35. are used to modify the contract or bidding documents (i, e., plans specifications) after the plans have been issued and prior to the bid opening. 36. The is a start-up meeting for the project; an opportunity for owner, engineer, contractor, and subs to address anything that's important to the project such as the schedule or the contract documents. 37. A portion of money held back from progress payments to allow a cushion for the owner if billings exceed the value of the project is referred to as

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter8: Pricing Generally
Section: Chapter Questions
Problem 5RQ
icon
Related questions
Question
A. Addenda
C. Cost plus
B. Lump sum
G. Escape clause H. Liquidated Damages 1. Alternates
N. Retainage
D. Field Change E. Latent Defect F. Cardinal Change
K. Bid Options
P. Precon. Meeting
L. Value Engineering
J. Unit Price
O. General conditions
M. Fixed fee
29. A change order that is of such magnitude that the original scope of the project is altered to an extent that
constitutes a new contract is known as a
30. The underlying purpose of the
the rules under which the project will be built.
or boilerplate of a construction contract is to outline
31. The exact bid amount is paid in one lump sum payment after completion of the project in a
contract.
32. The contractor is reimbursed for actual expenses plus a percentage markup in a
contract.
33. The actual number of units put in place is measured, then the unit price is multiplied by the number of units
installed in a
contract.
34. A
study examines the functions of goods and services for the purpose of
achieving necessary functions at the lowest overall cost, consistent with achieving essential characteristics,
35.
are used to modify the contract or bidding documents (i, e., plans specifications) after
the plans have been issued and prior to the bid opening.
is a start-up meeting for the project; an opportunity for owner, engineer, contractor,
and subs to address anything that's important to the project such as the schedule or the contract documents.
36. The
37. A portion of money held back from progress payments to allow a cushion for the owner if billings exceed the value
of the project is referred to as
Transcribed Image Text:A. Addenda C. Cost plus B. Lump sum G. Escape clause H. Liquidated Damages 1. Alternates N. Retainage D. Field Change E. Latent Defect F. Cardinal Change K. Bid Options P. Precon. Meeting L. Value Engineering J. Unit Price O. General conditions M. Fixed fee 29. A change order that is of such magnitude that the original scope of the project is altered to an extent that constitutes a new contract is known as a 30. The underlying purpose of the the rules under which the project will be built. or boilerplate of a construction contract is to outline 31. The exact bid amount is paid in one lump sum payment after completion of the project in a contract. 32. The contractor is reimbursed for actual expenses plus a percentage markup in a contract. 33. The actual number of units put in place is measured, then the unit price is multiplied by the number of units installed in a contract. 34. A study examines the functions of goods and services for the purpose of achieving necessary functions at the lowest overall cost, consistent with achieving essential characteristics, 35. are used to modify the contract or bidding documents (i, e., plans specifications) after the plans have been issued and prior to the bid opening. is a start-up meeting for the project; an opportunity for owner, engineer, contractor, and subs to address anything that's important to the project such as the schedule or the contract documents. 36. The 37. A portion of money held back from progress payments to allow a cushion for the owner if billings exceed the value of the project is referred to as
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Bid package
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,