects were independent, which project(s) would be accepted? would be accepted. What is Project B's NPV? Do not round intermediate calculations. Round your answer to the nearest cent. = t
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Economic Value Added
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
EBK CONTEMPORARY FINANCIAL MANAGEMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Corporate Fin Focused Approach
Corporate Fin Focused Approach
Finance
ISBN:
9781285660516
Author:
EHRHARDT
Publisher:
Cengage