A project for improving a billing process has the following precedence relationships and activity times: Activity Time (weeks) 2 Activity A B C₁ DEFGH 12 7 12 11 679 Immediate Predecessor(s) A B, C B D E F, G
Q: Harlen Industries Limited has a simple forecasting model whose forecast demand has been plotted…
A: In this question, we have the table data for an 8 periods duration, for each period, we have actual…
Q: Mark Gershon, owner of a musical instrument distributorship, thinks that demand for guitars may be…
A: Using least Square method Marron 5 TV appearancr(X) Demand for Guitars(Y X^2 Y^2 XY 3 4 9 16…
Q: min 8x1+6x2 subject to 4x1+2x2 ≥ 20 -6x1+4x2 ≤ 12 X1+X2 ≥ 6 X1, X2 20
A: "Since you have asked multiple question, we will solve the first question for you. If you want any…
Q: A project to build a new bridge seems to be going very well since the project is well ahead of…
A: Activities Planned value(P) Actual cost(A) Estimate value(E) 1 $1,423,000 $1,303,000 $1,423,000…
Q: On part D, the $600 was wrong. Is there another possible solution?
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Need Answers for questions D,E, and F ONLY
A: Given data is
Q: Round Tree Manor is a hotel that provides two types of rooms with three rental classes: Super Saver,…
A: Let, X1S = Reservations to be accepted for type 1 room and super saver rental class X1D =…
Q: Question 3 Regular output capacity is 130 units per month. Regular cost per unit = K600. Overtime…
A: Explanation: Level: If demand or forecast is greater than production, it goes backlog and satisfied…
Q: Your vice president asked you what the Estimate at Completion (EAC) will be for a small project you…
A: Budget at completion (BAC) = $50,000 Actual cost(AC) = $40,000 Earned value(EV) = $30,000 Calculate…
Q: Briefly discuss each of these terms related to the historical evolution of operations management: a.…
A: Note- Hi! Thank you for the question, As per the honour code, we are allowed to answer three…
Q: A U.S company has two manufacturing plants, one in the United State and one in another country. Both…
A: Disclaimer: “Since you have asked multiple questions, we will solve the first question for you. If…
Q: You are a purchasing director for a group of grocery stores in the northeastern United States. You…
A: An agreement can be non-formal and casual or written, a contract may be written or verbal, however,…
Q: As you develop your project closeout documents, you begin to review the project deliverables and…
A: Here, we are developing the documents for the project closeout process, so, we need to review the…
Q: Mark has just been fired as the college bookstore manager for setting prices too low (only 20…
A: Given data is Profit by small if the demand is good = P50,000 Loss by small if the demand is low =…
Q: Your answer will be the production hours needed to execute your production plan - rounded to the…
A: Production is the process in which inputs are combined to have the required output. It includes a…
Q: The main input for master scheduling schedule is: O a. Long term forecasting O b. Aggregate…
A: Ans) 1) Master Scheduling Schedule takes sales forecast as a Input. MPS is an Input to Aggregate…
Q: Lenovo uses the ZX-81 chip in some of its laptop computers. The prices for the chip during the last…
A: 2 month moving average is a forecasting model which considering forecast as the average value of…
Q: Problem 10-21 (Algo) A process that produces computer chips has a mean of .04 defective chips and a…
A: Given data is Mean = 0.4 Standard deviation(sigma) = 0.003 USL = 0.045 defective LSL = 0.035…
Q: 2. A bicycle manufacturer has three assembly plants at three different cities (City 1, City 2, City…
A: Find the given details below: Warehouse Retailer Retailer 1 Retailer 2 Retailer 3 Warehouse 1…
Q: Brown's, a local bakery, is worried about increased costs particularly energy. Last year's records…
A: Productivity is the ability to produce in an effective and efficient manner in an organisation.
Q: Twelve identical products were put on test for 65 days, by which time 9 had failed at 21, 25, 29,…
A: Given data: The total number of days of operation = 21, 25, 29, 33, 38, 43, 49, 56 & 65 Products…
Q: Product X currently sells for $12 per unit. The variable costs is $4 per unit and 10,000 units are…
A: Break even point is a point at which the company's production cost and production revenue are equal.
Q: a. Which process, Alpha or Beta, is more productive? Process has% higher labor productivity. Process…
A: Process Alpha: Labor productivity = Total value of Output A and B/Total labor cost of A and B = [(80…
Q: Case study: container shortage challenges Unexpected events have resulted in a global container…
A: The given case study is about the situation of container shortage due to the pandemic. The shipping…
Q: Question I - You are a co-founder of a start-up firm making electronic sensors. After a year of…
A: Due to the superiority of the new sensor, which will improve purchases and disrupt the market,…
Q: 140 Friday Using this table above, solve for Mean Absolute Deviation (MAD) xample 9.6568->9.66
A: Absolute error = |actual-forecast| MAD = Average |actual-forecast|
Q: In what way does analytics help the manager in their business operations?
A: Business Operations:- Business operations are the regular tasks that businesses complete to increase…
Q: following organizations. In doing this, first, identify the outputs of the organization, and then…
A: Operations Management:- The practise of operations management involves monitoring corporate…
Q: A company uses a special widget (SP) in its production process. The company uses 100 SP units per…
A: Given data, Annual demand=Monthly uniform demand×Total number of months in a year Annual…
Q: Metropolitan Manila has four incinerator sites for processing solid waste. There are five garbage…
A: Given data is
Q: Discuss the use of the Program Evaluation and ReviewTechnique (PERT) to schedule the tasks of a…
A: In a project management scenario, scheduling is described as listing the milestones, deliverables,…
Q: Café Michigan's manager, Gary Stark, suspects that demand for mocha latte coffees depends on the…
A: Given, Price Number Sold 2.7 770 3.6 550 1.9 975 4.2 245 3.2 315 4.05 480 y =…
Q: Wheels Distributors sells three types of tires to the commercial market. Type A. Type B and Type…
A: The expected value of perfect information is the price that one would be willing to pay in order to…
Q: a) Labor productivity per labor hour for these tires = tires/labor hour (round your response to two…
A: Productivity is the relationship between the volume of the input and output that is calculated in…
Q: A caterer prepares 2,000 meals for a client’ company event consuming the following resources: Labor…
A: Total output (O)= 2000 meal Number of working hour (N)= 6 hr Calculate Labor productivity Labor…
Q: A company that makes shopping carts for supermarkets and other stores recently purchased some new…
A: Productivity is the measure of output produced per input used. Productivity = output/input
Q: 10. Describe each of these systems: craft production, mass production, and lean production. II. Why…
A: Explanation of each of the system: 1) Craft Production: Craft production means manufacturing of…
Q: An initial time study was done on a process with the following results (in minutes). Based on the…
A: Element Obs 1 Obs 2 Obs 3 Obs 4 Obs 5 Average Performance rating Normal time 1 4 3 5 4 3…
Q: Every year, volunteers administer flu vaccine shots at a Medical Centre. The process involves four…
A: Note: - Since we can answer only three subparts, we will answer the first three subparts here. If an…
Q: Discuss the usefulness of Gantt charts in the scheduling process.
A: Scheduling is the process of arranging production activities in order to complete the manufacturing…
Q: List the tool of quality in operation management
A: Operation management is performed in each manufacturing organization. It all deals with the…
Q: The Swanky Hotel provides room service for its guests. The process for room service begins with a…
A: Find the given details below: Given details: Time taken for an order 5 minutes Time taken for…
Q: Subject: Logistic management Q): What are the concern of inventory control & overall objective of…
A: Inventory management:- Businesses may decide which goods to order when and in what amounts by using…
Q: Dave Fletcher was able to determine the activity times for constructing h ser scanning machine.…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: The following table lists the components needed to assemble an end item, lead times (in weeks), and…
A: An MRP plan helps to keep the inventory levels optimal. Optimal inventory level helps to reduce the…
Q: 2.1 Determine the EOQ of an item for spares inventory replenishment, where: a) The cost per unit is…
A: Annual demand(D) = 250 Cost per unit(Cu) = 1500 Carrying/ Shipment cost(S) = 750 Holding cost =…
Q: You work as a supervisor in a manufacturing firm. The company has implemented a balanced-scorecard…
A: A balanced Scorecard is a management approach used by organizations to monitor the internal…
Q: Give four ideas that you can recall about demonstration of non verbal communication, listening…
A: Introduction: Professional or otherwise, there is no part of life where effective communication…
Q: Mark Gershon, owner of a musical instrument distributorship, thinks that demand for guitars may be…
A: Forecasting is a technique used to predict future outcomes on the basis of past data. Business…
Q: (a) Use the graphical solution procedure to find the optimal solution. What is the value of the…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Step by step
Solved in 2 steps with 3 images
- BSOP 588 Managing QualityAll Assignments Course Projects, Midterm and Final ExamWeek 2 Course Project:BSOP 588 Week 2 Project Proposal (Toyota Motor Corporation)Week 3 Assignments:Week 3 Paper; Measuring Customer Service – MCS (Jan 2013)Week 3 Paper; Measuring Customer Satisfaction (July 2014)Week 4 Midterm ExamSET 1Page 1Question (TCO A) Compare and contrast the evolution of quality and the role it played in the management of U.S. and Japanese business firms from the 1950s to the present.Question (TCO B) Compare and contrast the following definitions of quality. Definition 1: Quality is the totality of features and characteristics of a product or service that bears on its ability to satisfy given needs. Definition 2: Quality is meeting or exceeding customer expectations.Question (TCO A) Explain the three core principles of total quality.Question (TCO H) Identify and discuss five differences between service and manufacturing organizations.Question (TCO B) Cite two ways that the…The following are some check points: * Problem 6: Month 9 forecast: 26.333; Month 9 error: -3.333 * Problem 7: Month 7 forecast: 22.68; Month 7 error -0.68 * Problem 16A: ROLLED DOWN unit forecast for part C is 22, F is 2, I is 254, and L is 3.A B с D E FL ד G H J K L M N P R S T U V 1 On Week 3 Forecast 4 2 a) Smell Fresh Customer Orders hand 1 2 20 20 5 3 5 PAB 20 50 30 3222 4 5 6 7 8 Problem 6: Georgia Clay and Gravel was updating the MPS record for one of its products, Smell Fresh Cat Litter. Partially-completed MPS time-phased record is given below. 20 30 30 30 30 30 Week 10 30 50 20 40 10 Item: Smell Fresh On hand 1 6 Available to Promise 7 MPS 50 50 50 50 Forecast 20 8 MPS lot size = 50 9 20 10 On Week hand 2 3 4 5 6 7 8 9 20 53 43 78 30 30 30 30 30 3220 2233 -250 30 10 30 50 6 8 45 12 13 14 PAB 15 11 b) Smell Fresh Forecast Customer Orders Available to Promise 16 MPS 17 MPS lot size=50 18 19 20 21 23 24 222 Orders Projected available balance Available-to-promise MPS MPS Lot Size = 50. 50 20 40 10 50 50 50 a) Complete the MPS time-phased record (the first table on the left). The following events occurred during week 1: • Actual demand during week 1 was 25 units. • Marketing forecasted that 40 units would be needed for…
- What is Open System Task Analysis (OSTA)?week 5In this discussion thread, we will safety and security in hotels.As most of you been doing so far, be sure to post elaborately and include research where appropriate. Remember that solid and elaborate posts will get you closer to full credit in the threaded discussions.Given the need for heighten security, how can hotels ensure their guests that they are safe in their hotels? Do you see any section of a hotel that is vulnerable to unsafe activity?diss 2Class,In this discussion thread, we will talk about TQM. Be sure to read about TQM in our textbook so you understand what it is all about. Then, we will develop a discussion.As most of you been doing so far, be sure to post elaborately and include research where appropriate. Remember that solid and elaborate posts will get you closer to full credit in the threaded discussions.As a hotel general manager how can you promote TQM within your hotel staff? Do you believe that TQM is a valuable management option to use in the hotel…3. General Construction Company General Construction Company has a contract to build three lower‐income apartment buildings for the city of Santa Fe, New Mexico. During the construction of the first building, the Project Manager formed an auditing team to audit the construction process for each building. He asked the team to develop a list of minimum requirements for the projects and use this as a baseline in the audit. While reviewing the contract documents, one of the audit team members found a discrepancy between the contract minimum requirements and the City’s minimum requirements. Based on his findings, he has told the project manager that he has decided to contact the city administrator and discuss the problem. Question: If you were the project manager, how would you handle this situation? How can a customer be assured of satisfactory project completion?
- How do firms decide what the upper and lower tracking limits should be?Identify the term being described for each of the following: f. The statistical distribution used to describe path variability.An electrical contractor's records during the last five weeks indicate the number of job requests: Week: 1 2 3 4 5 Requests: 25 27 25 26 27 Click here for the Excel Data File Predict the number of requests for week 6 using each of these methods:
- Which of the following information is required from the client for 'preliminary estimating'? Select the BEST combination. Select one: а. Site location, risk register, project requirements, budget constraints. b. Site location, key dates, sustainability strategy, budget constraints. Site location, building use, risk register, budget constraints. ос. O d. Site location, building use, key dates, budget constraints.2. The following figure demonstrate the personnel involved in any project from sampling to data user. Discuss the hierarchy and role of each personnel. Project manager Sampling - Field personnel - Field engineer - Geologist Soil specialist Data user Lab analysis - Chemist Data analysis Statistician Client Decision maker QA/QC specialistExplain when you think a baseline should be updated and why.