As a process engineer, you are designing sedimentation tanks for a new drinking water treatment plant using a conventional treatment process. The design flow is 0.50 m³/s. The major target of the WTP is to remove Turbidity from water using alum as coagulant. The detention time = 4.5 hrs and number of sedimentation tanks, N=2. Q V = 0 A S V Ө Q L = Vwater x 0 1 day = 86,400 s Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display. Long rectangular and circular m³/d. m² 40 30 20 70 57 = Application Alum or iron coagulation Turbidity removal Color removal High algae Lime softening Low magnesium High magnesium Source: AWWA. 1990. Upflow solids-contact m³/d. m² 50 35 130 105

Solid Waste Engineering
3rd Edition
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Worrell, William A.
Chapter2: Municipal Solid Waste Characteristics And Quantities
Section: Chapter Questions
Problem 2.9P
icon
Related questions
Question
100%
Based on the typical sedimentation tank overflow rate for the above problem, The
in m.
water depth, H, is_
1) 6.5
2) 4.5
3) 5.5
4) 7.5
5) 3.5
Transcribed Image Text:Based on the typical sedimentation tank overflow rate for the above problem, The in m. water depth, H, is_ 1) 6.5 2) 4.5 3) 5.5 4) 7.5 5) 3.5
As a process engineer, you are designing sedimentation tanks for a new drinking water
treatment plant using a conventional treatment process. The design flow is 0.50 m³/s.
The major target of the WTP is to remove Turbidity from water using alum as
coagulant. The detention time = 4.5 hrs and number of sedimentation tanks, N=2.
V
0
A
S
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
Long rectangular
and circular
m³/d. m²
40
30
20
70
57
V
0
Q
L = Vwater x 0
1 day = 86,400 s
Application
Alum or iron coagulation
Turbidity removal
Color removal
High algae
Lime softening
Low magnesium
High magnesium
Source: AWWA, 1990.
Upflow
solids-contact
m³/d. m²
50
35
130
105
Transcribed Image Text:As a process engineer, you are designing sedimentation tanks for a new drinking water treatment plant using a conventional treatment process. The design flow is 0.50 m³/s. The major target of the WTP is to remove Turbidity from water using alum as coagulant. The detention time = 4.5 hrs and number of sedimentation tanks, N=2. V 0 A S Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display. Long rectangular and circular m³/d. m² 40 30 20 70 57 V 0 Q L = Vwater x 0 1 day = 86,400 s Application Alum or iron coagulation Turbidity removal Color removal High algae Lime softening Low magnesium High magnesium Source: AWWA, 1990. Upflow solids-contact m³/d. m² 50 35 130 105
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Storm sewers and detention
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Solid Waste Engineering
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,