Target Completion method b. critical path method c. create 2 ways of network diagram d.conclusion
Q: As the Operations Manager of Shane Manufacturing Ltd., you are given the task to balance the…
A: Please find the attached answer in step 2
Q: Task time estimates for a production line setup project at XYZ Company are as follows; Activity Time…
A: We are authorized to answer three subparts at a time since you have not mentioned which part you are…
Q: What is the difference between an activity-on-arrow(AOA) network and an activity-on-node (AON)…
A: Activity on Arrow (A-O-A):- It is made out of bolts and hubs. The bolts address the exercises,…
Q: Construct a network diagram for the project. a. b. What are the project completion time and the…
A: Honor Code: Since you have posted a question with multiple subparts, we have solved the first three…
Q: Draw an Activity on Arrow network diagram
A: Given, Activity duration precedent A 3 - B 2 A C 2 A, B D 5 C E 4 D F 6 C, D G…
Q: Develop an "activity on Node" network diagram for this project and answer the following questions…
A: Project duration is the total time taken to complete the project successfully measurable in days or…
Q: Based on the set of activities below Description Task Must Follow Time (Weeks) Draw data flow A None…
A: PERT Diagram: Kindly find the PERT diagram below: Calculation methods: Assume 0 for start…
Q: You are the project manager of the software installation project in Table 7.12. You would like to…
A: Network has the following paths which explains the network diagram. Duration of the path is sum of…
Q: sen's regular customers asked him to prepare an estimate for the restoration of a 1964 model 356SC…
A: Correct project network is
Q: (a) Draw a project netvork. (Submit a file vith a maximum size of 1 MB.) Browse. No file selected.…
A: A project schedule network diagram shows the sequential and analytical association between tasks in…
Q: The process used for patient registration, consultation, blood test, X ray and other tests in a…
A: Operations management is an area of management dealing with production, storage and delivery of…
Q: A) Draw Precedence diagram (PD). B) Calculate completion data, what is completion data. C) Identify…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Suppose you are a project manager, and you have to manage a project with activities and their…
A: Task Duration Predecessors A 5 B 8 A C 3 B D 4 A E 5 C F 7 C G 6 D, E H 8 F I…
Q: b) Herlich's project manager, Ruby, believes that for the new product to succeed, it must be…
A: Find the Given details below: Activity Predecessors Duration Cost (RM) Crashed duration Crash…
Q: The Advanced Tech Company has a project to design anintegrated information database for a major…
A:
Q: When developing a Work Breakdown Structure (WBS) for a project, your team can organize the second…
A: A work breakdown structure is a project structure method where the components, activities, and…
Q: a) Draw the AON project network diagram. b) Calculate the expected time of each activity? (Round…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: a. Construct an activity-on-arrow precedence diagram for each of the following cases. Note that each…
A: 4(a) The activity-on-arrow precedence diagram for case 1 is as follows:
Q: Create a labelled network diagram. b) What is the % increase of project costs if the project is to…
A: Project crashing indicating the process of reducing project duration by crashing activities using…
Q: A. Create the NETWORK DIAGRAM B. Theprocesses that are included in the critical path are: for…
A: A project schedule network diagram shows the sequence of the task that is performed to complete a…
Q: Which one of the following is NOT a tool/technique for developing a project schedule? a.…
A: A project schedule is a timeline that outlines the start and end dates of all project tasks, how…
Q: Which one is NOT a basic output of a PM network analysis? Select one: a. Identification of the…
A: One of the important tools that are widely used in project management is network analysis. It is…
Q: Draw and analyze a project network diagram to answer the following questions: What is the most that…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: Create an AOA diagram based on the information Task A, duration 6, dependent on none Task B,…
A: The AOA network diagram is the project diagram that shows the project activities on arrows i.e., the…
Q: A. target Completion Date B. Critical Path Method C. create two ways of network Diagram
A: Project network is the graphical representation of project activities and their duration to complete…
Q: Build a PERT Network Diagram for a 3-month project with 6 activities (A to F) and 5 nodes
A: The answer is as below:
Q: How does activities along the critical path of a network diagram impacts the project as a whole?
A: Project management has mainly two types of techniques such as PERT analysis and CPM analysis. CPM is…
Q: The Porsche Shop, founded in 1985 by Dale Jensen, specializes in the restoration of vintage Porsche…
A: Given data: *As per guidelines first three parts are answerable in multipart questions,…
Q: Hoosier Burger Juan Rodriquez has assigned you the task of requirements determination for the…
A: a. Assume you are preparing the customer satisfaction questionnaire. What types of questions would…
Q: The activities, their durations and precedences for designing, writing and installing a bespoke…
A: Note: - Since the exact question to be answered is not specified we will answer the first question…
Q: Dr. Ell has been given a budget of $10,000 to organize a conference at her university in less than…
A: Forward Pass:Early Start (ES)= Maximum (or Highest) EF value from immediate Predecessor(s)Early…
Q: Material Requirement Planning (MRP) I. Introduction (minimum of 6 sentences) II. Body (minimum of 10…
A: Materials Requirement Planning is the process of buying materials, supplies and components from…
Q: What are three choices that may be used in a project depending on the layout of a decision tree?…
A: INTRODUCTION: Decision-making is a critical skill for managers in organizations. The ability to make…
Q: (a) Explained the reason of applying probabilistic time estimate (PERT) instead of using CPM in…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: b) Provide a brief explanation of the main difference between a Work Breakdown Structure and Network…
A: A project network diagram is shown as a chart with a sequence of boxes and arrows.
Q: Entrepreneur Andrew Field bought a print shop and used his selling skills to boost sales to about $1…
A: 1). Handling excess capability would have been difficult without the web as the net, eliminates the…
Q: Below matrix shows one of the important data used in project management, identify the name of the…
A: The matrix shown in the question is named as RACI Chart or RACI Matrix. The RACI Chart or RACI…
Q: Power Builders Inc. is planning for an upcoming job with a large client. They have listed the…
A: Given data is
Q: For each of the following network diagrams, determine both the critical path and the expected proj-…
A: The network diagrams for critical path can be constructed in two ways: Arrow to Node - AON Arrow to…
Q: Constraints are those factors that can limit a project. Which of the following are considered…
A: Project management is the management that requires a unique type of skills processes resources and…
Q: a. Use the Table 1 above to develop a network diagram. b. Calculate the Early Start (ES), Early…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: a) Prepare the Activity Node Diagram and identify the Critical Path
A: “Since you have asked multiple question, we will solve the first question for you. If you want any…
Q: Target Completion B. Critical Path Method C. Create 2 ways of network Diagram D. Conclusion
A: The answer is as below:
Q: The VOXN Cinema is installing a new system to enhance the quality of movies shown. Assume that the…
A: A. List of possible eight events to expand a Cinema: Find a location Build up the area Frame and…
Q: Project network diagram (PND) is a graphical diagram of project schedule represented the whole…
A: The question is related to Arrow diagram. The Path having the longest duration is the Criticial…
Q: Below is the first set of activities (Phase I) in constructing a new house, the respective time…
A: Find the Given details below: Activity Description Predecessor Duration (Weeks) A Clear site -…
Q: III. Evaluate the below statement according to the project management life cycle In this phase of…
A: The prior competency of a project manager is to achieve a thorough knowledge of the life cycle of…
Q: What is the point at which an owner can begin to occupy a building or use it for its intended…
A: There are a lot of stages in the completion of a construction project. Each stage has its own…
your final answer must include the following
a. Target Completion method
b. critical path method
c. create 2 ways of network diagram d.conclusion
Step by step
Solved in 5 steps with 1 images
- 1) Pre-tender planning: a. Selection of site b. Estimate and evaluate predicted risks in the project. c. Pool the companies past experiences knowledge and specialists. d. None of the above 2) Project Consultant is responsible for: a. Site preparation b. Supervises and coordinates the work in the project c. Writing Claims d. None of the above 3) The estimated time required to perform an activity, is known as: a. Total float time. b. Independent float time. c. Free float time d. None of the above 4) Organizing of a project is: a. Arrangement of resources b. Directing of workers c. A controlling system d. None of the above 5) Project manager a. Must have a signed contract b. Can start before having a signed contract c. Not responsible for this d. all of the above 2 6) The total estimated cost required to perform a project , is known as a. Budget b. Fund c. Cash flow d. All the above 7) Subcontractor may be : a. Electrical contractor b. Specialist contractor c. Painter d. all of the above…V what is feasibility Report ?Define when and why we need it And also define who prepare this document.6 Problem 13-3 (Algo) The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item End L C K B J G H Lead Time 1 2 3 433 mm 3 3 Amount on Hand 0 Click here for the Excel Data File Additional units 17 23 34 25 7 0 **** a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint. You don't need to develop an MRP plan.) I Direct Components L(2), C(1), K(3) B(2), J(3) G(2), B(2) H(4), B(2) Q Search W
- i. Define Scope Planning ii.Purpose of Scope Definition iii.Explain the documents needed for Scope Change Control↓ ← M Gmail UNILUS | E X ChatGPT X YouTube GBS 660_A X Maps GE News C + File C:/Users/nemet/Desktop/UNILUS/2024/GBS%20660_Assignment%20Distance%20January%202024%20(1).pdf Translate GBS 660_Assignment Distance January 2024 (1).pdf Production X Lusaka Times-Zamb... R Browse Map | Rulac Item cost per Unit Setup cost 4 / 4 2 80 6-Hour D X Inventory carrying cost per year Weekly Net Requirement 1 105 3 130 QUESTION 2: The determination of lot sizes in an MRP system is a complicated and difficult problem. Lot sizes are the part quantities issued in the scheduled receipt and planned-order release sections of an MRP schedule. For parts produced in-house, lot sizes are the production quantities of batch sizes. For purchased parts, these are the quantities ordered from the supplier. Consider the following data relevant to an MRP lot-sizing problem: 4 50 Membersh X b Answered: X G The detern X 100% + # $25 $100 20.8% 5 Building a Better Re... 0 6 200 Get involved in hum... 7 125 8 100 Use the…Felix & Company reports the following information. Period 1 567698AWNH 2 3 4 10 Units Produced 0 Cost equation = 460 860 1,260 1,660 2,060 2,460 2,860 3,260 3,660 Total Costs $ 4,560 3,860 4,260 4,860 3,960 4,160 8,660 16,060 4,860 10,782 Use spreadsheet software to use ordinary least-squares regression to estimate the cost equation, including fixed and variable cost amounts. per unit
- Judd 57 Joel Gus Tim $3 2. 1 $5 $2 First film Second film Third film Fourth film Fifth film 1. 0. 0. 5. 2. 1 a. Within the dorm room, is Ux showing of a movie a public good? Why or why not? b. W itcosts S5 to rent a movic how many movies should the mommates rent to maximize tothl surplus? c. li they choose the optimal number from part (b)and then split the cost of renting the movies equally, how much surplus does.cach person obtain from wakhing the me d. s there any way tospl ost.tormsre that everyone benefits? What practical problems does this solution reise? Suppose they agmeinarancetochoxxe the efficient number and to split the cosr of the movies equally. When fudd is asked his wiling ness to pay, will he have an incentive to toll the Iruth? If so, why? f not. what will he he tempted (1అ) బ* E What does this example teach you abou the optimal provision of public goods? yol public gods?nity College | Pima x B Module 12 Practice Assignment 6 Question 1- Module 12 Practice x A ezto.mheducation.com/ext/map/index.html?_con=con&external_browser=D0&launchUrl=https%253A%252F%252Flms.mheducation.com%252Fmghmiddleware%252Fr ediStay v4 E New Scorpion O Redistay - (Unknown) U Ulitpro -New e Scorpion (UAT) 5) Springfield - Home inContact Dashboards RediStay v4 (UAT) -... lodule 12 Practice Assignment_Ch.17 i Saved 1 Challenge Problem 17-25 (Static) [LU 17-2 (2)] A delivered price (including attachments) of a crawler dozer tractor is $135,000 with a residual value of 35%. The useful life of the tractor is 7,700 hours eBook Print a. What is total amount of depreciation allowed? References Total amount b. What is the amount of depreciation per hour? (Round your answer to the nearest cent.) Amount of depreciation per hour1.What is the point at which an owner can begin to occupy a building or use it for its intended purpose? At the end of the warranty period After final completion When the payment bond is terminated After substantial completion 2.What is used to determine periodic payment amounts on unit price contracts? Submitted invoices, receipts, and timesheets plus the contractor's fee. A fixed, monthly installment negotiated at the start of the project. Schedule of Values and percentage completion on each pay item Unit prices originally bid and quantities measured.
- The management of Pearson Institute of Higher Education (PIHE) has decided to run a registrationpromotion to give students some discount on their fees. The promotion is as follows:• Complete Registration at least two weeks before resumption, 5% discount is given• Up to 70% payment and black south African, 5% discount is given• Complete payment onsite, 5% discount given 1.2 Draw a decision table to represent your decision tree 1.3 Represent your decision table in a structure Englishhari Salman bin abdulaziz University, Al Kharj College of Business Administration Management Department Management Science (MGT321) Name: University No.: Assignment 1 Exercisel (a): What do you mean by Linear Programming Problem? Write the general form of an LPP. (b): Cycle Trends is introducing two new lightweight bicycle frames, the Deluxe and the Professional, to be made from aluminum and steel alloys. The anticipated unit profits are SAR 30 for the Deluxe and SAR 35 for the Professional. The number of pounds of each alloy needed per frame is summarized in the following table. A supplier delivers 90 pounds of the aluminum alloy and 100 pounds of the steel alloy weekly. How many Deluxe and Professional frames should Cycle Trends produce each week? Table: Pounds of each alloy needed per frame Frame Aluminum Alloy Steel Alloy Deluxe 4 3 Professional 3 Formulate the above problem as linear programming problem. Exercise2: 4In July 2021, Matthew Olsen, Head of Finance of XYZ Management Consulting had just set aside an amount of R300,000.00 to cover the renovation of all the organisation's offices. The money will be held in a savings account at a local bank that pays 6.50% interest per annum. Half of the money will be drawn in August and the rest when the job is completed in 90 days. Q.4.2 Matthew had to meet with all the other Heads of Departments (i.e., Marketing and Human Resources) to discuss the plan in the above scenario. Identify and explain the type of 'formal organisational communication flow' applicable when Matthew met with the rest of the team.