Equipment A: • The cost of equipment A is $100/ Hr • The volume per cycle is 4 CY / cycle The cycle time is 10 minutes • The equipment works 50 min / Hr Equipment B: • The cost of equipment A is $110/ Hr The volume per cycle is 6 CY/cycle The cycle time is 12.5 minutes The equipment works 50 min / Hr Which Equipment option has lower $ Cost per CY ?

Solid Waste Engineering
3rd Edition
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Worrell, William A.
Chapter9: Toward Integrated Resources Management—environmental, Political, And Economic Issues
Section: Chapter Questions
Problem 9.9P
icon
Related questions
Question
Equipment A:
The cost of equipment A is $100/ Hr
The volume per cycle is 4 CY / cycle
The cycle time is 10 minutes
The equipment works 50 min / Hr
Equipment B:
• The cost of equipment A is $110/ Hr
The volume per cycle is 6 CY / cycle
The cycle time is 12.5 minutes
• The equipment works 50 min / Hr
Which Equipment option has lower $ Cost per CY ?
Transcribed Image Text:Equipment A: The cost of equipment A is $100/ Hr The volume per cycle is 4 CY / cycle The cycle time is 10 minutes The equipment works 50 min / Hr Equipment B: • The cost of equipment A is $110/ Hr The volume per cycle is 6 CY / cycle The cycle time is 12.5 minutes • The equipment works 50 min / Hr Which Equipment option has lower $ Cost per CY ?
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Pricing of General Work
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Solid Waste Engineering
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,