* 4 Roy Creasey Enterprises, a machine shop, is planning to move to a new, larger location. The new buikding will be 60 feet kong by 40 foet wide. Creasey envisions the buikding as having six distinct production arcas, roughly oqual in sie. He foels strongly about safety and intends to have marked pathways throughout the building to facilitate the movement of people and materials. See the following building schematic. Bulding Schematie (with wok aras 1-4) His foreman has completod a month-long study of the number of koads of material that have moved from one process to another in the current building. This information is contained in the follow ing flow matrix. Flow Matrix Between Production Processes FROM MATERIALS WELDING ORILLS LATHES GRINDERS BENDERS Matera 100 50 Widing 25 Dris 25 Lthes 25 20 Grinders s0 100 Bender 10 20 Finally, Creasey has developed the following matris to indicate distances betwoen the work arcas shown in the building schematic Distance Between Work Areas 20 40 20 40 60 20 40 20 40 60 40 20 20 40 20 What is the appropriate layout of the new building Px elsls

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter5: Network Models
Section5.3: Assignment Models
Problem 12P
icon
Related questions
Question

4

9.4
Roy Creasey Enterprises, a machine shop, is planning
to move to a new, larger location. The new buikling will be 60 feet
long by 40 feet wide. Creasey envisions the buikling as having six
distinct production areas, roughly equal in size. He feels strongly
about safety and intends to have marked pathways throughout
the building to facilitate the movement of people and materials.
See the following building schematic.
Building Schematic (with work areas 1-6)
His foreman has completed a month-kong study of the number of
loads of material that have moved from one process to another in
the current building. This information is contained in the follow-
ing flow matrix.
Flow Matrix Between Production Processes
TO
FROM
MATERIALS WELDING DRILLS LATHES GRINDERS BENDERS
Materials
100
50
50
Welding
25
50
Drils
25
50
Lathes
25
20
Grinders
50
100
Benders
10
20
Finally, Creasey has developed the following matrix to indicate
distances between the work areas shown in the building schematic.
Distance Between Work Areas
2
3
4
5
20
40
20
40
60
2
20
40
20
40
3
60
40
20
4
20
40
20
What is the appropriate layout of the new building? Px
Transcribed Image Text:9.4 Roy Creasey Enterprises, a machine shop, is planning to move to a new, larger location. The new buikling will be 60 feet long by 40 feet wide. Creasey envisions the buikling as having six distinct production areas, roughly equal in size. He feels strongly about safety and intends to have marked pathways throughout the building to facilitate the movement of people and materials. See the following building schematic. Building Schematic (with work areas 1-6) His foreman has completed a month-kong study of the number of loads of material that have moved from one process to another in the current building. This information is contained in the follow- ing flow matrix. Flow Matrix Between Production Processes TO FROM MATERIALS WELDING DRILLS LATHES GRINDERS BENDERS Materials 100 50 50 Welding 25 50 Drils 25 50 Lathes 25 20 Grinders 50 100 Benders 10 20 Finally, Creasey has developed the following matrix to indicate distances between the work areas shown in the building schematic. Distance Between Work Areas 2 3 4 5 20 40 20 40 60 2 20 40 20 40 3 60 40 20 4 20 40 20 What is the appropriate layout of the new building? Px
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 7 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,