Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $110,700 Number of moves 4,500 Engineering 153,900 Number of change orders 9,000 Other overhead 310,000 Direct labor hours 50,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job 13-45 Job 13-46 Beginning balance $24,900 $19,800 $2,900 $0 Direct materials $5,800 $9,900 $13,200 $9,500 Direct labor cost $810 $1,080 $1,560 $130 Job 13-43 Job 13-44 Job 13-45 Job 13-46 Number of moves 45 48 33 4 Number of change orders 27 40 23 18 Direct labor hours 810 1,080 1,560 130 By July 31, Jobs 13-43 and 13-44 were completed and sold. Jobs 13-45 and 13-46 were still in process.

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter6: Activity-based, Variable, And Absorption Costing
Section: Chapter Questions
Problem 13MC: Activity-based costing systems: A. use a single predetermined overhead rate based on machine hours...
icon
Related questions
icon
Concept explainers
Topic Video
Question
Assignment/takeAssignmentMain.do?invoker%-Dassignments&takeAssignmentSessionLocator=Dassignment-take&
eBook
Required:
1. Calculate the activity rates for each of the three overhead activities. Round all activity rates to the nearest
Materials handling rate
26.1 per move
Engineering rate
per change order
Other overhead rate.
per direct labor hour
2. Prepare job-order cost sheets for each job showing all costs through uly 31.
When required, round your answers to the nearest dollar. If an amount is zero, enter "0"
Heitger Company
Job-Order Cost Sheets
Job 13-43
Job 13-44
Job 13-45
Job 13-46
Balance, July 1
$4
Direct materials
Direct labor cost
Materials handling
Engineering
Other overhead
Total
3. Calculate the balance in Work in Process on July 31.
$4
4. Calculate the cost of goods sold for July.
5. What if Job 13-46 required no engineering change orders? What is the difference in the new cost of Job 13-46?
How would the cost of the other jobs be affected?
%24
%24
64
624
Transcribed Image Text:Assignment/takeAssignmentMain.do?invoker%-Dassignments&takeAssignmentSessionLocator=Dassignment-take& eBook Required: 1. Calculate the activity rates for each of the three overhead activities. Round all activity rates to the nearest Materials handling rate 26.1 per move Engineering rate per change order Other overhead rate. per direct labor hour 2. Prepare job-order cost sheets for each job showing all costs through uly 31. When required, round your answers to the nearest dollar. If an amount is zero, enter "0" Heitger Company Job-Order Cost Sheets Job 13-43 Job 13-44 Job 13-45 Job 13-46 Balance, July 1 $4 Direct materials Direct labor cost Materials handling Engineering Other overhead Total 3. Calculate the balance in Work in Process on July 31. $4 4. Calculate the cost of goods sold for July. 5. What if Job 13-46 required no engineering change orders? What is the difference in the new cost of Job 13-46? How would the cost of the other jobs be affected? %24 %24 64 624
/takeAssignment/takeAssignmentMain.do?invoker=Dassignments&takeAssignmentSessionLocator%3Dassignment-take&inprogress%-false
☆ ロ
eBook
Job Costs Using Activity-Based Costing
Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and
related drivers. Budgeted information for the year is as follows:
Activity
Cost
Driver
Amount of Driver
Materials handling
$110,700 Number of moves
4,500
Engineering
153,900 Number of change orders
9,000
Other overhead
310,000 Direct labor hours
50,000
Heitger worked on four jobs in July. Data are as follows:
Job 13-43
Job 13-44
Job 13-45
Job 13-46
Beginning balance
$24,900
$19,800
$2,900
$0
Direct materials
$5,800
$9,900
$13,200
$9,500
Direct labor cost
$810
$1,080
$1,560
$130
Job 13-43
Job 13-44
Job 13-45
Job 13-46
Number of moves
45
48
33
4
Number of change orders
27
40
23
18
Direct labor hours
810
1,080
1,560
130
By July 31, Jobs 13-43 and 13-44 were completed and sold. Jobs 13-45 and 13-46 were still in process.
Required:
Previous
Next
^OEO4) 1:25
Transcribed Image Text:/takeAssignment/takeAssignmentMain.do?invoker=Dassignments&takeAssignmentSessionLocator%3Dassignment-take&inprogress%-false ☆ ロ eBook Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $110,700 Number of moves 4,500 Engineering 153,900 Number of change orders 9,000 Other overhead 310,000 Direct labor hours 50,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job 13-45 Job 13-46 Beginning balance $24,900 $19,800 $2,900 $0 Direct materials $5,800 $9,900 $13,200 $9,500 Direct labor cost $810 $1,080 $1,560 $130 Job 13-43 Job 13-44 Job 13-45 Job 13-46 Number of moves 45 48 33 4 Number of change orders 27 40 23 18 Direct labor hours 810 1,080 1,560 130 By July 31, Jobs 13-43 and 13-44 were completed and sold. Jobs 13-45 and 13-46 were still in process. Required: Previous Next ^OEO4) 1:25
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 4 images

Blurred answer
Knowledge Booster
Costing Systems
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Principles of Cost Accounting
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher: