RIBNA has estimated 200 m³ concrete and 800 dowels to complete a concrete paving project. 60 work hours is estimated to make dowel baskets and anchor them to the base course. A slipform paver, in 40 work hours, spreads, consolidates, and finishes the concrete slab. On a study date, 600 dowels in 45 work hours and 120 m³ concrete in 30 work hours are used.
RIBNA has estimated 200 m³ concrete and 800 dowels to complete a concrete paving project. 60 work hours is estimated to make dowel baskets and anchor them to the base course. A slipform paver, in 40 work hours, spreads, consolidates, and finishes the concrete slab. On a study date, 600 dowels in 45 work hours and 120 m³ concrete in 30 work hours are used.
Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter11: Pricing Concrete Work
Section: Chapter Questions
Problem 9RQ: Calculate the cost per cubic yard to place concrete using each of the alternatives described. The...
Related questions
Question
9
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,