"Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $3,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year: Manufacturing overhead Direct labor Department Machining Direct materials. Direct labor Manufacturing overhead. Fabricating Assembly Total Plant $ 365,750 $ 418,000 $ 94,050 $ 877,800 $ 209,000 $ 104,500 $ 313,500 $ 627,000 Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows: Fabricating $3,900 $4,600 ? Department Machining $ 200 $ 500 ? Assembly $2,300 $7,100 ? Total Plant. $ 6,400 $12,200 ? Required: 1. Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a.Compute the predetermined overhead rate for each department for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). a.What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? b.What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost?

Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter18: Pricing And Profitability Analysis
Section: Chapter Questions
Problem 30P: San Mateo Optics, Inc., specializes in manufacturing lenses for large telescopes and cameras used in...
icon
Related questions
Question
100%
"Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $3,000. It seems we're
either too high to get the job or too low to make any money on half the jobs we bid."
Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a
plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to
jobs. The following estimates were made at the beginning of the year:
Manufacturing overhead
Direct labor
Fabricating
Department
Machining
Assembly
Total Plant
$ 365,750 $ 418,000 $ 94,050 $ 877,800
$ 209,000 $ 104,500 $ 313,500 $ 627,000
Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing
costs in the three departments as follows:
Direct materials
Direct labor
Manufacturing overhead
Fabricating
$ 3,900
$ 4,600
?
Department
Machining
$ 200
$ 500
?
Assembly
$2,300
$ 7,100
?
Required:
1. Using the company's plantwide approach:
a. Compute the plantwide predetermined rate for the current year.
b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.
2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined
overhead rates based on direct labor cost. Under these conditions:
a.Compute the predetermined overhead rate for each department for the current year.
b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.
Complete this question by entering your answers in the tabs below.
Total Plant
$ 6,400
$12,200
?
4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied
overhead).
a.What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate?
b.What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost?
< Required 1A
Required 1A Required 1B Required 2A Required 2B Required 4A Required 4B
Using the company's plantwide approach, compute the plant wide predetermined rate for the current year.
Predetermined overhead rate
% of direct labor cost
Required 1B >
Transcribed Image Text:"Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $3,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year: Manufacturing overhead Direct labor Fabricating Department Machining Assembly Total Plant $ 365,750 $ 418,000 $ 94,050 $ 877,800 $ 209,000 $ 104,500 $ 313,500 $ 627,000 Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows: Direct materials Direct labor Manufacturing overhead Fabricating $ 3,900 $ 4,600 ? Department Machining $ 200 $ 500 ? Assembly $2,300 $ 7,100 ? Required: 1. Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a.Compute the predetermined overhead rate for each department for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. Complete this question by entering your answers in the tabs below. Total Plant $ 6,400 $12,200 ? 4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). a.What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? b.What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost? < Required 1A Required 1A Required 1B Required 2A Required 2B Required 4A Required 4B Using the company's plantwide approach, compute the plant wide predetermined rate for the current year. Predetermined overhead rate % of direct labor cost Required 1B >
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Pricing Decisions
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning